13-2.3 ADMIN SPECS 01201 Preconstruction Conference.pdf

PDF 32 KB Posted

Attached to
MacKenzie Park Workout Stations Phase 2E
Solicitation number
US.262761
Issued by
Montgomery County, Pennsylvania

About this file

This is an administrative specification document for preconstruction conference procedures related to the MacKenzie Park Workout Stations Phase 2E project in the Borough of West Conshohocken, Pennsylvania. The preconstruction conference will be conducted by the Engineer to clarify construction contract administration procedures and must be held within ten working days after contract execution but prior to the actual start of work. The conference requires attendance by authorized representatives of the Contractor and major subcontractors, with the Engineer advising other interested parties including the Borough. Contractors must advise the Engineer at least twenty-four hours in advance of any items to be added to the conference agenda. The Engineer will compile and distribute three copies of the conference minutes to the Contractor and required copies to the Borough.

The minimum conference agenda will address organizational arrangements of Contractor forces and subcontractors, communication channels and procedures, construction schedule and critical work sequencing, contract documents and drawing distribution, processing of shop drawings and submittals, field decisions and change order procedures, work performance rules and regulations, and procedures for safety, first aid, security, quality control, and housekeeping. Conference attendees must possess the authority to commit their respective entities to solutions and agreements reached during the meeting. No pricing terms, set-asides, or specific funding information is detailed in this administrative specification section.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01201-1

SECTION 01201

PRECONSTRUCTION CONFERENCE

PART 1 GENERAL

1.1 DESCRIPTION

A. Work included: To help clarify construction contract administration procedures, the Engineer will conduct a Preconstruction Conference prior to start of the Work.

Provide attendance by the designated personnel.

B. Related Work:

1. Documents affecting work of this Section include, but are not necessarily limited to, General Conditions, Supplementary Conditions, and Sections in

Division 1 of these Specifications.

1.2 QUALITY ASSURANCE

A. For those persons designated by the Contractor, his subcontractors, and suppliers to attend the Preconstruction Conference, provide required authority to commit the entities they represent to solutions agreed upon in the Conference.

1.3 SUBMITALS

A. To the maximum extent practicable, advise the Engineer at least twenty-four (24) hours in advance of the Conference as to items to be added to the agenda.

B. The Engineer will compile minutes of the Conference, and will furnish three copies of the minutes to the Contractor and required copies to the Borough. The

Contractor may make and distribute such other copies as he wishes.

1.4 PRECONSTRUCTION CONFERENCE

A. The Conference will be scheduled to be held within ten (10) working days after the Borough has executed the Contracts, but prior to actual start of Work.

B. Attendance:

1. Provide attendance by authorized representatives of the Contractor and major subcontractors.

01201-2

2. The Engineer will advise other interested parties, including the Borough, and request their attendance.

C. Minimum agenda: Data will be distributed and discussed.

1. Organizational arrangement of Contractor's forces and personnel, and those of subcontractors, materials, suppliers, and the Engineer.

2. Channels and procedures for communication.

3. Construction schedule, including sequence of critical work.

4. Contract Documents, including distribution of required copies of

Drawings and revisions.

5. Processing of Shop Drawings and other data submitted the Engineer for review.

6. Processing of field decisions and Change Orders.

7. Rules and regulations governing performance of the Work.

8. Procedures for safety and first air, security, quality control, housekeeping, and related matters.

END OF SECTION