Am 3 - ATT 7 - G004K - PHASING PLANS.pdf
PDF 1 MB Posted
- Solicitation number
- 36C77626B0016
About this file
This document is a mechanical phasing plan for a construction project involving facility additions and utility upgrades at an existing healthcare facility. The project is structured in multiple phases designed to maintain operational continuity while construction occurs.
Phase 0 spans 90 days from Notice to Proceed and focuses on schedule development, submittals, and shop drawings approval. Phase 1 (330 days) encompasses construction of two building additions, underground utility relocation, and supporting utility upgrades. Phase 1A requires relocation of all underground utilities within 30 days, with one entrance (either Urgent Care or Main) remaining open at all times for drive-up, walking, and handicap-accessible access; the contractor must install and maintain COR-approved signage. Phase 1B (60 days) involves SPS window fill and installation of ductwork for Air Handling Units 9 and 23, requiring brief SPS closure with careful attention to maintaining AHU 23 operations. Phase 1C includes Penthouse 3334 construction, power routing, and basement preparation for breakthrough work. Phase 2 (190 days) incorporates breakthrough into the existing facility with major disruptions to pharmacy and police areas. Phase 2A requires pharmacy breakthrough and finishing work within 90 days while maintaining full pharmacy operations with minimal disruption. Phase 2B addresses police breakthrough and remaining work. The contractor must coordinate all phasing, scheduling, demolition, and MEP sequences with the owner and all project trades prior to construction commencement and submit a phasing/sequence coordination plan for owner review and approval.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UP
UP
UP
UP
MECHANICAL PHASES AT PHASE 1
GENERAL NOTES:
1. BOUNDARY FOR PHASES =
2. COORDINATE AND SCHEDULE ALL PROJECT PHASING WITH OWNER PRIOR TO THE
START OF CONSTRUCTION.
3. COORDINATE TIMES AND DATES OF DEMOLITION AND NEW WORK WITH OWNER.
4. SUBMIT A PHASING/SEQUENCE COORDINATION PLAN FOR OWNER REVIEW,
COORDINATION, AND APPROVAL PRIOR TO COMMENCEMENT OF WORK.
5. SEE CIVIL PLANS, FIRE PROTECTION PLANS, PLUMBING PLANS, MECHANICAL PLANS
AND ELECTRICAL PLANS FOR ADDITIONAL INFORMATION.
6. COORDINATE PHASING PLAN WITH ALL PROJECT TRADES
7. CONSTRUCTION AND MEP SEQUENCES WILL OCCUR IN ALL OF THE CONSTRUCTION
PHASES IN ORDER TO CONSTRUCT THE PROJECT AND ALLOW FOR PORTIONS OF THE
EXISTING SPACE TO REMAIN OPERATIONAL DURING CONSTRUCTION.
PHASE 0:
THIS INITIAL PHASE BEGINS WITH THE ISSUANCE OF THE NOTICE TO PROCEED. DURING PHASE 0, THE TEAM WILL FOCUS ON PREPARING AND APPROVING THE PROJECT SCHEDULE, AS WELL AS
REVIEWING AND SUBMITTING NECESSARY SUBMITTALS AND SHOP DRAWINGS. ALL ACTIVITIES IN
PHASE 0 MUST BE COMPLETED WITHIN 90 DAYS OF RECEIVING THE NOTICE TO PROCEED.
PHASE 1: DURATION - 330 DAYS
PHASE 1 ENCOMPASSES THE CONSTRUCTION OF TWO BUILDING ADDITIONS, RELOCATION AND
INSTALLATION OF UNDERGROUND UTILITES, AND UPGRADES TO SUPPORTING UTILITIES WITHIN
THE EXISTING FACILITY. THE PRIMARY OBJECTIVE OF PHASE 1 IS TO MAXIMIZE THE
CONSTRUCTION OF NEW SPACE AHEAD OPENING INTO THE ADDITIONS. ALL SUBSPACES MAY
BEGIN CONCURRENTLY; HOWEVER, EACH IS SUBJECT TO SPECIFIC DURATION LIMITS.
CONTRACTORS WILL HAVE A DESIGNED EXTERIOR CONSTRUCTION ZONE, AS WELL AS INTERIOR
SPACES B101 AND B201.
PHASE 1A: RELOCATION OF UNDERGROUND UTILITIES
ALL UNDERGROUND UTILITIES WILL BE RELOCATED, AND THE WORK WILL BE COMPLETED WITHIN
30 DAYS FROM THE START OF PHASE 1. DURING THIS PROCESS, EITHER THE URGENT CARE
ENTRANCE OR THE MAIN ENTRANCE WILL REMAIN OPEN AT ALL TIMES, ENSURING PATRONS HAVE
UNINTERRUPTED DRIVE-UP, WALKING, AND HANDICAP-ACCESSIBLE ENTRY. THE CONTRACTOR
WILL BE RESPONSIBLE FOR INSTALLING AND MAINTAINING CLEAR, APPROVED SIGNAGE TO GUIDE
VISITORS THROUGHOUT THE RELOCATION PERIOD. ALL SIGNAGE MUST BE REVIEWED AND
AUTHORIZED BY THE CONTACTING OFFICER'S REPRESENTATIVE (COR) PRIOR TO POSTING.
PHASE 1B: SPS WINDOW FILL, AHU 9 AND 23 DUCTING
THE SPS WINDOW FILL, ALONG WITH THE INSTALLATION OF DUCTWORK FOR AIR HANDLING UNITS (AHU) 9 AND 23, WILL BE COMPLETED WITHIN 60 DAYS FROM THE START OF PHASE. THERE WILL
BE A BRIEF CLOSURE THE SPS TO ALLOW FOR THE CHANGEOVER, ENSURING MINIMAL
DISRUPTION TO OPERATIONS. SINCE AHU 23 SERVES THE SPS AND IS ESSENTIAL TO ITS
FUNCTION, EXTRA CARE WILL BE TAKEN TO MAINTAIN CRITICAL SERVICES THROUGHOUT THE
PROCESS.
1C: PENTHOUSE 3334 CONSTRUCTION AND POWER ROUTING
THE CONTRACTOR WILL CONSTRUCT PENTHOUSE 3334 AND ROUTE POWER TO THE NEW
PENTHOUSE. IN THE BASEMENT AREA, PREPARATIONS WILL BE MADE FOR CONTRACTORS TO
BUILD THE ADDITIONS AND COMPLETE AS MUCH INTERIOR WORK AS POSSIBLE BEFORE THE
BREAKTHROUGH INTO EXISTING SPACES. NEW CONSTRUCTION WILL BE STRATEGICALLY
SCHEDULE TO MINIMIZE THE SCOPE AND IMPACT OF BREAKTHROUGH ACTIVITIES AND WORK
WITHIN THE EXISTING FACILITY.
PHASE 2: DURATION - 190 DAYS
PHASE 2 WILL INCORPORATE BREAKTHROUGH INTO EXISTING FACILITY, MAJOR DISRUPTION TO
THE PHARMACY, POLICE, AND ALL OTHER AREAS ON THE NORTH SIDE OF THE BUILDING. THE
INTENT OF PHASE 2 IS TO INCORPORATE THE NEW AND EXISTING FACILITY ENSURING THAT THE FINAL CONNECTIONS ARE MADE SWIFTLY AND EFFICIENTLY TO MINIMIZE DISRUPTIONS FOR STAFF
AND PATRONS.
2A: PHARMACY BREAKTHROUGH AND FINISHING TOUCHES
ALL WORK RELATED TO PHARMACY BREAKTHROUGH AND FINAL FINISHES WILL BE COMPLETED
WITHIN THE FIRST 90 DAYS OF PHASE 2. THROUGHOUT THIS PERIOD, THE PHARMACY WILL
REMAIN FULLY OPERATIONAL AND OCCUPIED, WITH MINIMAL DISRUPTION TO DAILY ACTIVITIES.
THE TRANSITION WILL BE CAREFULLY MANAGED TO ENSURE A SMOOTH AND SEAMLESS
EXPERIENCE FOR STAFF AND PATRONS.
2B: POLICE BREAKTHROUGH AND REMAINING WORK
THE NEXT STAGE INVOLVES THE POLICE BREAKTHROUGH AND COMPLETION OF ALL REMAINING
TASKS ASSOCIATED WITH PHASE 2. THIS PHASE WILL BE EXECUTED EFFICIENTLY, COORDINATING
WITH KEY STAKEHOLDERS TO MINIMIZE OPERATIONAL IMPACT AND ENSURE SAFETY
THROUGHOUT THE PROCESS.
PHASES:
MECH.
B231A
BULK MEDICAL
STORAGE
B231D
MECH.
B231C
STORAGE
LOGISTICS
B231MECH.
B231B
ETO
B291C
UNISEX
BREAKROOM
B228
MENS SHOWER
B228C
LOCKER VEST.
B228A
MENS LOCKER
B228B
MECH.
B224A
PASSAGE
B226
LAUNDRY
B230
STAIR 3
B3
CORRIDOR
B299C-1
DECONT.
B295
PREPARATION
PACKAGING
B291B
MECH.
B295A
SUPPLIES
B291
CORRIDOR
B299A-1
WAN ROOM
B105
MSA
SUPERVISORS
B107B
VESTIBULE
B107
MECH.
B107D
TELEPHONE
EQUIPMENT
B103
PASSAGE
B206
RELEASE OF
INFO
B202
MEDICAL
RECORDS
B201
CODERS
WORKSTATION
B101
CHIEF, SPS
B291A
STAIR 2 STOCK/
BREAKOUT
B287
CORRIDOR
B299B-1
CORRIDOR
B199A-1
LOCKERS
B297
STORAGE
LOGISTICS
B203
PHASE
1A
PHASE 1A: APPROXIMATE LOCATION OF
UNDERGROUND UTITLIES. ONLY ONE ENTRANCE
OUT OF SERVICE AT ANY GIVEN TIME.
PHASE 1B
PHASE 1B:
AHU 9
INLET/
EXHAUST
PHASE 1B:
AHU 23
INLET/
EXHAUST
STAFF LOUNGE
RADIOLOGY
FLUOROSCOPY
IMAGING CHIEF
EQUIP. ALCOVE
2230B
PATIENT TOILET
2242B
PACS VIEWING
CORRIDOR
2230P
ULTRASOUND
STRESS TEST
PATIENT TOILET
ULTRASOUND
TECH WORK
ROOM
PENTHOUSE
2237A
STAIR 3
1107H
STERILE CLEAN
CLEAN SUPPLY
CYSTOSCOPY
ENDOSCOPY
ENDOSCOPY
CLEAN SUPPLY
STERILE SUPPLY
RESTRICTED/
CLEAN
CORRIDOR
HOUSEKEEPING
CLOSET
OPERATING
ROOM - EAST
SCRUB
2105A
MECH. SPACE
1107J
SUB-STERILE
2101A
MEETING ROOM
MEETING ROOM
WAITING AREA
CORRIDOR
C2-8
WOMENS TOILET
STAFF WORK
AREA
2374A
CLERKS AREA
MENS TOILET
MENS TOILET
TELE-HEALTH
EXAM ROOM
TELE-HEALTH
EXAM ROOM
CT SCAN
CT SCAN
CONTROL
PATIENT TOILET
LAUNDRY CHUTE
CHASE
1107I
UTILITY
PHASE 1B PHASE 1B
PENTHOUSE
2236A
ELECTRICAL
PENTHOUSE
PHASE 1C
NORMAL POWER
HALL
MECHANICAL
ROOM
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMP
321 4 5 6 7 8 9 10
EXPAND PHARMACY AND RADIOLOGY
OSCAR G. JOHNSON VA MEDICAL CENTER
325 H STREET,
IRON MOUNTAIN, MI 49801
ARCHITECT/ENGINEER
310 Pine Street | Green Bay, WI 54301 920-432-4865 | www.bernersschober.com FULLY SPRINKLERED
KEY PLAN:
Comm. Number: 6163.03
FEBRUARY 6, 2026
585-337
U.S. Department of Veterans Affairs
BID DOCUMENTS
Revisions: Date:
CONSTRUCTION SET 05/08/2023
95% DESIGN SUBMITTAL - REDESIGN 08/23/2024
BID DOCUMENTS 02/06/2026
Au to de sk
D oc s:
//O sc ar
G J oh ns on V
A M ed ic al C en te r/O G
JA
R
C H
.rv t
6/ 4/
:0
6:
A M
DPD JAP
G004K
PHASING PLANS
DWG. 4 OF 134
N 1/16" = 1'-0"G004K
BASEMENT MECHANICAL PHASING PLANF7
N 1/16" = 1'-0"G004K
SECOND FLOOR MECHANICAL PHASING PLANF2
N 1/16" = 1'-0"G004K
THIRD FLOOR ELECTRICAL PENTHOUSE MECHANICAL PHASING PLAND2
File details come from the government source that posted it. Updated .