14-2.4 ADMIN SPECS 01340 Shop Drawings and Samples.pdf
PDF 33 KB Posted
- Attached to
- MacKenzie Park Workout Stations Phase 2E
- Solicitation number
- US.262761
- Issued by
- Montgomery County, Pennsylvania
About this file
This is an administrative specification document for shop drawings, product data, and samples submissions applicable to the MacKenzie Park Workout Stations Phase 2E project in West Conshohocken, Pennsylvania. The specification establishes submission requirements for contractors to provide shop drawings, product data, and instruction manuals as required by the contract documents. All submittals must be made electronically in a clear and thorough manner, with shop drawings identified by reference to contract drawings and product data clearly marked to identify pertinent products or models, including performance characteristics, capacities, dimensions, and clearances. Submittals must be made promptly according to an approved schedule and must include specific information such as submission dates, project title, contract number, contractor and supplier names, product identification with specification section numbers, applicable standards, identification of deviations from contract documents, and an eight-inch by three-inch blank space for contractor and engineer stamps. The contractor must certify review of submittals, verification of products, field measurements, field construction criteria, and coordination with contract requirements.
The specification requires contractors to resubmit any shop drawings or product data with corrections or changes as directed by the engineer, with revisions clearly indicated on resubmittals. The document does not establish pricing terms, set-asides, or funding information, as it functions solely as an administrative specification governing the submission and approval process for project-related materials. No response deadlines, award dates, or contract term information are specified within this document, as those details are contained in the main bid solicitation for the MacKenzie Park Workout Stations Phase 2E project with a sealed bid deadline of December 4, 2026, at 11:00 A.M.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01340-1
SECTION 01340
SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
PART 1 GENERAL
1.1 WORK INCLUDED
A. Submit Shop Drawings, Product Data, and Instruction Manuals required by Contract
Documents.
1.2 RELATED REQUIREMENTS
A. Definitions, and Additional Responsibilities of Parties: Conditions of the Contract.
1.3 SHOP DRAWINGS
A. Drawings shall be presented in a clear and thorough manner.
1. Details shall be identified by reference to sheet and detail, shown on
Contract Drawings.
1.4 PRODUCT DATA
A. Preparation
1. Clearly mark each copy to identify pertinent products or models.
2. Show performance characteristics and capacities.
3. Show dimensions and clearances required.
1.5 SUBMISSION REQUIREMENTS
A. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor.
B. Number of Submittals Required:
1. Shop Drawings: Submit electronically.
2. Product Data: Submit electronically.
C. Submittals Shall Contain:
01340-2
1. The date of submission and the dates of any previous submissions.
2. The Project title and contract number.
3. The names of:
a. Contractor.
b. Supplier.
c. Manufacturer.
4. Identification of the product, with the specification section number.
5. Applicable standards, such as ASTM or Federal Specification numbers.
6. Identification of deviations from Contract Documents.
7. Identification of revisions on resubmittals.
8. An 8 in. x 3 in. blank space for Contractor and Engineer stamps.
9. Contractor's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the Work and of Contract Documents.
1.6 RESUBMISSION REQUIREMENTS
A. Make any corrections or changes in the submittals required by the Engineer and resubmit until approved.
B. Shop Drawings and Product Data:
1. Revise initial drawings or data, and resubmit as specified for the initial submittal.
2. Indicate any changes which have been made other than those previously noted by the Engineer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION