01 35 25 Fire Prevention - 8-3-2022 (MC).pdf

PDF 323 KB Posted

Attached to
Bricker Replace Fire Alarm and Notification System Federal contract opportunity
Solicitation number
47PF0022R0063
Issued by
General Services Administration Public Buildings Service Region 5

About this file

This document provides specifications for a fire alarm system replacement project. The General Services Administration (GSA) Region 5 is seeking a contractor to replace the fire alarm system in the Bricker Federal Building and Garage in Columbus, Ohio with a performance period of 357 calendar days for the building and 140 calendar days for the garage upon receipt of notice to proceed. Contractors must demonstrate experience with fire alarm projects in large office buildings and parking garages. The solicitation number is 47PF0022R0063 and proposals will be evaluated based on past experience, key personnel, project management plan, and past performance with technical factors weighted more than price. The estimated construction cost range is between $1,000,000 and $5,000,000 and it is a total small business set-aside. The anticipated award date is September 2022.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRE ALARM AND NOTIFICATION SYSTEM REPLACEMENT

BRICKER U.S. FEDERAL BUILDING AND GARAGE 100% CONSTRUCTION DOCUMENTS

BID AMENDMENT 2 AUGUST 3, 2022

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 1

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice

Properly destroy documents when no longer needed

SECTION 01 35 25 – FIRE PREVENTION & PROTECTION IN CONSTRUCTION,

ALTERATION, AND DEMOLITION PROJECTS

1. GENERAL

1.1. Scope

1.1.1. This specification shall apply to structures in the course of construction, alteration, or demolition activities.

1.2. Purpose

1.2.1. This specification is intended to prescribe minimum safeguards for construction, alteration, and demolition operations in order to provide reasonable safety to life and property from fire during such operations.

1.2.2. This specification provides measures for preventing or minimizing fire damage during construction, alteration, and demolition operations.

1.2.3. This specification is intended to provide guidelines for the Contractor’s response to fire related incidents and efforts to mitigate effects and losses from the same.

1.2.4. This specification provides requirements for reporting thresholds following fire related incidents.

1.3. Application

1.3.1. A fire safety program shall be included in all construction, alteration, or demolition projects.

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 2

Do not remove this notice

Properly destroy documents when no longer needed

1.3.2. The GSA Regional Fire Protection Engineer shall be consulted for guidance in application of this specification.

1.3.3. The Authority Having Jurisdiction (AHJ) for all technical aspects of this specification and application thereof shall be the GSA Regional Fire Protection Engineer.

1.3.3.1. In case of a conflict between applicable regulations, the more stringent requirements shall apply. Any guidance in regard to interpretation of codes and standards shall be sought from the GSA Regional Fire Protection Engineer.

1.3.3.2. The GSA Regional Fire Protection Engineer shall make the final decision on the proper compliance with this specification in case of conflicts.

1.3.4. GSA reserves the right to administer and enforce this program, even if the building is entirely under the jurisdiction of the contractor.

1.4. Definitions

1.4.1. Fire Watch: The individual(s) prepared for first aid firefighting who proactively observe(s) for the start of fire resulting from the effects of hot work. Such work must be the sole duty of this individual.

1.4.2. Fire Patrol: The individual(s) who regularly walk through a space prepared for detecting the presence of a fire and providing notification to both building occupants and the fire department due to an absent or impaired fire protection system

1.5. References

1.5.1. Applicable Publications: Perform construction, alteration, and demolition operations in a manner conforming to the requirements of the latest

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 3

Do not remove this notice

Properly destroy documents when no longer needed edition as of [month-day-year] for this project of the following publications including all amendments to these publications:

1.5.2. International Code Council (ICC):

1.5.2.1. International Building Code

1.5.2.2. International Fire Code

1.5.2.3. International Mechanical Code

1.5.3. National Fire Protection Association (NFPA):

1.5.3.1. 10 Standard for Portable Fire Extinguishers

1.5.3.2. [13 Standard for the Installation of Sprinkler Systems]

1.5.3.3. [13D Standard for the Installation of Sprinkler Systems in One and Two-Family Dwellings and Manufactured Homes]

1.5.3.4. [14 Standard for the Installation of Standpipe and Hose Systems]

1.5.3.5. [25 Standard for the Inspection, Testing, and Maintenance of Water Based Fire Protection Systems]

1.5.3.6. [30 Flammable and Combustible Liquids Code]

1.5.3.7. [51B Standard for Fire Prevention During Welding, Cutting, and Other Hot Work]

1.5.3.8. [54 National Fuel Gas Code]

1.5.3.9. [58 Liquefied Petroleum Gas Code]

1.5.3.10. 70 National Electrical Code (NEC)

1.5.3.11. 72 National Fire Alarm Code

1.5.3.12. 80 Standard for Fire Doors and Fire Windows

1.5.3.13. 101 Life Safety Code

1.5.3.14. 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations

1.5.3.15. 1620 Standard for Pre-Incident Planning

1.5.3.16. [1963 Standard for Fire Hose Connections]

1.5.4. Code of Federal Regulations

1.5.4.1. 29 CFR, Part 1910: Occupational Safety and Health

Administration (OSHA) General Industry and Health Standards

1.5.4.2. 29 CFR, Part 1926: OSHA Construction Industry Standards

1.5.5. U. S. General Services Administration

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 4

Do not remove this notice

Properly destroy documents when no longer needed

1.5.5.1. PBS-P100 Facilities Standards for the Public Buildings Service http://www.gsa.gov

1.6. Acquisition of Publications

1.6.1. Referenced CFR publications may be purchased from the Superintendent of Documents, U.S. Government Printing Office, U.S. Government Bookstore (1-866-512-1800 or www.gpoaccess.gov).

1.6.2. National Fire Protection Association publications are available from the

NFPA, 02269 (1-800-344-3555 or www.nfpa.org).

1.6.3. International Code Council Publications are available through the ICC

Store (1-800-786-4452 or www.iccsafe.org).

1.7. Equivalent Technologies

1.7.1. Nothing in this specification is intended to prevent the use of systems, methods, or devices of equivalent or superior quality, strength, fire resistance, effectiveness, durability, and safety over those prescribed in this specification.

1.7.2. Technical documentation shall be submitted to the GSA Regional Fire

Protection Engineer to determine equivalency. The system, method, or device shall be approved for the intended purpose by the GSA Regional Fire Protection Engineer prior to being utilized.

1.7.3. Systems, methods, or devices that are submitted for review after construction, alteration, or demolition starts, or after the systems, methods, or devices have been used, may be summarily rejected due to contractual considerations and/or technical considerations.

2. CONTRACTOR RESPONSIBILITIES

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 5

Do not remove this notice

Properly destroy documents when no longer needed

2.1. The Contractor shall assume full responsibility for compliance with all applicable codes, standards, and regulations pertaining to the fire & life safety of persons during execution of the work.

2.2. The Contractor shall be responsible for and liable for all damages both direct and indirect resulting from the Contractor’s personnel or subcontractor’s personnel damaging existing fire protection and life safety systems and equipment during any construction, alteration, or demolition.

2.3. When such damage occurs, the Contractor is responsible for:

a) Immediately notifying the GSA Property Manager & the Contracting Officer,

b) Immediately repairing the damage, and

c) Remaining on site until all damage has been repaired.

2.4. The Contractor shall hold the government harmless for any action or omission on the Contractor's part, or that of the Contractor's employees or subcontractors, that results in illness, injury, or death

2.5. Prior to commencing construction, alteration, or demolition operations the contractor shall appoint an on-site fire safety program manager.

2.5.1. For projects where the government retains the services of a construction manager or on-site technical representative, the fire safety program manager shall be from that oversight organization.

2.5.2. The fire safety program manager shall have knowledge of the applicable fire protection standards, available fire protection systems, and fire inspection procedures

2.5.3. The fire safety program manager shall assure that all requirements of this specification and of referenced codes and standards are being complied with throughout.

2.5.4. The fire safety program manager shall also have the authority to enforce provisions of this specification to assure compliance.

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 6

2.6. The Contractor shall develop and maintain a written fire safety program in compliance with NFPA 241, NFPA 51B, and the International Fire Code, Chapter 33.

2.6.1. A copy of the contractor’s site specific fire safety program shall be provided to the Contracting Officer at least 15 days prior to the beginning of construction, alteration, or demolition activities.

2.6.2. A copy of the GSA Regional Fire Protection Engineer approved Site

Specific Fire Safety Program shall be maintained onsite and be filed with the fire safety program manager and GSA Property management office.

2.7. Pre-Fire Response Plan with FD: The local responding fire department should be actively involved in all preplanning activities in compliance with NFPA 1620 (Standard for Pre-Incident Planning). The items noted below must be included.

2.7.1. Site Plan(s)

2.7.1.1. Location name

2.7.1.2. Address

2.7.1.3. Construction Type

2.7.1.4. Dimensions (Length x Width x Height, in feet)

2.7.1.5. Number of Stories (including below grade levels)

2.7.1.6. FD Access Roadways Gates

2.7.1.7. Hydrants, FDCs, and Firefighting Equipment

2.7.1.8. FD Lockboxes

2.7.1.9. Primary/Secondary Entrances

2.7.1.10. Exposures to the Building

2.7.2. Floor Plan(s)

2.7.2.1. Stairs for Roof Access and Below Grade Access

2.7.2.2. Show Egress from Construction Area

2.7.2.3. Show Egress From Building

2.7.2.4. Fire Protection Systems Controls

2.7.2.5. Sprinklers/standpipe

2.7.2.6. Fire Command Center /Main FACU

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 7

Do not remove this notice

Properly destroy documents when no longer needed

2.7.2.7. Alternative Power

2.7.2.8. Special Hazards

2.7.3. In lieu of Local Responding Fire Department Participation, the Contractor may provide the above noted information and place into a binder in the Fire Command Center. Such documents shall be approved by the GSA Regional Fire Protection Engineer.

2.8. The Contractor shall provide training for all on site contractor personnel on fire prevention and protection procedures.

2.9. The Contractor shall provide for all equipment and supplies as required by this specification.

2.10. The Contractor shall protect existing fire protection equipment and systems from damage incurred by their construction, demolition, and alteration activities.

2.11. All existing fire protection systems and equipment shall be maintained in continuous service.

2.12. The Contractor shall take all necessary precautions to prevent injury to the public, occupants, or damage to property of others.

2.12.1. The public and occupants includes all persons not employed by the

Contractor or a subcontractor.

2.12.2. Where practical, the work area shall be fenced, barricaded, or otherwise blocked off from the public or occupants to prevent unauthorized entry into the work area.

2.12.3. Care must be taken not to eliminate the means of egress for occupants of occupied areas of the building.

2.13. Fire Safety Program: The Contractor shall submit, for approval by the GSA Regional Fire Protection Engineer, copies of the site specific fire safety

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 8

Do not remove this notice

Properly destroy documents when no longer needed program, as applicable to the scope of work, which may include, but not limited to the following:

2.13.1. Administration

2.13.1.1. Completed Scope Review Checklist in Appendix A

2.13.1.2. Pre-Fire Response Plan

2.13.1.3. Key Personnel Contact Info

2.13.2. Equipment and Supplies Provided by Contractor

2.13.2.1. Include a listing of all fire protection related equipment and supplies proposed to be provided by the Contractor. This may include Portable Fire Extinguishers, Mobile Phone, Portable Two- Way Radio, Temporary Lighting, and any other necessary equipment and/or supplies

2.13.3. Any Phased Construction Proposed

2.13.3.1. Provide details of phasing, including project phase areas and impact on acceptance testing.

2.13.4. Fire Protection Systems Inspection, Testing, and Maintenance

2.13.4.1. Provide details for ITM activities for existing, temporary, and new fire protection systems. This is intended for projects of a duration that exceeds the periodic frequencies established by NFPA 25 and NFPA 72.

2.13.5. Temporary Facilities

2.13.5.1. Construction Egress during new Construction

2.13.5.2. Temporary Construction Separation Walls

2.13.5.3. Temporary Offices & Enclosures

2.13.5.4. Temporary Electrical Service

2.13.5.5. Temporary Material and Equipment Storage

2.13.5.6. Temporary Fire Protection

2.13.5.6.1. Fire Patrol

2.13.5.6.2. Water Based Fire Protection Systems during Construction

2.13.5.6.2.1. Standpipes

2.13.5.6.2.2. Sprinklers

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 9

Do not remove this notice

Properly destroy documents when no longer needed

2.13.6. Utility Use & Isolation

2.13.6.1. Electrical, Lighting, & Temporary Wiring

2.13.6.2. Fuel Gas

2.13.6.3. Domestic Water

2.13.6.4. Fire Protection Water

2.13.7. Impairment Procedures

2.13.7.1. Planned impairments

2.13.7.2. Emergency Impairments

2.13.7.2.1. Spill Response Equipment

2.13.8. Interim Life Safety Measures

2.13.9. General Fire Prevention

2.13.9.1. Cooking

2.13.9.2. Temporary Heating Equipment

2.13.9.3. Smoking Ban and Provisions for Smokers

2.13.9.4. Storage

2.13.9.5. Housekeeping

2.13.9.6. Waste Disposal

2.13.10. Target Hazard Operations

2.13.10.1. Hot Work Procedures

2.13.10.2. Flammable and Combustible Liquids

2.13.10.3. Flammable Gases

2.13.10.4. Electric Arc Welding & Cutting

2.13.10.5. Gas Welding & Cutting

2.13.10.6. Motorized Construction Equipment

2.13.10.7. Roofing Operations

2.13.10.8. Explosive Materials

2.13.11. Emergency Response

2.13.11.1. Fire Alarm Reporting

2.13.11.1.1. Notification Inside Construction Zone

2.13.11.1.2. Notification With Facility Outside of Construction Zone

2.13.11.2. First Aid Fire Fighting & Required Equipment

2.13.11.3. Evacuation & Personnel Accountability

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 10

Do not remove this notice

2.13.11.4. Post Incident Notification & Documentation

2.14. Removal Provision – See FAR and other Division 1 requirements for removal of non-compliant personnel.

2.15. No time extension or additional payment- See other Division 1 requirements for stop work orders.

2.16. Emergency Suspension of Work:

2.16.1. Immediate Correction Required: When the Contractor is notified by the

Contracting Officer, or the Contracting Officer’s Representative (COR), of non-compliance with the fire safety provisions of the Contract, the Contractor shall immediately, unless otherwise instructed, correct the unsafe or unhealthy condition.

2.16.2. Stop Work Order: If the Contractor fails to comply promptly, all or part of the Work will be stopped by notice from the Contracting Officer or the Contracting Officer’s Representative (COR)

2.16.3. Resuming Work: When satisfactory corrective action has been taken by the Contractor, as determined by the Contracting Officer or the Contracting Officer’s Representative (COR), work shall resume.

2.17. Fire and Explosion Reports

2.17.1. Accident Reporting: Any fire protection related accident or occupational illness which will require reporting to the Contractor's insurance carrier(s) and/or to the Occupational Safety and Health Administration (OSHA) must be reported to the Regional Fire Protection and Safety Team no later than 48 hours following the incident. GSA Form 3620, "Report of Injury/Illness or Accident," shall be used for this requirement.

2.17.2. A copy of each loss report that the Contractor or Subcontractors submits to their insurance carriers as a result of a fire or explosion shall be submitted to the Contracting Officer Representative (COR) within seven calendar days after the date of the incident. It is recommended to

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 11

Do not remove this notice

Properly destroy documents when no longer needed include the URL for the Insurer’s loss reporting function of their website or a blank copy of their loss report form with the fire protection plan in order to facilitate timely reporting.

2.17.3. Notifications

2.17.3.1. In the event a fire or explosion results in the injury of any individual(s) or the death of any individual(s), the Contractor, shall verbally notify the Contracting Officer immediately.

2.17.3.2. If the incident results in an evacuation of the facility for 1 hour or longer or if the building is deemed unsafe or uninhabitable by local authorities after an incident, the Contractor shall verbally notify the Contracting Officer immediately.

2.17.3.3. A written report shall be forwarded to the GSA Regional Fire

Protection Engineer no later than 48 hours following the incident.

2.17.4. Cooperation

2.17.4.1. In the event a fire or explosion takes place in a construction, alteration, or demolition site, the Contractor shall cooperate with Federal, State, and Local fire investigators to determine the cause.

2.17.4.2. If the incident triggers a Federal Board of Inquiry, the Contractor shall provide all information and contractor personnel required by the Board.

3. EXECUTION

3.1. Basic Requirements

3.1.1. Minimize Disruptions

3.1.1.1. Disruptions to fire protection systems and equipment shall be kept to a minimum or avoided.

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 12

3.1.1.2. Delineate phasing of construction to ensure that installations of new systems are expedited, and existing systems are kept in service until the replacement system is operational.

3.1.1.3. See GSA Facilities Standards for the Public Buildings Service, PBS – P100 for further information.

3.1.2. All existing fire protection systems and equipment shall be maintained in continuous service.

3.1.3. Pre-planned and Emergency impairments involving disruptions to the fire alarm, sprinkler, standpipe or similar fire protection systems shall comply with this specification.

3.1.4. Any pre-planned impairments that will involve disruptions for phased work shall have a procedure documented and approved in writing by the Contracting Officer’s Representative (COR) and GSA regional fire protection engineer.

3.1.5. Coordinate all necessary system shutdowns with the GSA property manager.

3.1.5.1. Contractor is responsible for costs of shutdowns including assistance by the building O&M service contractor.

3.1.5.1.1. O&M service contractor is to be hired as a sub-contractor to provide assistance and to perform any building system shutdowns.

3.1.5.1.2. O&M service contractor shall be contacted through GSA property Manager.

3.1.5.2. Contractor is responsible for the cost of providing fire patrols.

3.1.6. Emergency impairments are particularly critical In particular, unwanted sprinkler releases from physical damage present a high loss potential due

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 13

Do not remove this notice

Properly destroy documents when no longer needed to water damage of room contents, including electronics. Additionally, mold growth from delayed or improper clean up can result. Contractors shall have a spill response kit with a floor plan showing the location of valve(s) necessary for system isolation, shop vacuums, absorbent materials (boom, socks, pads, etc.), mops, and squeegees at a minimum.

3.2. Fire Alarm Impairments

3.2.1. Maintain existing fire alarm equipment outside of any area(s) under construction fully operational.

3.2.1.1. As necessary for completion of modifications, the existing fire alarm system and associated equipment can be taken out of service only during construction periods in which the system is being modified and the Contractor is at the work-site.

3.2.1.2. Prior to leaving the work-site each day the Contractor shall restore the fire alarm system to service. Work shall be completed in such a manner that allows for the return to service of the fire alarm system at the end of the work shift.

3.2.1.3. Existing fire alarm system and associated equipment shall not be removed from the construction area nor shut off for more than one shift at a time.

3.2.1.4. If it’s not practical to isolate the fire alarm system within the project area from adjacent non-work areas, all areas outside of the construction area shall also have the existing fire alarm system restored to service prior to leaving the project work area at the end of each work shift.

3.2.1.5. If the affected portion of the system remains out of service, a fire patrol shall be established at the contractor’s expense until all systems are properly restored back in service.

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 14

Do not remove this notice

Properly destroy documents when no longer needed

3.3. Water Based Fire Protection (Standpipe/Fire Pump/Sprinkler) System Impairments

3.3.1. Maintain existing fire protection systems outside of any area(s) under construction fully operational.

3.3.1.1. As necessary for completion of modifications, the existing fire protection sprinkler system and associated equipment can be taken out of service only during construction periods in which the system is being modified and the Contractor is at the work-site.

3.3.1.2. Prior to leaving the project work area at the end of each work shift, the contractor shall ensure the sprinkler system is properly restored back in service. Work shall be completed in such a manner that allows for the return to service of all sprinklers at the end of the work shift.

3.3.1.3. Sprinklers and standpipes shall not be removed from the construction area nor shut off for more than one work shift (i.e., maximum 12 hours) at a time.

3.3.1.4. If it’s not practical to isolate the sprinkler system within the project area from adjacent non-work areas, all areas outside of the construction area shall also have the existing fire protection sprinkler system restored to service prior to leaving the project work area at the end of each work shift

3.3.1.5. If the affected portion of the system remains out of service, a fire patrol shall be established at the contractor’s expense until all systems are properly restored back in service.

3.3.2. Hot work shall be prohibited during sprinkler impairments.

3.3.3. The contractor shall also conduct and document any required inspections or tests to verify that the affected system is operational in accordance with NFPA 25 (Inspection, Testing, and Maintenance of Water Based Fire

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 15

Do not remove this notice

Properly destroy documents when no longer needed

Protection Systems – latest edition), Chapter 15 “Impairments” requirements.

3.4. Preserve Existing systems

3.4.1. Removal of Suspended Ceilings in building areas Protected with Pendent

Type Sprinklers

3.4.1.1. There may be fire risks associated with the removal of suspended ceilings in projects where the space is protected with pendent type sprinklers such that interim risk mitigation strategies will need to be developed.

3.4.1.2. An approved interim risk mitigation strategy must be approved by the regional fire protection engineer. Interim risk mitigation strategies might include, but are not limited to:

3.4.1.2.1. Initiate an approved fire patrol; or,

3.4.1.2.2. Installation of temporary walls having a 1-hour fire resistance rating to separate the occupied portion of the building from the portion of the building under renovation; or,

3.4.1.2.3. Modifying the existing sprinkler system by installing new temporary upright sprinklers that provide the required protection for the space under renovation; or,

3.4.1.2.3.1. The upright sprinklers shall be installed within 12 inches of the deck above and obstruction sprinklers shall be provided where required by NFPA 13.

3.4.1.2.3.2. These temporary upright sprinklers shall remain in service until the new sprinkler system for the project is installed, tested, and accepted by the government

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 16

Do not remove this notice

Properly destroy documents when no longer needed

3.4.1.2.4. Other solutions approved by the GSA Regional Fire

Protection Engineer that eliminate potential ignition sources and limit the amount of fuel available to the fire.

3.5. Protection of Personnel: The Contractor shall take all necessary precautions to prevent injury to the public, occupants, or damage to property of others.

3.5.1. The public and occupants include all persons not employed by the Contractor or a subcontractor.

3.5.2. Where practical, the work area shall be fenced, barricaded, or otherwise blocked off from the public or occupants to prevent unauthorized entry into the work area.

3.5.3. Care must be taken not to eliminate the means of egress for occupants of occupied areas of the building.

3.6. Protection of Existing Structure

3.6.1. Temporary storage of equipment to be installed, combustible construction materials, or combustible packing materials shall not be permitted in unprotected structures under construction or alteration unless authorized by the GSA Regional Fire Protection Engineer.

3.6.2. Storage shall not be permitted in unprotected structures until protection is in service.

3.6.3. Yard storage of equipment to be installed or combustible construction materials shall not be stored closer than 9 m (30 ft.) from the structure under construction or alteration.

3.7. The Contractor shall perform roofing operations as required in NFPA 241, chapter 9.

3.8. The contractor shall perform demolition operations as required in NFPA 241, chapter 10.

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 17

Do not remove this notice

3.9. Fire Watches and Patrols

3.9.1. Where a Fire Watch or Fire Patrol is required by GSA standards or codes referenced therein, such personnel shall be trained and have documentation of hands on fire extinguisher training complying with 29 CFR 1910 within the previous twelve months

3.9.2. The sole duty of Fire Watch or Fire Patrol personnel shall be to perform constant patrols and watch for the occurrence of fire.

3.9.3. The Fire Watch or Fire Patrol shall be provided with at least one approved means for notification of the fire department.

3.9.4. All Fire Watch or Fire Patrol personnel shall have a direct means of communication with the project superintendent

3.9.5. Fire Watch or Fire Patrol shall be trained on how to sound the alarm within the building during any impairment and to independently notify the public fire department of a fire emergency within the building.

3.10. Submittals

3.10.1. Completed Job Hazard Analysis for Proposed Scope Checklist

(Annex A)

3.10.2. Site Specific Pre-Fire Response Plans

3.10.2.1. Site Plan(s)

3.10.2.2. Floor Plan(s)

3.10.3. Site Specific Fire Prevention and Protection Program

3.11. Conduct Employee Training

3.11.1. The Contractor shall provide training to all of their personnel working on-site and any subcontractors working under their contract.

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 18

Do not remove this notice

3.11.2. The Contractor shall maintain documentation of such training.

3.12. Program Oversight and Review

3.12.1. The Fire Safety Program Manager shall conduct regular oversight to ensure compliance with the requirements of the program.

3.12.2. The Contractor shall review the site specific Fire Safety Program annually

APPENDIX A follows

APPENDIX A

Fire Prevention & Prot. in Construction, Alt., and Demo. 01 35 25 - 19

END OF SECTION 01 35 25