Design-Build Services for the Bridge of the Americas (BOTA) Land Port of Entry (LPOE) Modernization Project, El Paso, Texas
Solicitation number
47PB5126R0003
Issued by
Not on record

About this file

This is a Request for Quote (RFQ) and Final Amendment 0002 for Phase 2 of a design-build procurement for the Bridge of the Americas (BOTA) Land Port of Entry (LPOE) modernization project located in El Paso, Texas. The U.S. Customs and Border Protection (CBP) is seeking design and construction services to modernize the critical international gateway crossing. The scope of work encompasses all labor and materials required for complete design and construction services under the Two-Phase Design-Build Selection Procedures, incorporating the Art in Architecture Program and Design-Construction-Operational Excellence policies. Phase 1 has been completed, and shortlisted offerors have been announced via sam.gov. The resulting contract will be firm fixed price and is funded under the Infrastructure Investment and Jobs Act (IIJA). This is a negotiated, best value procurement with an anticipated award date of January 2027. Shortlisted offerors are responsible for monitoring and downloading all solicitation documents and amendments from the appropriate government sources.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

GSA Solicitation 47PB5126R0003, Design Build Services for the Bridge of the Americas (BOTA) Land Port of Entry (LPOE), El Paso, Texas

See description of changes herein.

All offerors must acknowledge the amendment in accordance with the instructions in Block 11.

GSA PBS OAM Capital Construction Projects Division Div 819 Taylor Street, 11th Floor, Fort Worth, Texas 76102 POC Marsha Howard, Contracting Officer Email: marsha.howard@gsa.gov

PH: 817-505-8543

47PB5126R0003

KAHUA 0347

1 352

07/15/2026

01/26/2026

BOTA LPOE Modernization Project, El Paso, TX GSA PBS Capital Delivery Projects Division Solicitation 47PB5126R0003

BOTA LPOE Modernization Project, El Paso, TX

Amendment 002 amends Solicitation 47PB5126R0003 as follows:

This amendment incorporates the BOTA LPOE Phase 2 Request for Proposal (RFP) which contains the Solicitation, Agreement, Scope of Work, Wage Determination(s) and attachments needed for Phase 2.

All documents, Standards and Criteria Documents, GSA Templates and References including BOTA LPOE Modernization Price Form is located on the GSA Shared Drive. To obtain access, contractors should send their GACA account information (email) to Marsha Howard via marsha.howard@gsa.gov AND Daniel Partida via Daniel.partida@gsa.gov for access.

The BOTA LPOE Modernization Price Form in the Shared Drive can be downloaded to input all pricing. However, contractors will need to submit a .pdf copy to the Contracting Officer for consideration. GSA is not responsible for calculations within the spreadsheet posted on the shared drive. Contractors will need to make sure all calculations are correct prior to submission.

The RFP contains references to “Allowances” within the document. Spec Section 01 21 00 ALLOWANCES and other information regarding allowances will be further defined and addressed via a separate amendment.

All offerors must acknowledge the amendment in accordance with the instructions in Block 11 on Standard Form 30.

END OF AMENDMENT 0002

mailto:marsha.howard@gsa.gov mailto:Daniel.partida@gsa.gov

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

47PB5126R0003

PBS Office of Acquisition Management Capital Project Acquisition Delivery Division 1800 F Street NW Washington , DC 20405 USA

PHASE 2

GSA Solicitation Number 47PB5126R0003 Design Build Contract for: Bridge of the Americas (BOTA) Land Port of Entry (LPOE) Modernization Project, El Paso, Texas

See Project Summary herein.

The range of this project is $400,000,000.00 - $460,000,000,000.00

A Bid Bond (Phase 2 requirement), Performance and Payment Bond (after award) are REQUIRED.

Two Phase Design Build Procedures

NAICS 236220

PQA

PBS Office of Acquisition Management Capital Project Acquisition Delivery Division 1800 F Street NW Washington , DC 20405 USA

PQA

Marsha Howard 817-505-8543

KAHUA 0347

1 35007/15/2026

10/15/2026

2:00 PM (CST)

Period of Performance

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Marsha Howard

Base Scope 1 of

Project Costs

Bridge of The Americas (BOTA) Land Port of Entry (LPOE) Modernization Project

Price Form

GSA RFP Number: 47PB5126R0003

CLIN-0001 Base Scope - Design Costs

ITEM PRICE

20% Design Concept/GSA Commissioner's Approval $

35% Design/100% Civil/Demo/Utilities Design $

65% Design $

95% Design $

100% Design $

Design Overhead $ Design Profit $

Total Design Cost $0.00

Base Scope 2 of

CLIN-0002 Main Bldg. Construction Base Scope Costs - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total Main Bldg. Base Scope Construction Costs - Shell $0.00

Base Scope 3 of

CLIN-0003

Main Bldg. Construction Base Scope Construction Costs - Tenant

Improvement (TI)

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Main Bldg. Base Scope Construction Costs - Tenant Improvement (TI) $0.00

Base Scope 4 of

CLIN-0004

Non-Commercial Inspection Includes 27 Lanes & Head House

Construction Base Scope Costs - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total Non-Commercial Inspection Includes 27 Lanes & Head House Construction Base Scope Costs - Shell $0.00

Base Scope 5 of

CLIN-0005

Non-Commercial Inspection Includes 27 Lanes & Head House

Construction Base Scope Costs - Tenant Improvement (TI)

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total Non-Commercial Inspection Includes 27 Lanes & Head House Construction Base Scope Costs - Tenant Improvement (TI) $0.00

Base Scope 6 of

CLIN-0006 Outbound Inspection Construction Base Scope Construction Costs - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total Outbound Inspection Construction Base Scope Construction Costs - Shell $0.00

Base Scope 7 of

CLIN-0007

Outbound Inspection Construction Base Scope Construction Costs -

Tenant Improvement (TI)

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total Outbound Inspection Construction Base Scope Construction Costs - Tenant Improvement (TI) $0.00

Base Scope 8 of

CLIN-0008 FMCSA Bus Inspection Construction Base Scope Costs - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total FMCSA Bus Inspection Construction Base Scope Costs - Shell $0.00

Base Scope 9 of

CLIN-0009

FMCSA Bus Inspection Construction Base Scope Costs - Tenant

Improvement (TI)

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total FMCSA Bus Inspection Construction Base Scope Costs - Tenant Improvement (TI) $0.00

Base Scope 10 of

CLIN-0010 TABC Building Construction Base Scope Costs - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

TABC Building Construction Base Scope Costs - Shell $0.00

Base Scope 11 of

CLIN-0011 TABC Building Construction Base Scope Costs - Tenant Improvement (TI)

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total TABC Building Construction Base Scope Costs - Tenant Improvement

(TI) $0.00

Base Scope 12 of

CLIN-0012 Utilities Construction Base Scope Costs

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Utilities Construction Base Scope Costs $0.00

Base Scope 13 of

CLIN-0013 Site Construction Base Scope Costs

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Site Construction Base Scope Costs $0.00

Base Scope 14 of

CLIN-0014 Demolition Construction Base Scope Costs

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Demolition Construction Base Scope Costs $0.00

Bid Options 1 of

Bid Options

Bridge of The Americas (BOTA) Land Port of Entry (LPOE) Modernization Project

Price Form

GSA RFP Number: 47PB5126R0003

CLIN-0016 Option #1A - Kennel Building Construction - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Option #1A - Kennel Building Construction Costs - Shell $0.00

Bid Options 2 of

CLIN-0017 Option #1B - Kennel Building Construction - Tenant Improvement (TI)

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Option #1B - Kennel Building Construction Costs - Tenant Improvement (TI) $0.00

Bid Options 3 of

CLIN-0018 Option #2A - Noncommercial Insp 8 Additional Lanes- Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00 otal Option #2A - Noncommercial Insp 8 Additional Lanes Construction Costs - She $0.00

Bid Options 4 of

CLIN-0019 Option #2B - Noncommercial Insp 8 Additional Lanes -TI

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total Option #2B - Noncommercial Insp 8 Additional Lanes Costs - Tenant

Bid Options 5 of

CLIN-0020 Option #3A - Trusted Traveler Building Construction - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Option #3A - Trusted Traveler Building Construction Costs - Shell $0.00

Bid Options 6 of

CLIN-0021 Option #3B - Trusted Traveler Building Construction - TI

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Insurance (offeror to enter percentage)* 0% $0.00

Total Option #3B - Trusted Traveler Building Construction Costs - Tenant

Bid Options 7 of

CLIN-0022 Option #4A - Narcotics Vault Construction - Shell

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Option #4A - Narcotics Vault Construction Costs - Shell $0.00

Bid Options 8 of

CLIN-0023 Option #4B - Narcotics Vault Construction - TI

ITEM PRICE

General Conditions $

Foundations $

Basement Construction $

Superstructure $

Exterior Closure $

Roofing $

Interior Construction $

Stairs $

Interior Finishes $

Conveyance System $

Plumbing $

HVAC $

Fire Protection $

Electrical $

Equipment $

Furnishings $

Special Construction $

Environmental - Remediation (soil) $

Environmental- Abatement $

Selective Building Demolition $

Sitework - Building Related $

Sitework - Non-Building Related $

SUBTOTAL - Construction Costs $0.00

Overhead (offeror to enter percentage)* 0% $0.00

Profit (offeror to enter percentage)* 0% $0.00

Bond (offeror to enter percentage)* 0% $0.00

Total Option #4B - Narcotics Vault Construction Costs - Tenant Improvement (TI) $0.00

GSA Solicitation No. 47PB5126R0003 BOTA LPOE Modernization, El Paso, TX

Design Build Contract for: Design Build Contract for the Bridge of the Americas (BOTA) Land Port of Entry (LPOE) Modernization Project, El Paso, Texas

The Solicitation, Phase 2 – Request for Proposals

Document: DB201-2/MAY 2026 (The Solicitation)

Table of Contents

I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. Receipt of Offers

II. Proposals

A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors

III. General Provisions

A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Notice Concerning Preparation of Proposals F. Bond Requirements G. Contractor Performance Information H. Safeguarding and Dissemination of Controlled Unclassified Information

(CUI) Building Information

I. INFORM

IV. FAR/GSAR Solicitation Provisions FAR 52.209-7 Information Regarding Responsibility Matters (GSA Class Deviation RFO-2025-09) FAR 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (GSA Class Deviation RFO-2025-09) FAR 52.216-1 Type Of Contract (GSA Class Deviation RFO-2025-16) FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of Work Buy American Requirements Buy American Exceptions FAR 52.233-2 Service of Protest (GSA Class Deviation RFO-2025-33) FAR 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (GSA Class Deviation RFO-2025-09) FAR 52.252-1 Solicitation Provisions Incorporated by Reference GSAR 552.102 Incorporating Provisions and Clauses by Reference GSAR 552.252-5 Authorized Deviations in Provisions

Small Business Subcontracting Plan Project Labor Agreement Certified Cost or Pricing Data Additional Provisions

V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (GSA

Class Deviation RFO-2025-15) B. 52.222-90 Addressing DEI Discrimination by Federal Contractors C. Security Requirements D. Additional Clauses

VI. Method Of Award

A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Total Evaluated Price F. Non-Price Factors G. Evaluation of Joint Venture Offers

I. General Information

I.A. The Solicitation and Contract

(1) This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the Solicitation Documents. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.

(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.

(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.

(4) In consideration for the preparation of a technical proposal including design concept meeting the minimum requirements described herein, GSA will pay a stipend of $240,000.00 to Offerors not selected for award of the resulting contract. Offerors that submit incomplete or unacceptable proposals are not eligible for a stipend.

I.B. List of Solicitation Documents

The Solicitation Documents are comprised of:

(1) Standard Form (SF) 1442, Solicitation Offer and Award

(2) The Solicitation Phase 2 Document

(3) BOTA LPOE Price Form

(4) Offeror Representations and Certifications Form

(5) The Agreement and Attachments to the Agreement (6)Wage Determination TX20260245 Building dated 2026 05 18

(7) Wage Determination TX20260293 Highway dated 2026 05 18

(8) The Statement of Work, Specifications, Drawings, and Exhibits

(9) Proprietary Information Agreement – See attached sample

I.C. Authorized Representatives

The following individuals are designated as the authorized GSA representatives under this Solicitation:

Authorized Representative Information:

Contracting Officer’s Information

Name: Marsha Howard

Address: 819 Taylor Street, 11th Floor, Fort Worth, Texas 76102

Telephone: 817-505-8543

Email: marsha.howard@gsa.gov

I.D. Pre-Proposal Conference and Site Visit

Interested parties must notify the Contracting Officer AND the Contracting Officer’s Representative for further information about attendance and to confirm location, time, and date. Only those parties who have notified the Contracting Officer and provided necessary information in advance of the meeting will be allowed to attend. To request a reasonable accommodation due to a disability, contact the Contracting Officer and the Contracting Officer’s Representative (COR):

Contracting Officer: Marsha Howard, marsha.howard@gsa.gov

Contracting Officer Representative: Daniel Partida, daniel.partida@gsa.gov

Date: July 28, 2026

Time: 9:00 AM to 3:00 PM MDT

Location: Bridge of The Americas Land Port of Entry Quarter Deck Conference Room 3600 E. Paisano Ave El Paso, TX 79905

There will be an Industry Day on July 27, 2026 starting at 1:00 PM to 4:00 PM MDT at the following location:

Contract Opportunities Center El Paso Community College Administrative Services Center Building A, Auditorium 9050 Viscount Blvd.

El Paso, TX 79925

I.E. Estimated Price Range

The estimated design and construction cost range is between $400,000,000.00 and $460,000,000.00.

I.F. FAR 52.228-1 Bid Guarantee (Sep 96)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids;

and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.G. Receipt of Offers

(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 2:00 pm CST on the following date and at the following address.

Date: October 15, 2026 Point of Contact (POC) Address: via email to marsha.howard@gsa.gov

Electronic Submission of Proposals: Offers must be received by the email address of the GSA POC listed herein on or before the date and time established for receipt of offers. The date and time of receipt will be established according to the Government computer system’s documentation showing the exact official time of receipt by the GSA POC listed herein and not by the time the electronic proposal was sent by the Offeror or received by the GSA server. It is the Offeror’s responsibility to ensure proposals are complete and submitted early enough to be received by the GSA POC before the deadline, and to confirm receipt before the deadline. Proposals or portions of proposals which are received by the GSA POC later than the time noted within will be rejected and will not be considered.

NOTE: The maximum file size is 25 MB. GSA has occasionally experienced delays in delivery of emails from the GSA server to an email account. Therefore contractors / offerors need to plan accordingly.

WARNING: Consistent with GAO case law on the issue of “late-is-late rule” related to electronically submitted proposals, GSA will strictly comply with and enforce FAR 52.215-1(c)(3)(ii)(A). Pursuant to GAO’s application of FAR 52.215-1(c)(3)(ii)(A), an electronically submitted proposal that is received late will not be considered unless (1) it is received before award is made, (2) the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition and (3) it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals. FAR 52.215-1 (c)(3)(ii)(A)(1).

Acknowledgement of Amendments: Acknowledgement of receipt of all amendments shall be included in your proposal.

II. Proposals

II.A. Proposal Contents

Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:

1. Price Proposal

● Representations and Certifications

● Standard Form 24, Bid Bond

● Subcontracting Plan

● GSA Form 527 – Contractor’s Qualification and Financial Information

2. Phase 2 Technical Proposal

3. Proprietary Information Agreement(s)

4. Other Documents as Required

II.B. Proposal Format

Phase 2 Technical submissions shall be no more than 100 pages at least 11 font size, in an 8-1/2" x 11" format and submitted electronically.

The Government will award a contract resulting from this Solicitation to the responsible Offeror whose offer conforming to the Solicitation will be most advantageous to the Government, Total Evaluated Price and other factors considered. In addition to Total Evaluated Price, the following Phase 2 non-price factors shall be used to evaluate offers:

1. Quality of Design Concept 45%

2. Qualifications, Experience and Past Performance of Key Personnel 25%

3. Management and Technical Approach 25%

4. Small Business 5%

TOTAL 100%

Phase 2 – DESIGN-BUILD FIRMS AND LEAD DESIGNER INTERVIEWS

Initial Oral Presentation: Timing and Scheduling

Within 30 calendar days of the Source Selection Evaluation Board’s completion of the Phase 1 shortlist, the Offerors will be notified of advancement to Phase 2. GSA will contact each Offeror to schedule the Initial Oral Presentation. The Offerors are given sufficient time to prepare for the Initial Oral Presentation but that lead time should not exceed eight (8) weeks from the issuance of the Phase 2 RFP. The Offeror is free to choose the people who will attend the Initial Oral Presentation but are limited to a maximum of eight (8) people. The Initial Oral Presentation will be a virtual meeting, tentatively scheduled for and . Aug 25, 2026 Aug 26, 2026

Each firm participating in Phase 2 must assemble a high-quality integrated team whose expertise in multiple disciplines reflects the criteria of the interview notification.

Firms must also document how their respective teams fulfill GSA’s commitment to the socioeconomic initiatives of the notification—including subcontracting goals for small, women-owned, veteran-owned, and small disadvantaged businesses.

As provided for in accordance with FAR 15.105-1 (GSA Class Deviation RFO-2025-15) each Offeror shall participate in an initial oral presentation to the Government. This will provide the parties with an opportunity for dialogue during the Phase 2 proposal preparation. In regard to the scope and content of the exchanges that will occur between the Government's participants and the Offeror, the primary purpose of the Initial Oral Presentation is to allow the Government to review the preliminary concept with the Offeror for the purpose of facilitating a more complete and accurate submission. The information provided during the Initial Oral Presentation will not be evaluated. This is an opportunity for the offerors to gain better understanding of the requirements and to receive feedback from the Government. There are no maximum or minimum materials that must be prepared for the Initial Oral Presentation. Offerors are free to develop as much, or as little, material as they desire. Each Offeror will have a maximum of ninety (90) minutes in which to provide the presentation and engage in dialogue with the Government.

Offerors may allot this time in any manner they choose and are free to choose the presenters.

The Offeror may not leave any materials with the Government at the conclusion of the Initial Oral Presentation and none of the materials will be incorporated into the Contract.

No oral statements made by the Government can be used to modify, change, or otherwise alter the Phase II RFP and there will be no scoring or evaluation of the "preliminary concept" by the Government.

Technical Submission (incl. Concept Design)

The Evaluation Team will evaluate the technical submission for Phase 2, participate in discussion among themselves and devise a plan that will inform and shape the nature of discussions during the Final Oral Presentations. After the Final Oral Presentations, the Evaluation Team will finalize the evaluation and then participate in a consensus meeting to arrive at a final consensus evaluation of the proposals.

Final Oral Presentations

As permitted in FAR 15.105-1 (GSA Class Deviation RFO-2025-15), each Offeror selected to participate in Phase 2 will have the opportunity to make a Final Oral Presentation. The purpose of this second presentation will be to engage in discussions about the Offeror's proposed Design Concept, as submitted in response to Phase II RFP. Much like the Initial Oral Presentation, the Final Oral Presentation will provide the opportunity for dialogue between the parties. Unlike the Initial Oral Presentation, the Government will consider the information provided during the presentation as an element of the overall evaluation of the Offeror under the “Quality of Design Concept” evaluation factor.

Each Offeror will have a maximum of ninety (90) minutes in which to provide the presentation and engage in dialogue with the Government. Offerors may allot this time in any manner they choose. ALL of the Offeror's key personnel identified in response to Evaluation Factor 2 of Phase 2 RFP MUST attend the Final Oral Presentation in person.

The Offeror may also bring additional people to the presentation but are limited to a maximum of eight (8) people. The Government reserves the right to take into consideration the following during the Final Oral Presentation: (a) the preparedness of the key personnel; (b) the ease of interaction between the key personnel; and (c) the extent to which the key personnel are or are not aligned in terms of the overall vision for the project. The Final Oral Presentation will be an in-person meeting, tentatively scheduled for October 20, 2026 and October 21, 2026 in El Paso, Texas.

The Offeror may not leave any materials with the Government at the conclusion of the Final Oral Presentation and none of the materials will be incorporated into the Contract.

No oral statements made by the Government can be used to modify, change, or otherwise alter Phase 2 RFP.

II.C. Price Proposal

(1) Contents

The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.

(2) Qualifications, Exclusions and Conditions

If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

(3) Additional Proposal Requirements

Subcontracting Plan:

(A) GSA is committed to supporting the Small Business Program. These commitments extend to Historically Underutilized Business Zones (HUBZone), Small Business (SB), Small Disadvantage Business (SDB), Women-Owned Small Business (WOSB), Veteran-Owner Small Business (VOSB), and Service-Disabled Veteran- Owned Small Business (SDVOSB). Large businesses will be required to submit a subcontracting plan. This subcontracting plan only applies to work performed in the United States and its possessions.

(B) GSA has established a national subcontracting goal of at least 25% of the subcontracted effort to small businesses. Of the total subcontracted effort, GSA has established national subcontracting goals of at least 3% to HUBZone firms, 5% to SDB firms, 5% to WOSB firms and 3% to SDVOSB firms.

(C) FAR 52.219-8, Utilization of Small Business Concerns states in part; “The Contractor hereby agrees to carry out this policy in the awarding of subcontracts to the fullest extent consistent with efficient contract performance.” If the Offeror does not intend to subcontract, provide a detailed explanation why subcontracting would not result in efficient contract performance.

(D) Solicitation Submittal Requirements: Identify, in terms of dollar value and percentage of total proposed price, the extent of work you will perform as the prime contractor in your proposed Subcontracting Plan. Identify, in terms of dollar value and percentage of total proposed price, the extent of work you will perform as the prime contractor. State the extent of work, including type and percentages, you plan to subcontract to LB, HUBZone, SB, SDB, WOSB, VOSB, SDVOSB firms, and if applicable, HBCU/MI. Small business Offerors should not submit subcontracting plans.

II.D. Technical Proposal

PHASE 2 EVALUATION CRITERIA

The following criteria represent the factors that will be used by the Evaluation Team in evaluation of offerors.

● To be considered similar in size, a project managed must have exceeded $200,000,000.00 in costs, consisting of design and construction, a construction schedule over two years and be completed in the last ten (10) years.

● To be considered similar in complexity, a project consisting of major modernization of a LPOE, airport, military complex, campus or facility area (a project on one site that has multiple buildings or facilities on it), must include elements of significant design and construction of a facility, LPOE, and/or site.

Construction services include demolition, various construction activities (mechanical, electrical, civil, architectural) and site work.

● Similar in Type: A project consisting of major modernization of an LPOE, airport, military complex, campus or facility area (a project on one site that has multiple buildings or facilities on it), including but not limited to canopies, administration buildings, holding cells, administration offices, visitor and employee parking areas, major utility relocations, and road and paving site work. Additional and higher consideration will be given to projects completed as a result of a design-build construction project with modernization on occupied southern border LPOEs, including but not limited to POV primary inspection lanes with booths, secondary POV inspection area with inspection canopies, LPOE administration buildings with passenger processing, holding cells, admin offices, kennels, visitor and employee parking areas, major utility relocations, IT and security infrastructure and road and paving site work.

● Residential housing, warehouse projects or improvements to office renovation limited to reconfiguration of spaces within a high-rise office structure are not considered similar in type, regardless of size.

● A Base Contract for Indefinite Delivery Indefinite Quantity (IDIQ) will not be considered as similar in size, complexity and type. Only a task order awarded under the IDIQ that meets the criteria for similar size, complexity and type will be evaluated.

● Each project need not contain every element (size, type and complexity), but the combination of projects should demonstrate the ability to perform these services in a satisfactory manner.

● A project is considered similar when, based on the consensus judgment of the evaluating team members, the project has enough characteristics or similarities in common with the subject project that they could be determined comparable.

Scoring must be based on the RFP using the following criteria and percentage weighting:

QUALITY OF DESIGN CONCEPT (45%) - 50-page limit out of overall 100-page limit

The objective of this factor is to evaluate the extent to which the Design Concept displays a satisfactory probability that the Offeror will be able to achieve the minimum performance requirements set forth in the RFP and the innovation, purpose, and vision indicative of a Design Excellence project. Under this factor, the evaluation team will consider the information provided during the Final Oral Presentation as well as the written submission.

The following list identifies characteristics of design that the Government will use to evaluate the probability that the Offeror's Design Concept will achieve the innovation, purpose, and vision indicative of a Design Excellence project. Offerors may provide an additional narrative, not to exceed five (5) pages, to provide additional information to explain how the Design Concept provides Design Quality.

● Functionality - The extent to which the Offeror's Design Concept focuses on simplicity, spatial flexibility and efficiency, organizational adjacencies, and clear paths of travel.

● Performance - The extent to which the Offeror's Design Concept provides due consideration to areas such as energy, water and material efficiency, ease of maintenance, and clearly stated performance goals.

● Quality - The extent to which the Offeror's Design Concept considers the quality of materials and finishes, ceiling heights, and provides for functional design that supports the project's primary purpose but also provides for secondary or tertiary amenities.

● Architectural Design - The extent to which the Offeror's Design Concept reflects current profession’s best practices such as architectural expression, massing orientation, and materiality.

● Betterments - The Offeror shall include a section entitled “Betterments” in its proposal. For purposes of this evaluation factor, a “Betterment” is defined as any element, component, or system which exceeds the minimum…