This document is an Amendment (A0004) to an Invitation for Bid (IFB) for repairs and improvements at Beverly National Cemetery in Beverly, New Jersey. The project, numbered 804CM3021, involves renovation work on the Administration Building and Rostrum, which is a historic site. The amendment includes a comprehensive set of responses to Request for Information (RFI) questions covering various aspects of the project, such as permitting, work constraints, utility handling, staging areas, and specific construction details.
The solicitation is issued by the Department of Veterans Affairs National Cemetery Administration, with the contract (36C78625B0007) seeking a contractor to perform historic site repairs. Key project requirements include replacing windows, conducting roof work, managing electrical systems, and coordinating construction activities around cemetery operations. The amendment clarifies technical specifications, confirms no environmental impact, establishes work hour constraints, and provides guidance on handling existing site conditions. No specific subcontractors are required, and the project involves careful restoration of a historic site with minimal disruption to cemetery functions.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) A0004 03-10-2025
804CM3021
36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle
VA
22172 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle
VA
22172 To all Offerors/Bidders
36C78625B0007 01-06-2025 A0004
X X X X AMENDMENT (A0004) | Beverly National Cemetery | IFB No.36C78625B0007 | Project No. 804CM3021 The Purpose of Amendment (A0004) is to Notify the Public of the Government's Response to an RFI detailed, started on Page #2 for IFB No. 36C78625B0007 under Project No. 804CM3021.
**All Factors & Content of This IFB Solicitations remains the Same** Sheryl Palacio-Davis Contracting Officer
CONTINUATION PAGE
AMENDMENT A0004:
Beverly National Cemetery | IFB Solicitation No. 36C78625B0007 | Project No. 804CM3021 | Administration Building and Rostrum Repairs/Improvements (Historic Site).
· CEMETERY’S ADDRESS:
Beverly National Cemetery 916 Bridgeboro Road.
Beverly, NJ 08010
Amendment A0004 is the Response to RFI’s Questions and Answers to the Public for Beverly National Cemetery, under Project No. 804CM3021 as Follows:
RFI QUESTIONS & ANSWERS
· Please confirm if any permits are required for this project.
Generally, for a project on Government land permits are not required other than environmental permits, this project will have no environmental impact since it is mainly a historic renovation type project, that being said check with the local building permit office to confirm no-permits are required for federally owned historic renovation project.
· What are the procedures for halting work during burial services, and how much advance notice will be given?
Read SOW, 4.2
· Are there specific working hours or operational constraints, especially regarding visitor access and burial ceremonies?
Read SOW, 4.1
· Are there any as-built drawings available to aid in verifying existing conditions, or should discrepancies be assumed and addressed via additional RFIs?
I have 1957 drawing for the Administration Building, 1938 drawings for the rostrum, and 1997 drawings for the Admin. Renovation projects. The design team was working with these to generate this bid set.
· What is the preferred method for handling unknown or unverified underground utilities? Should additional geophysical surveys such as New Jersey One Call be conducted?
This is means and methods, not for me to answer, typically call before you dig, common sense.
· Is there a designated staging area for materials?
This can be coordinated with cemetery staff, we will designate a space for staging, the last project used the cul-de-sac and garage building adjacent to the historic lodge.
· If unsuitable material is encountered during excavation, what is the process for remediation?
Not likely to happen unless contractor is fishing for a mod pre-bid!
· The drawings state "assume 100 SF" of roof sheathing replacement. Can we confirm that any additional sheathing replacement beyond this quantity is outside the scope of work?
The construction scope includes 100 SF of sheathing if required.
· Are there any specific constraints on how water should be discharged from the new gutters and downspouts?
All downspouts get elbow and extension to new splash blocks that will direct water away from building, some minor regrading may be required to make this work.
· The drawings indicate replacing some windows while refinishing others. Can the government provide a schedule or confirmation on which windows require full replacement versus refinishing that is more detailed than the one on A601?
All windows are to be replace except those flanking the main entry door, see A-101, look at the drawings.
· The concrete specifications reference ASTM standards for testing concrete , but there is no mention of soil testing requirements for the subbase. Can the government confirm if soil compaction testing is required prior to concrete placement?
Of course, any time to place concrete on soil and sub-base it needs to be compacted and tested for that compaction.
· The specifications require field verification of existing conditions, including routing for electrical conduits. If conflicts arise with existing utilities, does the government have a preferred rerouting plan, or should we propose an alternative?
Means and methods, typically a contractor would locate and mark existing utility lines in the areas of new work by whatever means required. If conflicts between existing to remain and new work to be placed, they will have to be resolved on site during construction by the construction and design team.
· The spec references flashing and sheet metal requirements under Section 07 60 00 . Can the government confirm whether new flashing is required at all roof transitions, or are existing flashing elements to be reused where possible?
A new roof requires all new roof accessories, this includes all new flashing, drips, pipe boots, etc. Your roofer is going to be up there with a demolition shovel, need I say more. Scope is pretty clear on A-102.
· Are there existing panel schedules available to confirm if the new electrical loads (lighting, HVAC fans, etc.) can be accommodated without modifications to the service panel?
We are not increasing the existing electrical load.
· The documents mention coordinating active rooftop utilities during roofing work. Please confirm that the exhaust vent protruding from the roof is the only roof utility to account for.
Contractors are welcome to visit the site any time to verify field conditions during open hours, all we ask is that you call Washington Crossing National Cemetery and tell then when you plan to visit and what you will be doing at Beverly National Cemetery.
· Are there any nominated/required subcontractors for this project? No.
· Are there any active warranties on the admin building roof? No.
A.1 OTHER ATTACHMENTS
See attached document: A0004 - Questions and Answers - Beverly Natl Cem - Project No 804CM3021.