10 BOTA Phase 2 RFQ 47PB5126R0003 Final Amd 0007.pdf

PDF 610 KB Posted

Attached to
Design-Build Services for the Bridge of the Americas (BOTA) Land Port of Entry (LPOE) Modernization Project, El Paso, Texas
Solicitation number
47PB5126R0003
Issued by
Not on record

About this file

This is Amendment 0007 to GSA Solicitation 47PB5126R0003 for Design Build Services for the Bridge of the Americas (BOTA) Land Port of Entry Modernization Project in El Paso, Texas. The amendment, effective October 5, 2026, updates the solicitation with revised guidance documents and clarifies requirements through a Questions and Answers section.

Key updates include: (1) Revision 1 to the 2023 CBP Design Guide has been reissued, and offerors must update all proposal documentation, narratives, calculations, drawings, specifications, compliance matrices, and other materials to reflect the current version, with all prior versions superseded; (2) Four documents have been uploaded to the shared drive—the Disaster Resilience and Vulnerability Assessment Response Template, CBP Land Port of Entry Design Standard 2023 Revision 1, CBP OFO Baseline Design Requirements_2025, and CBP OFO Room Data Sheets_2025; and (3) the proposal due date is October 15, 2026. The Questions and Answers section addresses 17 topics including energy modeling requirements (not required for pre-award concept), Art in Architecture funding (0.5% of estimated construction cost, separate from contract), citizenship requirements for facility access, design options requiring clear identification, inclusion of pedestrian processing, "Return to Mexico" lanes, public transportation bus station within project scope, construction zone isolation requirements, and design drawing file size limitations. All offerors must acknowledge receipt of this amendment in accordance with instructions in Block 11 on Standard Form 30 prior to the hour and date specified for receipt of offers.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

2. AMENDMENT/MODIFICATION NUMBER

GSA Solicitation 47PB5126R0003, Design Build Services for the Bridge of the Americas (BOTA) Land Port of Entry (LPOE), El Paso, Texas

See description of changes herein.

All offerors must acknowledge the amendment in accordance with the instructions in Block 11.

GSA PBS OAM Capital Construction Projects Division Div 819 Taylor Street, 11th Floor, Fort Worth, Texas 76102 POC Marsha Howard, Contracting Officer Email: marsha.howard@gsa.gov

PH: 817-505-8543

47PB5126R0003

KAHUA 0347

10/05/2026

01/26/2026

BOTA LPOE Modernization Project, El Paso, TX GSA PBS Capital Delivery Projects Division Solicitation 47PB5126R0003

Solicitation 47PB5126R0003

BOTA LPOE Modernization Project, El Paso, TX

Amendment 0007 amends Solicitation 47PB5126R0003 as follows:

Questions and Answers: See attached chart

Revision 1 to the 2023 CBP Design Guide has been revised and reissued. Offerors shall update all proposal documentation, narratives, calculations, drawings, specifications, compliance matrices, and other submitted materials to reflect and reference the current version. Any references to prior versions shall be considered superseded and replaced by the current version.

The following has been uploaded to the Shared Drive under Amendment 0007 folder:

1. Disaster Resilience and Vulnerability Assessment Response Template

2. CBP Land Port of Entry Design Standard, 2023, Revision 1

3. CBP OFO Baseline Design Requirements_2025

4. CBP OFO Room Data Sheets (RDS)_2025

Proposal due date is October 15, 2026.

All offerors must acknowledge the amendment in accordance with the instructions in Block 11 on Standard Form 30.

END OF AMENDMENT 0007

# Reference Question Answer

Disaster Resiliency Template Request: CBS Submittal Matrix, Section 1:

Disaster Resiliency

The CBS Submittal Matrix Pre-Award Concept Section 1 General Information Disaster Resiliency section references a response template for compliance documentation.

Please supply template for submission if this a required for RFP submission.

The template will be provided in the shared drive.

Energy Model Requirements per CBS Submittal Matrix:

CBS Submittal Matrix, Section 1: Energy Usage Model

The CBS Submittal Matrix Pre-Award Concept Section 1 Energy Usage Model states demonstrate compliance with Energy Efficiency Performance Standard in 10 CFR

433.100. Confirm if pre-award concept submission

requires an energy model and which section in the submission this response should be included.

An energy model will not be required for the pre-award concept.

3 RFP, Page 103 of 132

Reference item 6. Art In Architecture. The RFP states that the 0.5% of the estimated construction cost is to be reserved for Art in Architecture commission. Is this the construction cost or total evaluated price? If it is the total evaluated price, this would likely be $2.5 Million. Do the allowances need to be included in the TOTAL EVALUATED PRICE?

The Art in Architecture (AiA) art piece is separate from this contract, which is 0.5% of the estimated cost, so no allowance is need for the actual art piect. The DB contractor will be required to coordinate with the artist. Depending on the art piece or pieces there could be a need for infrastructure that has yet to be determined, so a contract modification will need to be excuted if needed.

Please confirm that only individuals who will require access to GSA controlled facilities and information systems are required to be US citizens

In general, for GSA contracts, individuals who require routine physical access to GSA-controlled facilities and/or logical access to federally controlled information systems typically must satisfy HSPD-12/PIV credentialing and background investigation requirements. That does not necessarily mean they must all be U.S. citizens; eligibility may depend on the contract, role, system, data sensitivity, immigration status, residency history, and any applicable security/export-control/classified-information requirements.

5 AM0004, CLIN Summary The Current Allowances indicate TBD. Will the Allowances be provided by the GSA, or is each proposer responsible for determining these?

The current allowances will be provided by GSA.

6 AM0004, CLIN Summary The UNIT pricing is currently indicated above the TOTAL EVALUATED PRICE. To confirm, any pricing resulting from this will be in addition to it, correct?

See Amendment 0002 for definition

The CBP Design Standard notes NIC rating for walls instead of STC Rating. Can the Government provide STC requirements for each type of room.

The Design standard provides NIC rating for acoustic separation on full construction of rooms performance. The DB Team will be required to develop the STC ratings of various components based on the NIC rating. NIC rating will require field testing to measure the NIC rating performance.

CBP Design Standard 1.2.1 l Definition of the LPOE Design Standard

The CBP Design Standard notes various construction alternates. Can the construction alternates be used.

Based on the CBP Design standards 1.2.1 This Standard is CBP’s policy that establishes minimum requirements that must be met in all LPOE projects. Proposed revisions to these requirements are subject to a waiver request process, per Section 1.2.6, Alternate or Equivalent Means, Exceptions, and Deviations, in this Standard.

Deviations from specific minimum security requirements are considered only when necessitated by operational requirements or conditions and not for budgetary reasons.

CBP Design Standard 17.5 Material

The CBP Design Standard notes "Piping for drainage, waste, and vent systems must be cast iron with heavy-duty no-hub couplings above grade and cast-iron bell and spigot heavy-duty below grade". Can the cast iron piping be substituted with schedule 40 PVC.

A waiver/deviation proposal must be submitted to CBP for approval.

# Reference Question Answer

Does the RFP Options need to be shown separately to include: Kennel Building, 8 additional lanes and canopy for non-commercial inspection, trusted traveler building, and standalone narcotics vault?

Offerors must clearly identify and incorporate all proposed design options within their preaward drawings. Each option must be itemized to allow GSA, at its sole discretion, the ability to select and award specific options as part of the initial contract.

Does the BOTA LPOE accept and process pedestrian traffic crossing the bridge?

Yes. The Bridge of the Americas (BOTA) Land Port of Entry processes pedestrians, who cross via the designed walkways and undergo inspection inside the main Administration Building.

How should the betterments be identified and illustrated for clarification?

Offerors must clearly highlight all proposed betterments within their technical proposals and include a section entitled "Betterments" in their proposal and define how each betterment exceeds the baseline RFP requirements to allow GSA to evaluate and determine acceptance.

Is a POV (Privately Owned Vehicle) "Return to Mexico" lane required in the design?

Yes. All proposed design drawings must incorporate and clearly delineate a dedicated "Return to Mexico" lane for POV traffic.

Is the public transportation bus station located north of the site included in the scope of the overall project?

Yes. The public transportation station to the north is within the project boundaries and is included in the overall scope of work. Offerors must account for this facility in their proposals and design submittals.

Must the construction zone be physically isolated from government personnel during the construction phase?

Yes. For site security and operational integrity, the contractor must completely isolate the construction zone and construction personnel from active government operations and personnel. All site segregation, temporary barriers, and access control measures must comply with the project's security specifications.

Will off-site parking be provided for government workforce and port visitors?

No, The government will not provide additional or temporary off-site parking for the government workforce or port visitors.

With design drawings that need to be high quality so they can be zoomed in on per the Amendment response, I'm nervous that come submission time our file size will be above the 25MB limit. Can we utilize our GACA account google drive to submit to you?

Answered via Amendment 0006

SF30 Amendment 0007
BOTA LPOE Amendment 0007
Amd 0007 question and answer chart