This document is a Price/Cost Schedule for a construction project at the Beverly National Cemetery in New Jersey. The solicitation (Project No. 804CM3021) covers repairs and improvements to the Administration Building and Rostrum, which is a historic site. The pricing schedule includes three line items:
- Base Contract (Item 0001): Administration Building and Rostrum Repairs & Improvements
- Option 01 (Item 0002): New Concrete Floor at Rostrum
- Option 02 (Item 0003): New Drywell & Associated Other Work
The contractor is required to provide all labor, tools, materials, equipment, services, testing, submittals, approvals, and professional supervision. The work will be completed in accordance with the Scope of Work (SOW), Specifications, and Drawings. The document is part of a solicitation by the Department of Veterans Affairs National Cemetery Administration, with bidders expected to fill in unit prices and total amounts for each line item.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
?.## PRICE/COST SCHEDULE
Contractor shall provide all labor, tools, materials, equipment, services, testing. submittals, approvals, and professional supervision related work for the Construction Project, Under Project No. 804CM3021; ADMINSTRATION BUILDING ROSTRUM REPAIRS & IMPROVEMENT (HISTORIC SITE), located at the Beverly National Cemetery, NJ. The work Shall be completed In Accordance With (IAW) the Scope of Work (SOW), Specifications, Drawings, and this Solicitation.
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 BASE CONTRACT:
Base BID: Administration
Building and Rostrum Repairs
& Improvements
1. JB $_____________ $_____________
0002 Option 01:
New Concrete Floor at Rostrum. 1. JB $_____________
0003 Option 02:
New Drywell & Associated Other Work 1. JB $______________
TOTAL PRICE