Am 3 - ATT 5 - 585-337 - Rev phasing plan.pdf

PDF 54 KB Posted

Attached to
Y1DA--585-337 Expand Pharmacy and Radiology (MINOR) PR 585-26-4-337-0003
Solicitation number
36C77626B0016
Issued by

About this file

This is a Revised Phasing Plan for a construction project at Oscar G Johnson VAMC involving the expansion of pharmacy and radiology facilities (Project 585-337). The total project duration is 610 calendar days, divided into four sequential phases with specific duration limits and operational constraints.

Phase 0 (90 days from Notice to Proceed) focuses on project schedule preparation, approval, and submission of necessary submittals and shop drawings. Phase 1 (330 days) encompasses construction of two building additions, relocation and installation of underground utilities, and utility upgrades within the existing facility. Phase 1 is subdivided into three concurrent subphases: 1A—Relocation of Underground Utilities (30 days) with requirements to maintain continuous public access via urgent care or main entrance and install COR-approved signage; 1B—SPS Window Fill and AHU 9 and 23 Ducting (60 days) with brief SPS closure and emphasis on maintaining critical services; and 1C—Penthouse 3334 Construction and Power Routing with advance basement preparations to minimize breakthrough impacts. Phase 2 (120 days) involves breakthrough into the existing facility with major disruption to pharmacy, police, and north-side building areas. Phase 2A (60 days) addresses pharmacy breakthrough and finishing touches while maintaining full pharmacy operations with minimal disruption. Phase 2B addresses police breakthrough and completion of all remaining Phase 2 tasks, coordinated with key stakeholders to minimize operational impact and ensure safety. The plan emphasizes maintaining critical facility operations throughout all construction phases and requires contractor responsibility for public safety and facility signage management.

View the file

Other files

File Type Posted
Am 7 - Att 1 - 585-337 Prebid RFIs 061626.pdf PDF
36C77626B0016 0007.pdf PDF
Am 6 - Att 1 - Wage Rate 051826.pdf PDF
36C77626B0016 0006.pdf PDF
Am 5 - Att 1 - 585-337 Prebid RFIs 061526_.pdf PDF
36C77626B0016 0005.pdf PDF
36C77626B0016 0004.pdf PDF
Am 4 - Att 1 - Addendum 3 Documents - 2026-05-14 1.pdf PDF
36C77626B0016 0003.pdf PDF
Am 3 - ATT 1 - 585-337 Prebid RFIs 060826.pdf PDF
Am 3 - ATT 9 -097216-585-337 reissue.pdf PDF
Am 3 - ATT 10 - Site Plan Laydown.pdf PDF
Am 3 - ATT 3 - 585-337 - ADD 2.pdf PDF
Am 3 - ATT 4 - 585-337 - ADD 3.pdf PDF
Am 3 - ATT 8 - 014535-585-337 Spec.pdf PDF
Am 3 - ATT 2 - 585-337 - ADD 1.pdf PDF
Am 3 - ATT 6 - G003K PHASING PLANS.pdf PDF
Am 3 - ATT 7 - G004K - PHASING PLANS.pdf PDF
Amend 2 - ATT 1 - WR Determination 051326.pdf PDF
36C77626B0016 0002.pdf PDF
Amend 2 - ATT 2 - 52.222-90.pdf PDF
Amendment 1 - ATT 2 - Site Visit Agenda 585-337.pdf PDF
Amendment 1 - ATT 1 - 585-337 Site visit sign in.pdf PDF
36C77626B0016 0001.pdf PDF
Attachment 02 - Drawings_Iron Mountain.pdf PDF
Attachment 06 - ICRA Pharamcy and Radiology 585-337 15Dec2025.pdf PDF
Attachment 08 - Site Visit - Iron Mountain.pdf PDF
Attachment 03 - Brand Name Justification - Iron Mountain_redacted.pdf PDF
Attachment 05 - PCRA Pharamcy and Radiology 585-337 15Dec2025.pdf PDF
Attachment 01 - Specifications_Iron Mountain_030526.pdf PDF
Attachment 04 - Limitations on Subcontracting - Iron Mountain.pdf PDF
36C77626B0016.pdf PDF
Attachment 07 - Wage Rate Determination - Iron Mountain.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

585-337 Expand Pharmacy and Radiology

Revised Phasing Plan

Oscar G Johnson VAMC

Total Project Duration: 610 calendar days

Phase 0: This initial phase begins with the issuance of the Notice to Proceed. During Phase 0, the team will focus on preparing and approving the project schedule, as well as reviewing and submitting necessary submittals and shop drawings. All activities in Phase 0 must be completed within 90 days of receiving the Notice to Proceed.

Phase 1: Duration – 330 days

Phase 1 encompasses the construction of two building additions, relocation and installation of underground utilities, and upgrades to supporting utilities within the existing facility. The primary objective of Phase 1 is to maximize the construction of new space ahead opening into the additions. All subphases may begin concurrently; however, each is subject to specific duration limits. Contractors will have a designated exterior construction zone, as well as interior spaces B101, B201, B202, and B203. Note that no work is scheduled within Rooms B101 or B201, however they will be available to the Contractor for use at the Start of Phase 1 and shall be restored to the existing condition when the project is complete.

1A: Relocation of Underground Utilities — All underground utilities will be relocated, and the work will be completed within 30 days from the start of Phase 1. During this process, either the urgent care entrance or the main entrance will remain open at all times, ensuring patrons have uninterrupted drive-up, walking, and handicap-accessible entry. The contractor will be responsible for installing and maintaining clear, approved signage to guide visitors throughout the relocation period. All signage must be reviewed and authorized by the Contracting Officer’s Representative (COR) prior to posting.

1B: SPS Window Fill, AHU 9 and 23 Ducting

The SPS window fill, along with the installation of ductwork for Air Handling Units (AHU) 9 and 23, will be completed within 60 days from the start of Phase 1. There will be a brief closure of the SPS to allow for the changeover, ensuring minimal disruption to operations.

Since AHU 23 serves the SPS and is essential to its function, extra care will be taken to maintain critical services throughout the process.

1C: Penthouse 3334 Construction and Power Routing

The contractor will construct Penthouse 3334 and route power to the new penthouse. In the basement area, preparations will be made for contractors to build the additions and complete as much interior work as possible before the breakthrough into existing spaces.

New construction will be strategically scheduled to minimize the scope and impact of breakthrough activities and work within the existing facility.

Phase 2: Duration – 120 days

Phase 2 will incorporate breakthrough into existing facility, major disruption to the Pharmacy, Police, and all other areas on the north side of the building. The intent of phase 2 is to incorporate the new and existing facility ensuring that the final connections are made swiftly and efficiently to minimize disruptions for staff and patrons.

2A: Pharmacy Breakthrough and Finishing Touches

All work related to the pharmacy breakthrough and final finishes will be completed within the first 60 days of Phase 2. Throughout this period, the pharmacy will remain fully operational and occupied, with minimal disruption to daily activities. The transition will be carefully managed to ensure a smooth and seamless experience for staff and patrons.

2B: Police Breakthrough and Remaining Work

The next stage involves the police breakthrough and completion of all remaining tasks associated with Phase 2. This phase will be executed efficiently, coordinating with key stakeholders to minimize operational impact and ensure safety throughout the process.