This document is a Participants' Guide for the Project Definition Rating Index (PDRI) project review discussion and scoring session for the General Services Administration (GSA) Public Buildings Service.
The guide outlines the purpose and benefits of using the PDRI tool to assess the definition and risks of a project in the early planning and design phases. It provides detailed instructions and prompts for the project team to evaluate 38 elements across 3 main sections: Basis of Project Decision, Basis of Design, and Execution Approach. The elements cover critical aspects such as business strategy, owner policies/standards, project requirements, site information, building programming, project scope parameters, procurement strategy, deliverables, and project controls. The guide explains how to score each element and document needed actions and identified risks. The goal is to help the project team thoroughly understand the project's scope definition and risks to enable successful project delivery.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PDRI
Project Review
Discussion & Scoring Session
PARTICIPANTS’
GUIDE
General Services Administration Public Buildings Service
Office of Project Delivery (OPD) Center for Construction Excellence
December 2021
PDRI Project Review Discussion & Scoring Session PARTICIPANTS’ GUIDE
CONTENTS:
1. Introduction 3
2. Your PDRI Session 6 Section I 10 Section II 27 Section III 53
3. Conclude PDRI Session 70
References 71
Appendix 72
1. INTRODUCTION:
Why do a PDRI? A project gets “defined” during planning and early design phases.
Periodic assessment of its definition can identify risks to its successful delivery. As we define a project, it gets a trajectory. We have many project delivery trajectories (Capital;
Small; Site & Design Funding, Prospectus Development Study then Construction Funding;
Site, Design, Construction funding all at once, etc.).
Knowing its trajectory informs us of the typical risks a project must manage during its delivery. This Project Definition Rating Index (PDRI) tool, helps us identify project risks during planning and early design. Ensuring we define our scope accurately is good risk management. We hold PDRI sessions in the early phases of a project when influence is high and costs are low, (see Figure below).
FIGURE: Project Delivery: Influence and Expenditures Relation
What is the PDRI? The PDRI is both a repeated process and a product. Its process is to convene the delivery team for facilitated discussions to ensure best practice elements of well planned projects are accounted for in our project, and if not, to list on the projects Risk Register any risks caused by insufficient inclusion or completeness of these best practice elements. Its product is the project's initial Risk Register, and the team’s action list of needed work to improve the project’s definition. A score is also produced, feedback, which can be used to compare to industry best practice ranges for projects at similar stages of development, and to compare to a future PDRI discussion to verify improvement of the project’s planning, and readiness for its next stage of development.
How does it help us? The PDRI helps teams reveal issues that might have been accidentally overlooked in the normal course of work. It is a check against industry best practices to help projects be, and stay, on a good course, and to prevent risks from becoming hidden from view. It is a form of scope control in our program’s overall Risk Management efforts.
The PDRI helps teams reveal issues that might have been accidentally overlooked in the normal course of work.
Since, as the adage goes, “hope is not a strategy to manage risks”, use of this tool enables methodical risk management. It engages teams to decide how to handle identified risks, and document their decisions. Risk must be handled by: accepting, managing, transferring, or mitigating them. With proper use of the PDRI, project risks will not arise as a surprise. Limiting surprises is an aspect of good project management.
The PDRI is organized into 3 main sections. Each section has elements to be evaluated, and scored. An excel workbook is used to capture scores and action items. Identified Risks are to be placed on a CII Risk Register form.
The PDRI as prepared by CII is necessarily generic because it was developed to serve a variety of owners who participate in CII.
This Participants’ Guide’s PDRI Discussion Prompts provide greater specificity to aspects that matter on GSA projects so our project teams can maximize its benefits as they prepare projects to move forward through our program’s key planning and conceptual design phases
CII found value in the use of the PDRI in early, or front end, planning. Here is their project life cycle diagram that identifies when front end planning is done:
FIGURE: CII Project Life Cycle
Here is a comparison of CII’s project development flow to ours.
FIGURE: GSA Process compared to CII
A key difference between CII’s generic tool, and our reality, is that we get funding earlier in a project’s development than other owners, and our clients contribute significant funding to our projects. For both of us, because our funds are provided by Congress, we have unique circumstances. Because of these reasons, and because we deliver space for client agencies, we obtain full project funding earlier than other CII owners.
2. Your PDRI SESSION Ready, set, go.
Let’s Begin.
The Elements with Discussion Prompts by Category by Section:
FIGURE: Teamwork
The following pages contain by section and category, the detailed descriptions for each element to score. These descriptions include lists of prompts to enable teams to evaluate the level of completeness and inclusion of regulatory necessary and best practice items in the project at the present stage at which the PDRI session is held. The lists of prompts for each element are not “all-inclusive”. Project Teams are encouraged to add prompts and raise points that will improve the quality of their assessment of an element’s, and ultimately the project’s readiness for its next phase, and for documenting the risks to address.
At the conclusion of each element’s discussion, you will score the element.
To come up with a score, individually have in your mind a score, and then discuss what you collectively believe the score to be. To help do this, ask yourselves this question: “How well defined is this element within our project?”
Below are some helpful hints, a graphic, and a Scoring an Element Guide Sheet (the one written on a board, or as a few printouts placed onto the table for sharing).
Evaluate the inclusion, completeness, and relevance of the elements’ prompts to your project. Determine the scoring range of the elements’ definition within your project.
FIGURE: Scoring Definitions
Scoring an Element Guide Sheet How complete is this element within our project?
What level of definition would I evaluate it to be?
How should we score it:?
Here is the index to use:
0 = Not applicable to the project
1 = Complete Definition.
Fully defined, fully documented accurately, no further front end planning work required
2 = Minor Gaps in Definition.
Almost fully defined, one or two minor issues, some inaccuracies in documentation
3 = Some Gaps in Definition.
Defined but not fully defined, no “showstoppers” but numerous minor issues that need to be completed
4 = Major Gaps in Definition.
Not well defined, need more work, discussion, and thought to the project’s requirements
5 = Poor Definition, not defined, need to put in more thought?
The scribe will mark your score on the Score Sheet.
Next, determine who needs to work on the missing parts discussed in your evaluation.
The scribe will write these into the Score Sheet workbook on the “for action” tab.
The scribe will also write down any risks identified for the Risk Register
Then, move to the next element.
Let’s get started.
SECTION I - BASIS OF PROJECT DECISION
GSA decided to do this project. The basis for this decision was the project achieves business objectives. A project team must understand a project’s business objectives, and align individual efforts to achieve them.
This section determines for the team how well, or how poorly, it is aligned, and how well, or poorly, the project aligns to its objectives.
Categories:
A - Business Strategy
B - GSA Policies, Guidance and Standards
C - Project Requirements
For these categories, and this section to get the most out of the discussion, if any of the related documents of the Capital Investment and Leasing Program’s call for work, (Project Data Sheet, Housing Plan, Prospectus, and any other backup documentation to be submitted as part of the CILP) are completed, or being drafted, it would be good for the team - in advance of conducting the session to be familiar with them - also, the Asset Manager should be present at the session since investing in the asset is a focus of our Office of Portfolio Management and Customer Engagement (PT). Their Active participation is essential for this section’s categories’ discussions.
Please remember at the conclusion of your discussion, score the element. The scribe will mark your score on the Score Sheet. Determine who needs to work on the missing parts discussed in your evaluation. The scribe will write these into the Score Sheet workbook on the “for action” tab. The scribe also will write down any risks identified for the Risk Register.
Category A. BUSINESS STRATEGY
Read this introductory statement that tells this category’s purpose, and risk management benefits - to frame the elements’ discussions:
Through the PBS, GSA is in the Real Estate business. We are the landlord for the civilian federal government. We acquire space through new construction and leasing. We act as a caretaker for federal properties. In conducting our business our primary strategy is to save taxpayer money through better management of Federal real estate. This includes construction, repairs, and alterations to buildings. In service to our mission to provide effective and sustainable workplace solutions for federal agencies at the best value for the American Taxpayer, we actively manage risks. Use of this PDRI tool in early planning and design helps us manage risks. To determine how well defined a project’s scope is as it relates to our business strategy, we examine the 8 elements of this category:
A1. Building Use Requirements
A2. Business Justification
A3. Business Plan
A4. Economic Analysis
A5. Facility Requirements
A6. Future Expansion/Alteration Considerations
A7. Site Selection Considerations
A8. Project Objectives Statement
Element A1. Building Use Requirement: What building type is needed? Since a building's use may include more than one function, such as a Federal Building & Courthouse, what is its primary purpose? Is it a stand-alone or combined use buildings? What other shared use spaces for tenants will be included, such as child care centers, or special use spaces, such as laboratories? Consider the primary use of your project’s building. Discuss whether all of the building's intended uses have been identified. Here are some prompts:
❑ Courthouse ❑ Laboratory ❑ Storage/Warehouse ❑ Data Center ❑ Office ❑ Land Port of Entry ❑ Other
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element A2. Business Justification: What are the driving forces for the project? What is needed the most by GSA? What is most expected of GSA? As you discuss it, the scribe will write down any needed items, and any harboring risks. Here are some prompts:
❑ Need date ❑ Market capacity ❑ Location ❑ Building image ❑ Use flexibility ❑ Customer need ❑ Security ❑ Other Building efficiency (efficient use of space) ❑ Support new business initiatives ❑ Facility replacement and consolidation ❑ Level of amenities/functional needs ❑ Functional obsolescence
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element A3. Business Plan: Does the project’s funding and approval strategy support the business justification for doing this project? Here are some prompts:
❑ Signed OA’s?
❑ Total Project Budget (ETPC) ❑ What is the impact on performance measures?
❑ Schedule milestones (including known deadlines)
❑ Project Delivery Method (PDM) ❑ Types and sources of project funds (BA51, 55, 54, 80) identified? secured?
❑ Related/resulting projects/phasing NOTE: If GSA has 3rd party agreements with the City, State or SHPO then additional steps are required (MOU/MOA, etc)
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element A4. Economic Analysis: Has an economic analysis been performed? (TAPS, Pro Forma, LCC)? Does it include the necessary items? Here are some prompts:
❑ Rental rate ❑ Intended design/service life ❑ Return on investment ❑ Tier analysis ❑ GSA’s appraised value from an independent appraisal ❑ Lease, Renovation and New Construction ❑ Long-term operating and maintenance costs, (Gvt-Owned space only) ❑ Analysis of capital and operating cost versus disposal or occupancy and profitability
NOTES:
● A description of other options which could also meet the user need should be defined. As an example, did we consider renovating existing space rather than building new space? A listing of current facilities that will be vacated due to the new project should be produced.
● TAPS analysis is not required for Limited Scope projects
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element A5. Facility Requirements: Has a housing plan been prepared? If not, at the macro level are requirements documented somewhere? Here are some prompts:
❑ Number of occupants ❑ Border Traffic Modeling (LPOE’s) ❑ Net and gross space requirements by area uses ❑ Facility Security Level ❑ Support infrastructure ( i.e. Mechanical plant, circulation, etc.)
❑ Tenant Improvement Requirements (i.e. telecommunications, Information technology, number of desks, number of workstations, on-site child care, etc.)
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element A6. Future Expansion / Alteration Considerations / Space Consolidation. Has the possibility of expansion and/or alteration and/or consolidation upon the site and/or within the building, been considered in the planning for the facility’s design? If applicable to your project, do you have any studies that examined all these kinds of alternatives? Here are some prompts:
❑ Future phasing plan ❑ Courts long range plan ❑ Land Port of Entry long range plans ❑ Flexibility for future uses.
❑ Workplace Strategy Session ❑ Adaptability to the observed and expected changes in climate (i.e site development and/or enclosure) ❑ Technologically advanced facility requirements ❑ Asset Management Plan (long range occupancy goals for the building in 10, 15, 20 years?
❑ Building Preservation Plan (Historic Preservation Requirements) ❑ Building Design Standards for the building to be altered ❑ Provisions for site space in case of possible future expansion / contraction ❑ Are departments or functional areas intended to “grow in place” / “reduce in place” / “relocate” during a future phase?
❑ If there will not be future expansion of the building, how will departments or areas expand?
❑ Are there any proposed future mission changes for Tenants?
❑ Are any functional areas more likely than others to move out of the building in the future to allow others to expand or move in?
❑ Building adaptability for multiple tenants requiring separate security controls to entry
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element A7. Site Selection Considerations: Have you taken into consideration existing buildings or properties, as well as new / different locations? Did you consider these criteria? Here are some prompts:
❑ CBD vs. non-CBD (EO12072 set policy for urban areas to give first consideration to locating Federal facilities in centralized community business areas, such as central business districts)
❑ Wildland Fire Classification/ Distance from Wildfire Zones ❑ Floodplain Classification (Pluvial, Fluvial and Coastal Surge) ❑ Seismic Zone Classification ❑ Archeological Findings ❑ Landslide Hazard Classification
❑ Site congestion/lay down space ❑ Labor relations ❑ Weather/Climate (Observed and expected changes in climatic trends including severe weather events) ❑ Available utilities or utilities that require relocation ❑ Existing facilities ❑ General geographic location ❑ Customer mission ❑ Underground contamination ❑ Consultation with Local Officials/Compatibility with Local Planning Goals ❑ Local Zoning and Design Guidelines ❑ Security Considerations ❑ Landscape Design Opportunities ❑ Symbolic and aesthetic ❑ Proximity to public transit ❑ Political issues/constraints ❑ Cost of Brownfield remediation ❑ Setback requirements ❑ Historic / Cultural designation and preservation ❑ Legal constraints (e.g. property liens) ❑ NEPA status ❑ Land availability and development costs ❑ Potential of Stranded or Impaired Site ❑ Customer need (e.g. SSA service location) ❑ Master Plan Considerations (Campus), Local Portfolio Plans ❑ Multiple Owners - properties / possibility of Condemnation
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element A8. Project Objective Statement: Are the project objectives clear, concise and measurable? Has the team aligned on the objectives and priorities? Does the team understand the project drivers? Is a priority order set for cost, schedule, and scope choices? Have options, like value-adding features, been considered? Do project objectives align with applicable management direction, project charters, and / or master plans? Here are some prompts:
❑ Prior to this PDRI, has the team verified the objectives are aligned within the CapPMP and Prospectus?
❑ What is the priority? (Cost, Schedule, Quality, Historic Preservation, Mission Continuity, Improved Energy Efficiencies, Tenant satisfaction, Proximity to Transit / Parking, etc.)
❑ What trade-offs exist?
❑ Is there stakeholder consensus?
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on
Category B. OWNER PHILOSOPHIES (or for us), GSA POLICIES, PROCEDURES, and STANDARDS
Read this introductory statement that tells this category’s purpose, and risk management benefits - to frame the elements’ discussions:
As owner, the GSA represents the US Federal Government, our People. So our philosophy is to enact good government for and by the people. What we do is governed by the will of the people as written into laws. This drives our policies, procedures, and standards. In support of it, we shape our policies and standards with the assistance of associations of related industries to our business, and with our industry partners who perform much of the work by contract for us. We implement policies and procedures and standards to follow the law, and use best practices and state of the art products of today to produce beautiful durable real estate. To determine how well defined a project’s scope is as it relates to our owner philosophy, we examine the 4 elements of this category:
B.1 Reliability Philosophy (policies & standards)
B.2 Maintenance Philosophy (policies & standards)
B.3 Operating Philosophy (policies & standards)
B.4 Design Philosophy (policies & standards)
Element B1. Reliability Philosophy = (GSA Policies & Standards): Have general design principles been considered - to achieve desired operating performance? Here are some prompts:
❑ During planning phases has building and operations staff represented reliability standards?
❑ Mission critical systems’ sensitivity to interruption, relocation, replication ❑ Critical systems surety approach (redundancy, islanding, flexibility or other methods for the continuity of water, sewer, power, security, communications, etc.)
❑ Expectations for continuity of occupancy/shelter in place/safe-haven i.e.
operations, access, lighting, thermal resilience, filtration, ventilation ❑ Architectural/structural/civil durability (per P100) ❑ Review previous Post Occupancy Lessons Learned ❑ Mechanical/electrical/plumbing reliability (per P100) ❑ Information Technology, Telecom and Data systems and components reliability and potential for planned obsolescence.
❑ Has a life cycle cost analysis been performed on the building systems (per P100 and P120)?
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element B2. Maintenance Philosophy = (GSA Policies & Standards): Is a list of general maintenance principles to meet building requirements developed / identified? Were frequencies of maintenance, Preventive versus Reactive maintenance, and other impacts to life cycle costs considered? Here are some prompts:
❑ Sustainable maintenance practices ❑ Daily occupancy loads ❑ Maintenance accessibility ❑ Energy conservation programs ❑ Durable materials & finishes ❏ Availability of parts for replacement (consider future owner impact of customized parts or features) ❑ O&M documents and guidance (Operational Excellence) ❑ Building Design Standards requirement ❑ Equipment monitoring requirements ❑ Operation of BAS system ❑ Maintenance of High Performing Building systems (i.e. on-site energy generation) ❑ Is building project using “Smart Building Strategies” or anticipating to be a “Smart
Building”?
❑ Maximum building occupancy requirements ❑ Has project team reviewed current FM guidance applicability?
❑ Reliability Centered Maintenance Program requirements (Preventative Maintenance and Monitoring Impacts from Extreme Weather and Climatic Change i.e. corrosion, scouring) ❑ Are the Office of Facilities Management policies in the project requirements ❏ Consider occupant satisfaction ❏ Complete electrical circuit designation and marking
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element B3. Operating Philosophy = (GSA Policies & Standards): Is a list of general maintenance principles to meet building requirements developed / identified? Here are some prompts:
❑ Operating schedule/hours ❑ Flexibility to change layout ❑ Co-location of tenants ❑ Other
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element B4. Design Philosophy= (GSA Policies & Standards): Are the Guiding Principles of Federal Architecture understood? Is the team committed to achieving them with this project? Here are some prompts:
❑ Design Excellence Guiding Principles for Building Design Adherence
● Will this project provide requisite and adequate facilities?
● Will it be in a distinguished architectural style and form?
● Will it reflect the dignity, enterprise, vigor, and stability of the American
National Government?
● Will it be a design that embodies the finest contemporary American architectural thought?
● Will it incorporate regional architectural traditions?
● Will it incorporate fine art of living American artists?
● Will it adhere to sound construction practice?
● Will it utilize materials, methods and equipment of proven dependability?
● Will it be economical to build, operate and maintain, and accessible to the handicapped?
● Will its design flow from the architectural profession to the Government?
❑ Design Excellence Guiding Principles for Site selection and Development Adherence:
● Will/was the choice and development of the site the first step of the design process?
● Will/was site chosen in cooperation with local agencies?
● Will/was attention paid to the general ensemble of streets and public places in which the Federal building will form a part, (was good urban design employed)?
● If feasible, will/was the building (be) located on the site to permit generous development of landscape?
❑ Has LEED level been determined? ❑ Has SITES level been determined?
❑ Has Security Level been determined per Interagency Security Committee (ISC) Criteria?
❑ Historic preservation considerations ❑ Agency Special Design Requirements ❑ Design for special functionality ❑ Compatibility with master plan ❑ Quality of life (Total Workplace solutions) ❑ Facilities durably fit for purpose over design life (Observed Weather and Expected Climate) ❑ Energy Independence & Security Act (EISA) energy usage requirements and stormwater management requirements (Section 438) ❑ Environmentally sustainable design (internal/external) ❑ Compatibility with Local Planning Initiatives/Collaborative Design
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on
Category C. PROJECT REQUIREMENTS
Read this introductory statement that tells this category’s purpose, and risk management benefits - to frame the elements’ discussions:
We spend a good amount of time working with our tenants to identify their facilities needs, and in keeping up with evolutions in Real Estate and Construction. We identify facilities projects that will provide new or revitalized space. When a decision is made to proceed with a project, the requirements get increasingly better defined, both the end result, the facility (spaces, functions, etc..), and its managerial requirements (budget, schedule, etc…). To determine how well defined a project’s scope is as it relates to these project requirements, we examine the 6 elements of this category:
C.1 Value-Analysis Process C.2 Project Design Criteria C.3 Evaluation of Existing Facilities C.4 Scope of Work Overview C.5 Project Schedule C.6 Project Cost Estimate
Element C1. Value-Analysis Process: A value analysis process is a prioritization of discretionary scope issues. In forming this project, have you looked at items that impact the economic viability [ROI, Pro Forma, etc.] of this investment of the tax payer’s dollars?
Items to be considered and evaluated are often interrelated, are you looking at their relationships? Here are some prompts:
❑ Discretionary scope issues ❑ Initial material costs vs durability ❑ General vs. custom build-out ❑ Life-cycle analysis of construction methods and structure
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element C2. Project Design Criteria: Project design criteria are the requirements and guidelines which govern the design of the project. To assure criteria is met and control scope, have you built into the project the mandatory selection boards, applicable design review processes to validate criteria are being met? Here are some prompts:
❑ P100 ❑ General Requirements:
● Historic Preservation
● Accessibility (ABBAS)
● Codes and Standards
● Energy Use Targets
● Total Building Commissioning
● Performance Requirements (Structural, Mechanical, Electrical, etc)
● Resilience - Management of Climate-related and Extreme Weather Related
Risks ❑ Feasibility Study reference criteria ❑ Owner’s Project Requirements ❑ Courts Design Guide
❑ USMS P64
❑ Design Guide for Operational Excellence
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element C3. Evaluation of Project Area and Existing Facilities : If existing facilities are available, has a condition assessment been performed to determine if they will meet project requirements? Is the area of the project suitable to the criteria the project will provide? Here are some prompts:
❑ Roads ❑ Retail ❑ Power ❑ Fitness ❑ Access ❑ Security ❑ Capacity ❑ Childcare ❑ Amenities ❑ Fire water ❑ Food service ❑ Mass Transit ❑ Parking areas ❑ Sanitary sewer ❑ Medical facilities ❑ Telecommunications ❑ ABAAS or local standards ❑ Waste treatment/disposal ❑ Utilities (i.e., potable water, gas, oil, etc.)
❑ Type and size of buildings/structures ❑ Storm water containment system/filtration ❑ Recreation facilities including public outdoor spaces ❑ Availability and condition of As-Built drawings (record documents) ❑ Condition assessment of existing facilities and infrastructure (BER) ❑ Specific facilities design guides, in compliance with agency design guides
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element C4. Scope of Work Overview: This is a complete narrative description of the project as delineated in multiple documents (Planning Studies, CapPMP and Professional Service Contracts). It is discipline-oriented and supports the development of the project schedule and project cost estimate. It sets the limits of work by each participant and generally articulates their financial, task, and contractual, responsibilities. It clearly states both assumptions and exclusions used to define the scope of work. How complete is it?
Here are some prompts:
❑ Were the most recent GSA Templates for key planning documents used?
❑ Has everyone read the planning studies that set the scope?
❑ Does everyone agree the scope is accurate?
❑ Are there major risks to the scope being maintained?
❑ Does anyone have any major concerns with it?
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element C5. Project Schedule: Ideally, the project master schedule should be developed by the project team (GSA, client agencies, A/E, and contractors). It should include milestones, standard scheduling practices, unusual schedule considerations. Here are some prompts:
❑ Were the most recent GSA Schedule Templates used to prepare it?
❑ Has relevant parties reviewed the schedule?
❑ Is there agreement with relevant parties that the schedule is realistic and achievable?
❑ Are there major risks to the schedule being maintained?
❑ Is the schedule’s Work Breakdown Structure detailed sufficiently?
❑ Are the primary phases’ durations reasonable?
❑ Does the schedule address the project scope based on the information that we know at this time?
❑ Does the schedule make sense?
❑ Is the schedule based on assumptions or previous experience?
❑ Do you have a low, medium, or high confidence factor in the schedule?
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element C6. Project Cost Estimate: The project cost estimate should address all costs necessary for completion of the project. Different estimating methods are done during different project phases. Here are some prompts for discussion and some items typically included items in a thorough cost estimate:
❑ Has the official Budget Estimate been reviewed and approved by Central Office’s Quality Assurance team?
❑ Is there an alignment between the estimate, scope of work and project schedule?
❑ Has the Delivery Method been chosen? If so, did estimate consider it?
❑ How thorough is the cost estimate?
For Feasibility Session ask these questions:
❑ Was most recent cost estimate done per P120?
❑ Is the estimate representative of the proposed housing plan?
❑ Are known constraints considered within the estimate?
❑ If estimate is prepared by the A/E was the latest Cost Estimating Workbook used?
For Concept Session ask these questions:
❑ Is the base design-to value equal to 90% of the budgeted Estimated Construction
Cost at Award (ECCA)? If not are there proposed design options to meet the 90% ceiling?
❑ Has a third party estimate been done?
❑ Has reconciliation between A/E and 3rd party estimate (CMa) been done?
❑ Was most recent cost estimate done per P120?
❑ Did the estimate submission include a:
o market study?
o life cycle cost analysis?
o cost risk analysis?
o separate Core & Shell, Tenant Improvement, and any other special cost categories?
❑ Has a Concept Phase Value Management workshop occurred?
❑ Does the estimate include:
Direct Construction costs o for required scope and conditions
Indirect Construction costs, such as:
o Design contingency o Home office overhead o Job site overhead o Profit / Commission o Bond costs o Taxes (special use / value added) if required o Phasing premium o Market escalation (to the midpoint of construction) o Construction contingency
Design and owner oversight o Architect / Engineer costs o Construction Administration / Management (CMa) costs o Commissioning (Cx) costs
Move and external Swing costs (if required) Furnishings, Fixtures, & Equipment (FFE) Costs (If required)
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on
Review of Section 1’s Results.
Good job! You have completed the first section, Basis of Decision.
Have the scribe read out what was recorded on your scoring sheet, the action list with the assigned individual, and the Risk Register - verify you have marked all things down.
Take a break and return to evaluate the project through Section 2, the Basis of Design.
SECTION II - BASIS OF DESIGN
GSA projects consist of space, site, and technical design elements that a project team must fully understand and evaluate. These form the basis for the design of the product the project will deliver.
This section determines for the team how well it understands the basis for design, and how well, or how poorly, the project’s basis for design aligns to its objectives.
Categories:
D - Site Information
E - Building Programming
F - Building/Project Design Parameters
G - Equipment
For these categories, and this section to get the most out of the discussion, if a new site is being acquired, the person leading the acquisition must share with the team - in advance of conducting the session, with ample time for reading them - the related documents of the acquisition, and must be present for the session. If a new site is not being acquired, the person(s) leading the programming must share with the team- in advance of conducting the session, with ample time for reading them - the related documents of the project applicable to these categories, and must be present at the session.
Please remember at the conclusion of your discussion, score the element. The scribe will mark your score on the Score Sheet. Determine who needs to work on the missing parts discussed in your evaluation. The scribe will write these into the Score Sheet workbook on the “for action” tab. The scribe also will write down any risks identified for the Risk
Category D. SITE INFORMATION
Read this introductory statement that tells this category’s purpose, and risk management benefits - to frame the elements’ discussions:
Since a facility gets located on land, geographic realities and government regulations influence how it can be set. In early, front end, planning we need to investigate the constraints and opportunities any given site posses. Real estate history teaches us that sites harbor many potential risks. Because we manage risks, it is critical that we thoroughly understand our project’s site, before moving too far forward too fast with project delivery. To determine how well defined a project’s scope is as it relates to the site, we examine the 8 elements of this category:
D.1 Site Layout D.2 Site Surveys D.3 Civil/Geotechnical Information D.4 Governing Regulatory Requirements D.5 Environmental Assessment D.6 Utility Sources with Supply Conditions D.7 Site Life Safety Considerations D.8 Special Water and Waste Treatment Requirements
Note: For any of these elements, if your project is a modernization or interiors only project that does not have any outdoor site work / landscaping, this applicable element may be skipped.
Element D1. Site Layout: For a new facility, has it been placed on a site? If yes, how well has it been placed on its site? If not, how will this project have its placement evaluated?
Several criteria should be considered. For an existing facility has it been evaluated for constraints its site layout may pose to doing the project to it, or in it? Here are some prompts:
❑ Construction access ❑ Historical/cultural significance ❑ Trees, vegetation and wildlife (Has the team reviewed P100’s landscape section 2.5.2 to understand existing vegetation evaluation processes?)
❑ Access (e.g., road, rail, marine, air, etc.)
❑ Access – transportation, parking, delivery/service, & pedestrian circulation considerations (Coordination with Facilities Management) ❑ Compatibility with Local Zoning or Design Guidelines ❑ Landscape and Public Space Design Opportunities related to Local Planning (Has the team reviewed P100 Planning Section 2.2’s coordination process guidance?)
❑ Prevailing winds, and solar orientation for natural lighting, views, heat loss/gain, water/energy conservation, and aesthetic concerns ❑ Climatic trends including precipitation type for site hydrology and hydraulics, temperature, sea level change ❑ Safety and occupational health issues ❑ DHS/FPS for perimeter, USMS for Interior ❑ Blast area and quantity distance consideration ❑ Interagency Security Committee (ISC) issues
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element D2. Site Surveys: Understanding the developmental constraints of a site are critical to developing scope of architecture and civil engineering. The site should be surveyed for geographic features like plot/plat’s property boundaries, buildable areas, topography,and site flood plain circumstances. Have these been obtained yet? Are they thorough? Certain criteria are necessary to know the site sufficiently for proper development. Here are some prompts:
❑ Deeds ❑ Setbacks ❑ Easements ❑ Rights-of-way ❑ Drainage and soil type ❑ Access & curb cuts ❑ Meets and Bounds ❑ Topography; vertical elevation ❑ Archeological Surveys ❑ Solar Access/Constraints
❑ Benchmark control systems ❑ Trees, vegetation and wildlife ❑ Proximity to drainage ways, floodplains, flood hazard, sea level and wildfire zones (both historic information and anticipated change) ❑ Existing facility locations and conditions ❑ Legal property descriptions with property lines ❑ Known below grade geology; seismic conditions ❑ Known below grade structures and utilities (both active and inactive)
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element D3. Civil Geotechnical Information: The civil/geotechnical site evaluation provides a basis for foundation, structural, and hydrological design. Has a geological study been done? Were a few or many locations of bore cores done? Several criteria are important to evaluations to estimate the subsurface and soil conditions. These determine the design requirements that will need to be met. Here are some prompts:
❑ Depth to bedrock ❑ Fault line locations ❑ Pier/pile capacities ❑ Ground water quality ❑ Floodplain and flood hazard analysis (using both historic information and anticipated change) ❑ Overall site analysis ❑ Seismic requirements ❑ Demolition requirements ❑ Paving design options
❑ Allowable bearing capacities ❑ Soil percolation rate & conductivity ❑ Water table/groundwater depth, flow rate and direction, chemistry (include changes due to sea level change) ❑ Site subsidence or uplift ❑ Permafrost thaw or change in frost line depth (change in climatic temperature trends) ❑ Expansive or collapse potential of soils ❑ Need for soil treatment or replacement ❑ Description of foundation design options ❑ Spoil area for excess soil (i.e., location of on-site area or off-site instructions) ❑ General site description (e.g., terrain, soil types, existing structures, spoil removal, areas of hazardous waste, etc.)
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on
Element D4. Governing Regulatory Requirements: Does the Project Management Plan, Statements of Work, Previous Studies provide a clear work plan to prepare, submit, and track necessary regulatory, code compliance, and permitting necessary to execute the project? Several criteria that are regulated. Here are some prompts:
❑ National Environmental Policy Act (NEPA) ❑ Environmental (HAZMAT) ❑ Fire ❑ Platting ❑ Signage ❑ Air/water ❑ Demolition ❑ Occupancy ❑ Solar ❑ Special issues ❑ Accessibility ❑ Unique requirements ❑ Transportation ❑ Building height limits ❑ Setback requirements (ISC) ❑ Structural calculations ❑ Historical issues (Section 106) ❑ Energy Independence and Security Act of 2007 (EISA438) Stormwater Management
Note: The codes that will have a significant impact on the scope of the project should also be investigated and explained in detail. Particular attention should be paid to local requirements. Regulatory and code requirements may affect the defined physical characteristics and project cost estimate. The project schedule may be affected by regulatory approval processes. For some technically complex buildings, regulations change fairly often. Many of these permits are the responsibility of the contractor. Do not forget to include this in the contract.
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element D5. Environmental Assessment: Have sufficient environmental assessments been performed for the site, or existing facilities, to evaluate, qualify and quantify issues for the project in terms of needs to address in the cost estimate and project schedule? Many risks to project delivery may arise if not known from a thorough environmental assessment.
Here are some prompts::
❑ Archeological ❑ Location in a wetlands area ❑ Existing contamination ❑ Past/present use of site ❑ NEPA Assessments ❑ Endangered species ❑ Site water detention requirements ❑ Coastal Zone Management ❑ Erosion / sediment control ❑ Neighborhood concerns (Traffic)
❑ Impact on Tax Base ❑ Social / Cultural Impact
❑ Impact on Indian Tribes ❑ Impact to farm lands ❑ Location in an EPA air quality non-compliance zone ❑ Environmental permits now in force ❑ Location of nearest residential area ❑ Groundwater monitoring in place ❑ Downstream uses of groundwater ❑ Existing environmental problems with the site ❑ Noise attenuation /vibration attenuation requirements ❑ Air/water discharge requirements and options evaluated ❑ Discharge limits of sanitary and storm sewers identified ❑ HAZMAT mitigation (asbestos, lead paint, mercury...etc.)
Note: GSA project team should begin with an environmental checklist which determines if we need an Environmental Assessment. The Environmental Assessment in turn will determine if an Environmental Impact Statement is necessary.
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element D6. Utility Sources with Supply Conditions: The availability / non-availability of utilities near the site - to construct and operate the facility - is the need known. Utilities service reliability of supply, quantities, and certain qualities, like temperature, pressure, voltage, are important to project scope definition. How thoroughly have utilities services been evaluated? Several criteria need to be understood. Here are some prompts:
❑ Sewer ❑ Facility air ❑ Heating water ❑ Cooling water ❑ Natural Gas ❑ Steam ❑ Potable water, drinking water ❑ Electricity (voltage levels) ❑ Water for fire fighting (see D7 for non-utility fire life safety issues) ❑ Communications (e.g., data, cable television, telephones) ❑ Special requirement (e.g., deionized water or oxygen) ❑ Other (Refer to element G3 for specific equipment requirements)
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element D7. Site Life Safety Considerations: Recognizing the dangers of fire, and the risks to people and facilities of fire, and other natural disasters, thinking about emergency management procedures at any given site is important to site selection and planning, and as part of the basis for design. How well does the project demonstrate an understanding of the fire protection practices at the site, available firewater supply (amounts and conditions), and other special safety requirements unique to the site, like evacuation routes, etc. Here are some prompts:
❑ Threat assessment ❑ Flow testing ❑ Access and evacuation plan ❑ Available emergency medical facilities ❑ Fire monitors & hydrants ❑ Wildfire risks / smoke migration ❑ Urban fires frequency / smoke migration ❑ Security considerations (site illumination, access control, etc.)
❑ Coordinate with the local fire protective services
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element D8. Special Water and Waste Treatment Requirements : With our environmental rules, such as stormwater management per the Stormwater Management for Federal Facilities under Section 438 of the Energy Independence and Security Act, we must carefully understand our responsibilities. Is the team familiar with EISA Section 438, and GSA’s interpretation of it? On-site, containment, or pretreatment of water and waste needs evaluated properly. Will your project’s facility need to dispense of any industrial process created wastewater that requires special treatment? How is your project approaching the SITEs program matters that relate to water treatment? Here are some prompts:
❑ Wastewater treatment ❑ Process waste ❑ Sanitary waste ❑ Waste disposal ❑ Well water pretreatment ❑ Storm water containment & treatment
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on
Category E. BUILDING PROGRAMMING
Read this introductory statement that tells this category’s purpose, and risk management benefits - to frame the elements’ discussions:
Up to this point in our session, we’ve scored our business case to do this project. We’ve scored our application of our policies, guidelines, and standards. We now need to score our building programming, how well we have refined what we need to design to build, repair, or revitalize it. To determine how well defined a project’s scope is as it relates to the building programming, we examine the 13 elements of this category:
E.1 Program Statement E.2 Building Summary Space List E.3 Overall Adjacency Diagrams E.4 Stacking Diagrams E.5 Growth and Phase Development E.6 Circulation and Open Space Requirements E.7 Functional Relationship Diagrams / Room by Room E.8 Loading / Unloading / Storage Facilities Requirements E.9 Transportation Requirements E.10 Building Finishes E.11 Room Data Sheets E.12 Furnishings, Equipment, and Built-Ins E.13 Window Treatment
Element E1. Program Statement: With our early planning through our implementation of the Project Intake Guide, Project Planning Guide, we do our programming. We capture and refine the program through our feasibility studies, housing plans, Prospectus Development Studies for Capital Projects, the Owner’s Project Requirements (OPR) Documents, and the Tenant’s Program of Requirements, and distill and write the essential scope statement in our Project Management Plan. In our programming we define the essential criteria and standards for our project. Project teams should prepare this program statement to identify in terms of space planning and functional relationships,the levels of service/performance for the facility. It should address the human, physical, and external aspects to be considered in the design. Here are some prompts:
❑ Does the Program Statement provide a correct depiction of what is to be done?
❑ Does the performance criteria identified while planning include these items:
● A statement that outlines what performance goals are to be attained?
● Any unique measures that must be achieved (e.g., usable/gross, floor loading, foot-candles at work surfaces, skin ratio, fenestration ratio)
● Any unique testing that is the accepted manner to establish that the criterion is met (e.g. using a standard light meter to do the job)?
❑ Does the Program Statement reflect management’s reason for doing this project the basis for project decision?
❑ Is the Program Statement clear and sufficient for the project’s further development?
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element E2. Building Summary Space List: Through our programming we capture the necessary space requirements via our preparations of project scope defining documents:
Feasibility Studies, Housing Plans, Prospectus Development Studies, and our Tenant’s Space Program of Requirements. A building’s summary space list includes all space requirements for the entire project. This list should address specific types and areas required for the performance of the functions for which the building is being made, or altered. The list should be technically based and show net areas to be assigned to uses, unassigned space calculated to support the assigned net areas, and an efficiency factor of net areas’ use to building gross area. It should show these factors. It assists with calculations for people, capacity, net area, and gross area. Does this project’s space list include all it needs? Here are some prompts:
❑ Building population ❑ Administrative offices ❑ Training rooms ❑ Lounges ❑ Laboratories ❑ Corridors ❑ Conference rooms ❑ Storage facilities ❑ Vending alcoves
❑ Mechanical rooms ❑ Janitorial closets ❑ Electrical rooms ❑ Elevators ❑ Entry lobby ❑ Stairs ❑ Restrooms ❑ Loading docks ❑ Court space ❑ Data/computer areas ❑ Food Service Cafeteria ❑ Vaults ❑ Daycare ❑ Parking space and types ❑ Sally Ports / Cell Blocks ❑ Special technology considerations ❑ Are net, usable, common, gross areas tabulated?
❑ Are Assignable areas, assignments, tabulated?
❑Is Net to Gross area calculated?
● If new, is gross to buildable area calculated?
Note: A room data sheet should correspond to each entry on the summary space list.
Room data sheets are discussed in element E11. The room data sheet contains information that is necessary for the summary space list. This list is used to determine assignable, usable, gross, joint use, rentable and others types of space.
Now, score the element, mark it on the Score Sheet. Write needed work and assign it on the “for action” tab. Write identified risks on the Risk Register.
Element E3. Overall Adjacency Diagrams and Test Fits (Space Planning Horizontally) :
Through our programming we capture the…