This file is an Administrative Specifications document for the Borough of West Conshohocken, Pennsylvania, detailing contractor responsibilities for the MacKenzie Park Workout Stations Phase 2E project. The project involves the installation of workout equipment at six locations along an existing walking trail within MacKenzie Park. The contractor must furnish all labor, materials, equipment, tools, supplies, and supervision necessary to complete the installation work. Sealed bids were due on December 4, 2026 at 11:00 A.M., with bid documents available through PennBid (www.PennBid.net) and hard copies available for inspection at 112 Ford Street, West Conshohocken, PA 19428. No bidder may withdraw a bid within sixty days after the scheduled closing time for receipt of bids. The contract requires adherence to a detailed construction schedule with milestone dates, submission of a detailed work schedule prior to construction, and compliance with all state, county, and local permits and approvals.

The estimated project cost is $100.00, with each proposal requiring a certified check or bid bond payable to the Borough of West Conshohocken in an amount of not less than ten percent of the bid. The successful bidder must furnish Performance and Labor and Material Bonds in one hundred percent of the contract amount, a Maintenance Bond in the amount of twenty-five percent of the total contract price, and a Certificate of Insurance. Project bids must comply with Pennsylvania Prevailing Wage requirements. The contractor is responsible for all costs including temporary power, water, telephone, testing services, road opening permits, construction permits, and licenses. The contractor must confine operations within specified right-of-ways, protect existing structures and adjacent property, restore disturbed areas to their original condition, and perform final cleanup inspections as required by the Engineer. The Borough reserves the right to waive any informality or reject any or all bids.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01010-1

SECTION 01010

CONTRACTORS WORK

PART 1 GENERAL

1.1 RESPONSIBILITY OF CONTRACTOR

A. Contractor shall furnish all field design as required, materials, implements, machinery, equipment, tools, supplies, transportation, labor and supervision required for the construction of Work Out Stations as specified in the Contract documents. It shall be the responsibility of the Contractor to proceed with the work in the manner and within such limitations as may be prescribed by the

Engineers.

The scope of work will be as follows:

Installation of workout equipment at 6 locations along the existing walking trail in

MacKenzie Park. Work to include all equipment, materials and labor.

1.2 CONSTRUCTION LIMITS

A. Contractor shall confine their operations strictly within the limits of right-of-ways, indicated by the plans and/or directed by the Engineers, unless written permission is obtained to occupy additional ground. Upon completion of work the

Contractor shall cleanup and restore the area of their operations to a condition at least equal to original conditions. Unless specified elsewhere herein, all restoration shall be included in the Contractor's unit and/or lump sum price bid.

Damage to property outside of specified construction limits shall be the responsibility of the Contractor and restoration of same shall be made at the

Contractor's expense.

1.3 MEASUREMENT OF WORK AND MATERIALS

A. The Contractor will be paid for the actual quantity of authorized work or material furnished under each item of the contract, at the prices stipulated for each item. If the quantity of any unit price item is decreased the Contractor shall have no claim for damages on the basis of loss of anticipated profits. All quantities of work and materials to be paid will be determined by the Engineers in accordance with working lines specified in the contract documents.

1.4 SUGGESTED CONSTRUCTION SEQUENCE

A. Submit for approval prior to construction a detailed schedule outlining all major activities, including the projected dates for work on each roadway intersection in each phase. Upon approval, the Contractor shall adhere to this schedule unless written permission to the contrary is given by the Borough.

01010-2

B. ALL WORK MUST COMPLY WITH THE CONTRACT SCHEDULE

AND MILESTONE DATES OUTLINED IN SECTION 01001.

1.5 CONTRACTOR'S RESPONSIBILITIES

A. The Contractor shall be responsible for all costs, including temporary power, water, telephone, testing services, road opening permits in local roads, construction permits, and licenses.

1.6 PROTECTION OF WORK AND PROPERTY

A. Contractor shall protect and maintain existing structures, access to existing homes and driveways, equipment and new construction (unless otherwise specified) in an undisturbed condition during the contract period.

B. Contractor shall provide adequate protection for the public, the Borough, and their employees during the contract period. Provide protective devices and equipment for protection of people and property. Protective measures shall comply with the

Occupational Safety and Health Administration (OSHA) and other codes having jurisdiction.

C. The Contractor shall provide adequate protection against injury or loss arising in connection with this Contract for all their work and the property of the Borough.

He shall make good any such damage, injury or loss. He shall adequately protect adjacent property as provided by law and the specifications and drawings. He shall provide facilities for protection required by public authority or local conditions as passageways, guard fences, lights, etc.

1.7 CLEAN-UP

A. Each Contractor shall periodically remove waste so that at no time shall there be undue accumulation in the work area. Upon completion of the work, the

Contractor shall remove from the project and adjacent property, all surplus and discarded materials, equipment and temporary structures and leave the premises broom clean.

B. A final cleaning inspection shall be made by the Engineer. The Contractor shall perform any additional cleaning as required by the Engineer.

1.8 TIME OF THE ESSENCE

A. Time is of the essence in the performance of the Work required by this Contract.

No extensions of time will be granted for rain days, snow days or cold weather.

1.9 COPIES OF DOCUMENTS

01010-3

A. Furnished Copies: Contractor will be furnished at no cost to them a maximum of three (3) sets of full-size Contract Drawings, (in addition to as-built set) including revised drawings, and a maximum of three (3) copies of the Contract

Specifications in addition to those used in the execution of the Agreement.

B. Additional Copies: Additional copies of the above documents will be supplied with the Contractor paying for printing, handling and delivery cost upon receipt.

1.10 RELATED DOCUMENTS

A. The Contractor shall adhere to the rules, regulations and requirements of all state, county and local permits and/or approvals issued for this project. Permitting agencies must be notified by the Contractor prior to construction per the requirements of the permits.

1.11 WORK WITHIN PRIVATE PROPERTY RIGHT-OF-WAY

A. The Contractor's construction operations, equipment, materials and any other such items shall not leave the permanent and temporary construction right-of-ways without the written permission of the property Owner and Engineer.

B. The Contractor shall neither damage nor destroy any trees or shrubs not located in the permanent right-of-way. Any trees or shrubs damaged or destroyed that are located outside of the permanent right-of-way shall be replaced in kind by the

Contractor at no additional cost to the Borough.

C. Contractor shall restore all disturbed areas as specified herein.

1.12 CONSTRUCTION STAKEOUT

A. The Contractor shall perform all construction stakeout required for the installation of the facilities, using the information provided on the drawings.

B. The Contractor shall provide the Engineer with one (1) copy of the cut sheets.

END OF SECTION