About this file

This is an Administrative Specifications document for Measurement and Payment issued by the Borough of West Conshohocken, Pennsylvania, for the MacKenzie Park Workout Stations Phase 2E project. The project involves the furnishing of all labor, materials, tools, and equipment to perform installation of workout stations equipment along an existing walking trail within MacKenzie Park. The contract includes two base bid items: Item 1.01 requires the provision and installation of work-out equipment at six locations as a lump sum price, and Item 1.02 requires the provision and installation of a MONTCO project sign at the park entrance as a lump sum price. Sealed bids are due by 11:00 A.M. on December 4, 2026, with bids submitted online through PennBid. Project documents are available for inspection at 112 Ford St., West Conshohocken, PA 19428, and hard copies may be purchased through PennBid for an estimated cost of $100.00. No bidder may withdraw a bid within sixty days after the scheduled closing time.

Payment will be made based on the actual quantities and measurements of work incorporated into or made necessary by the project, as verified by the Engineer. All lump sum prices must include the cost of materials, labor, equipment, proper disposal of existing materials removed, and all incidental work. Each proposal must be accompanied by a certified check or bid bond in an amount of not less than ten percent of the bid. The successful bidder will be required to furnish Performance and Labor and Material Bonds in one hundred percent of the contract amount, a Maintenance Bond in twenty-five percent of the total contract price, and a Certificate of Insurance. The project must comply with Pennsylvania Prevailing Wage requirements. Payment will not be made for products wasted, disposed of improperly, determined unacceptable, placed beyond required lines and levels, remaining on hand after completion, or for loading, hauling, and disposing of rejected products.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01025-1

SECTION 01025

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Measurement and payment criteria applicable to the Work performed under a Unit

Price payment method and stipulated Lump Sum method.

B. Defect assessment and non-payment for rejected work.

1.2 AUTHORITY

A. Measurement methods delineated in the individual specification sections, if any, are intended to complement the criteria of this section.

B. The Contractor shall take all measurements and compute quantities. The Engineer will verify measurements and quantities.

1.3 UNIT QUANTITIES SPECIFIED

A. Quantities and measurements indicated in the Form of Proposal are for bidding and contract purposes only. Quantities and measurements supplied or placed in the Work and verified by the Engineer shall determine payment.

B. If the actual Work requires more or fewer quantities than those quantities indicated, provide the required quantities at the unit or lump sum prices contracted.

1.4 MEASUREMENT OF QUANTITIES

A. Stipulated Lump Sum or Unit Price Measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as a completed item or unit of the Work.

1.5 PAYMENT

01025-2

A. Payment Includes: Full compensation for all required supervision, labor, products, tools, equipment, plant, transportation, services and all incidental work; erection, application or installation of an item of the Work; overhead and profit.

B. Final payment for Work governed by Lump Sum prices will be made on the basis for Work which is incorporated in or made necessary by the Work.

1.6 DEFECT ASSESSMENT

A. Replace the Work, or portions of the Work, not conforming to specified requirements.

1.7 NON-PAYMENT FOR REJECTED PRODUCTS

A. Payment will not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products placed beyond the lines and levels of the required Work.

4. Products remaining on hand after completion of the Work.

5. Loading, hauling, and disposing of rejected Products.

PART 2 GENERAL

2.1 GENERAL

A. Payment for materials furnished and work done under this contract will be made as hereinafter stipulated for the amount of materials furnished and work performed under authorization of Engineers, or their authorized representative, and in accordance with their measurements. Contractor shall not be entitled to receive additional compensation for any work or materials except as shall be authorized by written order of the Owner.

B. The following items, classifying the various kinds of work, refer to respective items bid in the "Form of Proposal".

BASE BID – Bid Item 1.01

Item 1.01 Provide and install work out equipment at 6 locations – Payment will be made at the Lump Sum unit price listed in the “Form of Proposal”. Lump Sum price bid shall include the cost of all, materials, labor and equipment, proper disposal of the existing materials removed, and all other work intended and incidental thereto as shown and noted on the plans and specifications.

01025-3

BASE BID – Bid Item 1.02

Item 1.02 Provide and install the MONTCO project sign at the entrance of the park –

Payment will be made at the Lump Sum unit price listed in the “Form of Proposal”. Lump

Sum price bid shall include the cost of all, materials, labor and equipment, proper disposal of the existing materials removed, and all other work intended and incidental thereto as shown and noted on the plans and specifications.

END OF SECTION