11-2.6 ADMIN SPECS 01720 Project Record Documents.pdf
PDF 44 KB Posted
- Attached to
- MacKenzie Park Workout Stations Phase 2E
- Solicitation number
- US.262761
- Issued by
- Montgomery County, Pennsylvania
About this file
This file is an administrative specification section (01720) detailing project record document requirements for the MacKenzie Park Workout Stations Phase 2E project in West Conshohocken, Pennsylvania. The specification establishes mandatory procedures for maintaining comprehensive documentation throughout the construction phase, including one copy each of contract drawings, specifications, amendments, change orders, shop drawings, product data, and field test records. The contractor must maintain these documents in clean, dry, and legible condition at the job site, organized according to Construction Specifications Institute (CSI) filing standards, and make them available for inspection at all times. Documentation must be recorded concurrently with construction progress, with particular attention to marking actual locations of underground utilities and appurtenances, field changes, supplemental instructions, and change order modifications. No work shall be concealed until required information is recorded.
Upon project completion, the contractor must submit one marked set of contract drawings showing all notations, two copies of annotated shop drawings and product data sheets, and two sets of all other project record documents, accompanied by a transmittal letter certifying completeness and accuracy. All submittals must be signed by the contractor or authorized representative and include the project title and number. The specification does not establish pricing terms, set-asides, or funding requirements, as it functions solely as a technical administrative requirement within the broader project specifications for the installation of workout station equipment along MacKenzie Park's existing walking trail.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01720-1
SECTION 01720
PROJECT RECORD DOCUMENTS
PART 1 GENERAL
1.1 MAINTENANCE OF DOCUMENTS
A. Maintain at job site, one copy of record documents including Drawings, Specification, Amendments, Change Orders and other modifications, Shop Drawings, product date and samples.
B. In addition, maintain one copy of field orders or written instructions and field test records.
C. Provide files and racks for storage documents.
D. File documents and samples in accordance with Data Filing Format of the Construction Specifications Institute (C.S.I).
E. Maintain documents in a clean, dry, legible condition and in good order. Do not use record documents for construction purposes.
F. Make Documents and samples available at all times for inspection.
1.2 RECORDING
A. Label each document "Project Record" in neat large letters.
B. Record information concurrently with construction progress.
C. Do not conceal any work until required information is recorded.
D. Drawings - Legibly mark to record actual construction:
1. Horizontal and vertical locations of laterals, underground utilities and appurtenances, referenced to permanent surface improvements.
2. Field changes of dimension and detail.
3. Changes made by Supplemental Instruction or by Change Order.
4. Details not on original Contract Drawings.
01720-2
E. Specifications and Amendments - Legibly mark each Section to record
1. Manufacturer, trade name, catalog number, and Supplier of each Product and item of equipment actually installed.
2. Changes made by Supplemental Instructions or by Change Order.
F. Shop Drawings - Maintain as record documents. Legibly annotate any changes made after review.
1.3 SUBMITTALS
A. At completion of the Work, furnish one set of drawings showing all notations specified above. A copy of the Design Professional's drawings may be used for this purpose upon reimbursement of the printing costs to the Design Professional. In addition, furnish two copies of any shop drawings or product data sheet which required annotation after approval.
B. After inclusion of additional data, if any, furnish:
1. One set of contract drawings as specified under 1.3, A. above.
2. Two sets of all other Project Record Documents.
C. Accompany this final submittal with transmittal letter containing data, project title and number, Contractor's name and address, title and number of each Record Document, certification that each document as submitted as complete and accurate, signature of Contractor or his authorized representative.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION