Responses to Technical Questions_Murfreesboro EHRM 8_19_2025.pdf
PDF 923 KB Posted
- Attached to
- Z2DA--626A4-22-700 EHRM Infrastructure Upgrades Construction Murfreesboro, TN Federal contract opportunity
- Solicitation number
- 36C77625R0066_1
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND SOLICITATION #: 36C77625R0066
RESPONSES TRACKING SHEET PROJECT TITLE: EHRM Infrastructure Upgrades Construction
# RECEIVED ANSWERED CONTRACTOR QUESTION VA RESPONSE
1 Confirmation of Grounding Bus Bar Installation Responsibility (Section 26-05-26 – Grounding and Bonding for Electrical Systems)
(Drawing No. TG-100 – Item #6 - Typical Flush Outlet Mounting) Keynotes denotes Provide by Electrical Installer. We want to confirm the Electrical contractor will be responsible for the installation and testing of Grounding Bus Bars for all rooms and areas where required.
The General Contractor is responsible for all requirements under the contract documents. How they choose to sub-contract and assign the work is a means and methods question.
2 Confirmation of Outside Fiber Optic cabling type (Section 27-13-23 – Communications Optical Fiber Backbone Cabling)
Section 26-05-226, Part 2 Products, paragraph 2.2 states - Single mode fiber optic backbone cables are specified for inside and outside plant (OSP) use. We want to confirm outdoor armored rated fiber optic cabling is being specified here.
Confirmed, armor rated cables are required due to exposed routes through building crawl spaces. The alternative would require conduit runs through utility and crawls spaces.
3 Fiber Optic Site Plan (00-CG-001 to 00-CS-302)
Along with the provided site drawings, can any up-to-date information be provided on the conditions of the existing campus outside plant (OSP) backbone interbuilding pathways such hazards, flooding issues, structural stability, etc. for access points, manholes, crawlspaces, ducts, underground vaults, and conduits?
All available information is in the Bid Documents
4 Has the VAProgram Manager (PM) for the Murfreesboro VA (EHRM) Infrastructure Upgrade developed a system cutover and transition plan that will address the following:
1. Limitingand coordinating end-users’ and stakeholders’ outages and service interruptions.
2. Transitioning network systems hardware and components by sections, functions,operations, and
3. Having routine detailed pre-transition coordination meetings withend-users and stakeholders educating them on the upgrade and addressing their concerns and questions.
4. Ensuring infrastructure network systemtransitions are conducted outside of normal business operating hours such as weekends and afterhours.
5. Ensuring infrastructure transition prerequisites stepsare completed prior to cutover.
6. Ensuring system rollback plansare developed prior to any system transition.
This plan will be developed by local and National OIT support teams at a later date.
5 Drawings 001-T-11- through 001-T-151 have new data work are outlets (WAO) on them with the amount of cables to each one. Also Drawing # 001-T-405 has a list of all WAO locations with quantity of cables. The 2 items do not show the same quantity of cables to be installed. Which of the drawings takes precedence?
See bid schedule for quantities.
6 We respectfully request that the Government revise or clarify the evaluation language to account only for contractor-initiated cost growth when applying the 7.5% threshold.
Specifically, we propose that the cost growth calculation exclude the value of Government-directed changes, contract modifications initiated by the VA, or documented changes in scope requested by the owner.
The evaluation language will not be updated. An explanation can be added to the narrative portion of the proposal.
7 Background: Specification Section 01 00 00, par. 1.6.D.1 lists requirements for construction of temporary partitions and smoke-tight partitions. Question: Would the VA accept the use of STARC panels for temporary partitions in lieu of FR construction partitions?
No, Starc panels are not allowed at this station.
8 Background: Specification Section 01 00 00, par. 1.7.L calls for removal of abandoned service lines and their hangers.
Scope may be difficult to quantify without full knowledge of existing concealed conditions. Question: If work tasks reveal existing conditions that are not clearly defined during bidding that require additional work, will the VA consider this a differing site condition and issue a contract modification?
Quantity is verifiable based on WAO counts and locations.
Assume route and distance to existing TR’s. Cable removal can be completed by cutting and removing cabling in limited sections therefore “existing conditions” are irrelevant and will not constitute a differing site condition.
9 Background: Civil work scope may require excavation and soil disturbance. Question: Can the VA provide a geotechnical report or soil report for the types of soil that will be encountered as part of the Civil Work on this project?
A geotechnical report is available for the MCR site specifically. Additional related reports will be provided for other projects on campus
10 Background: AutoCAD files would expedite and improve accuracy of shop drawing production. Question: Will the VA be able to provide project construction drawings in AutoCAD format to the contractor upon contract award?
Yes, AutoCAD and Revit files will be available upon award
11 Background: Specification section 01 35 26, par. 1.11.B appears to require safety inspection by a CSP or CSHT.
Question: Please clarify if the contractor is required to provide this person or if it will be provided by the VA.
CSP or CSHT shall be provided by the contractor.
12 Background: Specification Section 01 45 00, par. 3.2.B.10 references Section 01 45 35 for Special Inspections, which is not included. Question: Please provide the 01 45 35 document or clarify the SI requirements for this section.
There are no Special Inspections required; however, standard inspections and three-phase inspections are still part of the scope of work.
13 Background: Specification Section 01 45 00, par. 3.4.B requires a full-time CQC Manager with qualifications.
Question: Please confirm this requirement is part of this contract and that the CQC Manager cannot be assigned other duties.
CQC is required and is a sole responsibility
14 Background: Specification Section 01 91 00, Par. 1.7.B includes commissioning of systems that may not be in project scope. Question: Please revise the list of commissioned systems to only include those that relate to this project.
See revised specification section 01 91 00, 1.7 B
15 Background: Specification Sections 02 82 13.13 and 02 82
13.19 refer to contractor avoidance of potential ACM and removal if unavoidable. Question: If existing potential ACM cannot be avoided, will the VA require the contractor to test the suspect materials?
The distributed Asbestos and lead paint survey details locations surveyed, and materials discovered. It is the contractor’s responsibility to cross-check this report with demolition requirements and abide by abatement requirements where relevant. Avoidance refers to areas outside of those surveyed and know materials. If avoidance of non-surveyed but suspect materials are identified, the contractor is to comply with Differing Site Conditions clause.
16 Background: Follow-up to RFI 010 regarding ACM abatement responsibility. Question: If test results verify ACM, will the VA consider this a differing site condition and issue a contract modification?
See response to question #15 above.
17 Background: Specification Section 02 83 33.13 lists a CIH in multiple places. Question: Please confirm if the contractor is required to obtain the services of a CIH.
Yes, Abatement as outlined in the specifications is the responsibility of the general Contractor and individuals as outlined must perform the role detailed.
18 Background: Specification Section 05 12 00 references 03 51 16 and 03 55 11, which are not included in the contract documents. Question: Please confirm these sections are not required for this project.
Confirmed. No Gypsum concrete roof or floor decks in project.
19 Background: Specification section 07 50 05 includes patching of existing roof systems. Question: Please provide roof type and manufacturer for each roof affected by this work.
Refer to Mechanical plans for new roof top equipment and reference photo for existing conditions. Buildings 1,2 built up roof with mineral cap sheet.
20 Background: Roof patching and protection work may affect warranty compliance. Question: Please provide current/existing roof warranty information for each roof and building as applicable.
Warranty information is not available for all buildings.
Certified Contractors are required and should be able to perform all work within warranty framework
21 Background: Walkway pad installation locations and quantity are not defined. Question: Please provide location and roof type for all required walkway pads.
Refer to Mechanical plans for any new rooftop equipment and provide single direct walkway paths to roof access typically.
22 Background: Walkway pad quantity is needed for consistent bidding. Question: Please provide a quantity of roof pads for equitable bidding purposes.
Refer to Mechanical plans for any new rooftop equipment and provide single direct walkway paths to roof access typically.
23 Background: Specification 07 50 05, par. 3.5.F calls for snaking roof drains after construction. Question: Please confirm this applies only to roof drains immediately adjacent to new work and not to all roof drains.
Applies only to drains installed or affected by new work.
24 Background: Firestopping inspection scope is not clearly defined. Question: Please confirm that the contractor is required to obtain the services of a third-party independent firestopping inspector.
Confirmed. Per 07 84 00 1.5.C, the Contractor is required to hire a third-party independent firestopping inspector.
The firestopping inspector must hold a Firestop Special Inspector certification from the International Firestop Council or similar program. The certification program must meet the requirements of ASTME3038-20.
Inspection procedures shall follow applicable industry standards (e.g., ASTM E2174 for penetrating firestops and ASTM E2393 for fire-resistive joint systems/perimeter containment) and in compliance with the listed system details firestopping systems.
The Contractor shall submit
• the proposed inspector’s qualifications, certifications, and resume detailing experience during the submittal process.
• A firestopping inspection plan prepared by the inspector describing the inspector procedure
• written inspection reports identifying locations inspected, systems verified, any nonconformances, and required corrective actions.
a final compliance report/letter stating that inspected firestopping work conforms to the approved submittals, tested/listed assemblies, and applicable standards.
25 Background: Specification 21 22 00 references 'Existing System Shop Drawings'. Question: Can the VA provide these existing system drawings or clarify if this note should be removed?
The Contractor is required to provide the clean agent system specified in Section 21 22 00. This system is being installed in a new free-standing building. There are no “existing systems” for which to provide shop drawings.
The Contractor is required to provide new shop drawings, system calculations, relief vent sizing calculations, Blower Door Room Air Leakage Test, and all other submittals required by Specification 21 22 00.
26 Background: Specification 22 05 11 refers to 13 05 41, which is not in the documents. Question: Please provide or confirm that spec 13 05 41 is not part of the contract.
Appropriate Seismic bracing is required. See attached section 13 05 41
27 Background: Specification 22 11 00, Par. 3.3.A requires flushing and sterilization of the domestic water system.
Question: Please confirm this applies only to new plumbing work under this contract and not to the entire facility.
This applies only to the new MCR Building plumbing
28 Background: Specification 23 05 11 references spec 23 82 00, which appears unrelated. Question: Please confirm that work on convection equipment and spec section 23 82 00 is not required.
Confirmed, No Convection Heating and Cooling
29 Background: Specification 23 23 00 references 23 21 13, which is not in the documents. Question: Please provide spec 23 21 13 or confirm it is not required for this project.
Confirmed, No Hydronic piping
30 Background: Specification 26 41 00 for Lightning Protection is included. Question: Please confirm which buildings have existing LPS installed.
Lightning protection installation required for New MCR building only. No work in existing buildings
31 Background: LPS system scope is unclear across all buildings. Question: Can the VA please provide the existing LPS certification status for each building requiring work?
Lightning protection installation required for New MCR building only. No work in existing buildings
32 Background: LPS work includes new and replacement systems. Question: Will the new MCR building receive a new LPS system, and are any existing buildings scheduled to receive brand new LPS or just repairs?
Lightning protection installation required for New MCR building only. No work in existing buildings
33 Background: Specification 28 05 00, par. 1.18.C references undefined components required by manufacturer. Question:
How is the contractor to quantify supporting equipment, materials, and hardware not described in the contract documents?
Contact your chosen manufacturer and request a quote for a fully complete and functioning system.
Understanding what components they require to comply with the design and specifications. The specification require manufacturer certified installation contractor who are fully trained and certified to install their systems.
34 Background: Division 28 specifications reference specification section 28 08 00 ‘Commissioning of Electronic Safety and Security Systems’. This spec section is not included in the documents. Question: Please provide spec section 28 08 00 for requirements or confirm this spec section does not apply to the work within the contract and therefore is not required to be included in the project documents.
28 08 00 not included, functional testing of new components for existing systems only.
35 Background: Specification Section 28 13 00, par. 1.4.I.5 requires the contractor to provide technical data drawings in AutoCAD in accordance with VA standards. Question:
Please confirm that drawings for this project are available in AutoCAD format and will be made available to the contractor upon contract award.
Confirmed
36 Background: Specification Section 28 31 00, par. 3.3 requires the contractor to perform testing on the Fire Alarm system upon completion of the work. Question: Please confirm that testing is required for only the FA devices that have been newly installed or relocated and that testing of the entire fire alarm system in the facility is NOT part of this contract.
The Contractor is required to provide complete fire alarm testing of the new fire alarm system for the new MCR Building, and connection to the existing system. In remodeled areas, the Contractor is required to provide testing for new or relocated devices.
37 Background: The contractor must match existing FA system compatibility. Question: Please provide the current/existing manufacturer of the Fire Alarm System in the facility.
The manufacturer of the existing fire alarm system is JCI/Simplex system. However, a new fire alarm project was recently awarded and the new manufacturer will be Edwards EST
38 Background: Specification section 31 20 11, par. 3.6 gives instructions for disposing of unsuitable and contaminated soils. Question: Please confirm that encountering unsuitable or contaminated soils is NOT expected.
See attached Geotechnical reports
39 Background: Clarification needed in case unsuitable or contaminated soil is discovered during work. Question: If unsuitable or contaminated soils are discovered, will this be considered a differing site condition and a contract modification will be issued?
No, bid the work in accordance with the geotechnical report findings
40 Background: BICSI certification is industry standard for cable installers. Question: Please confirm the cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by BICSI.
Installers must be BICSI installers trained and certified or trained and certified by brand of product they are installing. Contractor shall have at least one BICSI RCDD on staff as a full-time employee of the company
41 Background: Telecom contractor qualifications are not listed explicitly. Question: Please confirm the telecom contractor must be a licensed BICSI contractor with a minimum of five
(5) years of experience installing and servicing systems of similar scope and complexity.
Confirmed. Installers must be BICSI installers trained and certified or trained and certified by brand of product they are installing. Contractor shall have at least one BICSI RCDD on staff as a full-time employee of the company.
42 Background: VA provided drawings appear to already include existing site survey information. Question: Please clarify site survey drawing requirements for the contractor.
Will the contractor be required to provide a final as-built site survey drawing of the work once the project is complete?
Yes. Contractors are required to final redline drawings.
Including final location for new underground utilities. This does not have to be done by a surveyor if accurately noted during construction.
43 Background: Drawing sheet MCR-A-510 calls out “single-ply roof membrane” in multiple locations for the new MCR building. Multiple roofing specs are provided. Question:
Please confirm the new roof membrane type for the new MCR building.
The MCR is to receive single-ply PVC roofing. Additional roof sections are for existing building conditions.
44 Background: Drawing 001-MD-401 note reads “remove ceiling grilles and diffusers and cap off ductwork as far back as possible.” Existing conditions are not clearly shown.
Question: Can the VA provide existing mechanical, electrical, and data/telecom drawings to help bidders determine the extent of work needed to complete this task?
Mechanical Demolition plans clearly show extent of ductwork and removal.
45 Background: Drawing 001-MD-401 note requires rebalancing airflow after device removal. Rebalancing impact is unclear. Question: Is the intent for the VA to require the contractor to rebalance the entire HVAC system for each unit affected by the work?
Yes, where existing systems are modified the remaining affected system must be rebalanced.
46 Background: General Notes on RCPs require extending existing walls to structure. Scope is unclear. Question:
Please provide existing wall heights and structure heights above each TR, or a fixed square footage for this work so bidders can provide accurate cost.
Where noted existing walls stop 6” above existing ceilings. TR elevations are illustrated to bottom of Approx.
structure.
47 Background: New rooftop equipment may differ in size and weight from existing. Question: Can the VA confirm if new equipment supports will be required for this work (e.g., steel channels, beams, etc.)?
Outdoor equipment will require anchorage and support systems per details and specifications (see MG-102).
No modification of existing roof structure to accommodate added loads is anticipated.
48 Background: If additional steel support is required for rooftop units, cost and scope may vary. Question: If additional steel is required to support new equipment, will the VA issue a modification to the contractor for this work?
No modification of existing roof structure to accommodate added loads is anticipated.
Outdoor equipment will require anchorage and support systems per details and specifications (see MG-102).
49 Background: If no modification is planned, quantifying support steel becomes critical for bidding. Question: If a modification will not be considered for additional steel after award, can the VA please provide additional drawings to quantify the steel to be included in the base bid?
No modification of existing roof structure to accommodate added loads is anticipated.
Outdoor equipment will require anchorage and support systems per details and specifications (see MG-102).
50 Background: Drawing Sheet 001-E-501, General Note 1 states that all shutdowns shall be on an overtime basis.
Question: Please confirm this means all shutdowns are to be scheduled after regular business hours (i.e., nights and weekends).
Confirmed
51 Background: Notes on drawings call for “new 24 strand A & B OS2 fiber cables” from existing TRs to new MCR.
Question: Please confirm this work is complete or part of a separate contract, and that fiber installation is NOT part of this contract.
New Fiber installation is a major component of this contract.
52 Background: Drawing 001-T-133 calls for fire-rated floor sleeves with capacity for growth. Question: Please confirm if there are enough existing floor penetrations in this area, or if new floor penetrations will be required.
Note reads: PROVIDE 4” fire rated sleeves as required for density plus growth. No existing sleeves.
53 Background: If new cores are required, a quantity is needed for fair bidding. Question: If new cores are required, can the VA please quantify the number of cores needed for bidding purposes?
Provide sleeves in compliance with conduit specification for fill ratio based on cable count.
54 Background: Existing furniture and loose fixtures are present in work areas. Question: Please confirm that existing furniture, fixtures, and equipment will be relocated by the VA and are not the responsibility of the contractor.
Contractor will be required to shift and return furniture as required to access WAO’s areas to be renovated for TR’s will be vacated by the VA.
55 Background: Work appears to require dismantling in-wall heaters, which may disturb hazardous materials. Question:
Please confirm if the existing wall conditions are known or suspected of containing asbestos.
The distributed Asbestos and lead paint survey details locations surveyed, and materials discovered. It is the contractor’s responsibility to cross-check this report with demolition requirements and abide by abatement requirements where relevant. If non-surveyed but suspect materials are encountered the contractor is to comply with Differing Site Conditions clause.
See Specification sections 02 82 11, 02 82 13 and 02 83 33 for abatement procedures related to hazardous materials
56 Background: Follow-up to RFI 050 for confirmation of contractor testing scope. Question: Will the VA require the contractor to provide hazardous materials testing for existing walls where in-wall heaters are scheduled to be removed?
See response to #55 Above
57 Background: Specification Section 28 05 00, par. 1.18.C mentions that some supporting equipment, materials, and hardware required for complete system operation may not be described in the drawings or specifications. Question: Can the VA please provide a list of these non-listed materials for pricing purposes?
The manufacturers require certified installation contractors who are fully trained and certified to install their systems. Certified installers should be fully aware of the MFG. requirements.
58 Background: Hazardous materials may be encountered in walls where in-wall heater work is scheduled. Question: If testing results reveal existing wall locations where in-wall heater work is scheduled to contain hazardous materials, will the VA consider this a differing site condition and issue a modification to the contractor for the additional abatement?
See response to #55 Above if materials not indicated in the ACM reports provided are discovered and require abatement, it would be a differing site condition
59 Background: Keyed Note 1 on drawing sheet 112-T-401 calls for a new wall-mounted telecommunications rack, but BOD is listed as TBD. Question: Can the VA provide the Basis of Design for this Telecommunications Rack? This information will allow bidders to provide accurate pricing and anticipate potential lead times.
See specifications for Basis of Design
60 Background: Cabling support method in corridors is not clearly defined in the specifications or drawings. Question:
Please confirm if cabling in corridors should be run through conduit, in cable tray, or using “J” hooks.
J hooks are acceptable. Cable tray required only where shown. Conduit required for vertical runs and above hard lids.
61 Background: Compatibility with existing Fire Alarm system requires manufacturer coordination. Question: Can the VA provide the existing Fire Alarm manufacturer?
The manufacturer of the existing fire alarm system is JCI/Simplex system. However, a new fire alarm project was recently awarded and the new manufacturer will be Edwards EST
62 Background: Coordination with ongoing facility maintenance is important for Fire Alarm system work. Question: Is there an existing Fire Alarm maintenance contractor for the existing facility?
The manufacturer of the existing fire alarm system is JCI/Simplex system. However, a new fire alarm project was recently awarded and the new manufacturer will be Edwards EST
63 Background: Exterior conduit runs may or may not require innerduct installation. Question: Will any innerducts be required to be installed in the outside conduit?
No, Maxcell is required in all conduits.
64 Background: Fiber risers may require additional conduit inside buildings. Question: Will the conduit be required to be installed inside of all buildings to support the riser fibers?
Yes, all vertical fiber risers outside of TR rooms must be in conduits with Maxcell.
65 Background: Specification for inside plant conduit accessories is unclear. Question: Will innerduct or Maxcell be required to be installed in any inside plant conduits being installed for the riser fibers?
Yes, Maxcell is required in all conduits.
66 Background: Armored fiber could eliminate the need for conduit and innerduct. Question: Can armored fiber be utilized instead of conduit and innerduct for the fiber riser cabinets?
All outdoor Duct banks and indoor fiber risers require conduits with Maxcell
Only horizontal indoor fiber runs are permitted without conduit or innerduct when armored Fiber is used.
67 Background: Voice cabling scope is not explicitly addressed for new telecom spaces. Question: Are there any new voice-cabling requirements for new TRs or floor end stations?
No. Provide structured cabling system is as defined on drawings and specifications.
68 Background: It is unclear whether innerduct is required for indoor fiber runs. Question: Are all new indoor fiber cables to be plenum-armored cables with no innerduct?
Maxcell is required in all conduits. Horizontal indoor fiber runs do not require conduit or innerduct
69 Background: It is unclear whether innerduct is required for outdoor fiber runs. Question: Are all new outdoor fiber cables to be armored indoor/outdoor with no innerducts?
All outdoor Duct banks and indoor fiber risers outside TR’s require conduits with Maxcell.
Only horizontal indoor fiber runs are permitted without conduit (j-hooks or cable tray)
70 Background: Some buildings may not have an existing fiber backbone entry. Question: Do any existing areas of the hospital need a new building entry pathway for the new fiber backbone cabling?
New Duct banks routes and building entry points are clearly shown on civil drawings.
71 Background: Network equipment may be needed during cutovers to maintain service. Question: Does the VA have extra network equipment (switch gear, routers, UPSs) to keep the network connected during construction and cutover?
VA provides limited additional switches to make cutovers to new TR’s. contractor required to move switches from decommissioned TR’s in a phased progression.
72 Background: Lack of extra network gear may lead to unplanned service disruptions. Question: If the VA does not have extra network equipment to maintain connectivity, can the system have an 8-hour downtime?
Downtime will be limited to a few minutes per WAO during normal business hours. Downtime outside of normal business hours is acceptable.
VA provides limited additional switches to make cutover to new TR’s. contractor required to move switches from decommissioned TR’s in a phased progression.
73 Background: Head-end fiber runs may require added protection. Question: Is Fiber Optic cabling between head-end equipment required to be 100% in conduit?
Build conduit pathways as shown on the provided documents
74 Background: Clarification needed on division of labor.
Question: Will the VA or the Contractor make final terminations in the TR and MCR?
The Contractor will make all terminations in the MCR/TRs, TE's and ERs then label and test each one.
75 Background: Escorts may be required for secure areas.
Question: Are escorts required for all work in existing TR and MCR?
YES
76 Background: Secure environments may require oversight during sensitive installations. Question: Are escorts required during terminations within new TR and MCR?
Only in active TR’s and Active MCR.
“new” not in service spaces do not require escorts.
77 Background: General Note 3 on Sheet AE101 calls for extending TR walls to deck, but no information is given as to which walls require this. Question: For bidding purposes, can we assume all existing walls extend to deck, and that any which do not will be addressed with a change order?
NO. see TR elevations for existing deck heights and partial height walls.
78 Background: If TR wall-to-deck assumption is not acceptable, more detail is needed. Question: If the above assumption is not acceptable, please provide the location and wall type details of every wall which does not currently extend to the deck and will need to be extended.
NO. see TR elevations for existing deck heights and partial height walls.
79 Background: AE101 Note 5 calls for sprinkler head replacement in new/expanded TRs, but number of heads is not shown. Question: Can the VA provide a proposed quantity for the existing sprinkler heads to be replaced so that an accurate price can be included in the bid proposal?
The Contractor shall provide all new fire sprinklers in Telecommunication Rooms in accordance with NFPA requirements for Light Hazard Coverage. The Contractor is required to install the quantity of sprinklers necessary to comply with NFPA 13’s Protection Areas and Maximum Spacing of Standard Pendent and Upright Spray Sprinklers for Light Hazard. The contractor shall provide new branch piping as necessary for the floorplan changes. The contractor shall also provide new branch piping and sprinklers for any new obstructions created by new ductwork, cable trays, conduits, and electrical equipment.
Provide new intermediate temperature, standard response, fusible link sprinklers for all Telecommunication Rooms. Provide UL listed mechanical guards.
80 Background: Delegated design for sprinkler systems may require hydraulic flow test data. Question: Will the VA provide flow test calculations for delegated sprinkler design or will the contractor need to perform these tests?
For the new fire sprinkler system in the MCR Building, the Contractor is required to provide a new fire hydrant flow test compliant with the requirements of NFPA 291, and the Contractor is required to prepare shop drawings and hydraulic calculations for this system. Hydraulic calculations are not required for the TRs.
81 Background: Keynote 3 on MCR-E-001 specifies a CAT diesel generator. Question: Are equal generator manufacturers acceptable in lieu of CAT?
CAT is basis of design. Alternatives can be submitted for approval
82 Background: Keynote 4 on MCR-E-001 specifies ASCO for ATS switches. Question: Are equal manufacturers acceptable in lieu of ASCO for ATS switches?
Basis of Design. Alternatives can be submitted for approval
83 Background: Keynote 7 on MCR-E-001 specifies APC for UPS units. Question: Are equal manufacturers acceptable in lieu of APC for the UPS?
Basis of Design. Alternatives can be submitted for approval
84 Background: Utility transformer on the one-line diagram on MCR-E-001 is shown without size. Question: Please specify the required size for the utility transformer shown on drawing
MCR-E-001.
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
85 Background: Keynote 16 on MCR-E-001 states to coordinate transformer requirements with utility provider.
Question: Will the utility company or the contractor be responsible for providing the transformer, pad, and location on this project?
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
86 Background: It is unclear if the contractor must furnish the transformer, pad, and location. Question: If the contractor is responsible for providing the transformer, pad, and location, will the government please provide the corresponding specifications?
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
87 Background: Coordination with the utility provider may involve fees and contracts. Question: Who is responsible for coordinating with the utility provider and covering any associated fees?
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
88 Background: In prior projects, the contractor has provided medium voltage primary cabling to transformers. Question:
Will the contractor be responsible for providing the medium voltage cabling to feed the primary side of the transformers?
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
89 Background: If medium voltage cabling is required by the contractor, specifications are needed. Question: If the contractor is to provide the medium voltage cabling to feed the transformer, please provide the associated specifications.
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
90 Background: Routing for medium voltage cable is not indicated. Question: If the contractor is providing the medium voltage cabling to feed the primary side of the transformer, where is the source location for this feed?
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
91 Background: Utility provider ownership affects contact and coordination scope. Question: If utility transformers are provided by the utility company, please provide the name and contact information for the utility company.
Provide the following: medium voltage 500 KVA compartmental transformer with primary protection and loop feed. Tie into the existing campus medium voltage loop and extend both sides of the loop to the new transformer. For this work, provide a $150,000 allowance. Design to be issued at a later date.
92 Background: Coordination with the existing BAS vendor may be required for tie-in. Question: Can the government please provide information on who currently manages the BAS system for the campus?
Siemens and Alerton.
93 Background: Contact information is required for proper BAS tie-in coordination. Question: Please provide contact information for the current BAS system vendor.
Contact information will be provided post award.
94 Background: General Note 5 on MCR-E-001 states that the Monitoring System must connect to the BAS. Question:
Please provide the building numbers and physical locations for tying into the BAS system.
See plans and specs.
95 Background: Cable routing methods are not clearly defined for buildings. Question: Can voice/data cabling throughout the buildings be supported by J-hooks and run free-air?
J-hooks are permitted for horizontal cabling. Conduits only required where indicated on dwg and specifications.
96 Background: Clarification needed on conduit requirements for low-voltage cabling. Question: Is all voice/data cabling required to be installed in a complete conduit system?
J-hooks are permitted for horizontal cabling. Conduit only required where indicated on dwg and specifications.
97 Background: Fiber optic routing may allow for J-hook support. Question: Can fiber cabling throughout the buildings be run on J-hooks and in free air?
J-hooks are permitted for horizontal indoor runs.
Conduit required for vertical sections.
98 Background: Clarification needed on pathway requirements for fiber cabling. Question: Is all fiber required to be installed in a complete conduit system?
J-hooks are permitted for horizontal indoor runs.
Conduit required for vertical sections.
99 Background: Transformer feeder schedule on MCR-E-001 includes multiple transformers not shown on the one-line.
Question: Are the 225, 300, and 500 KVA transformers listed in the feeder schedule specific to this project?
This is a general schedule. Only provide what is indicated on the one line diagram
100 Background: The feeder schedule on MCR-E-001 includes feeders up to 4000 amps, but the one-line only shows up to 800 amps. Question: Are the feeders rated over 800 amps shown in the schedule specific to this project?
This is a general schedule. Only provide what is indicated on the one line diagram
101 Background: ICRA drawings and specs do not define fire rating for temporary barriers. Question: Please confirm the required temporary barrier type (1-HR rated vs. non-rated) for various room types, especially Telecom rooms adjacent to patient zones.
Rating requirement for temporary barriers are defined in notes 2 and 5 of G-031.
In accordance with NFPA 241-2022, 4.12.3, if construction requires the impairment of the fire sprinkler system, the temporary barriers shall have at least 1-hour fire resistance rating. Opening protectives shall have at least a 45-minute fire resistance rating.
If construction requires the impairment of an existing fire barrier, the fire rating of the temporary barrier must match the impaired barrier to provide a continuous rated partition. Opening protectives shall have at least a fire resistance rating commiserate with the rated partition.
If the fire sprinkler system is not impaired, and the construction does not affect a rated partition, the temporary construction barrier is permitted to be of non-rated non-combustible or limited-combustible material.
102 Background: Exhaust path guidance is not included where exterior access is limited. Question: What discharge locations are acceptable for HEPA-filtered exhaust when direct exterior access is limited?
Refer to ICRA permit application provided on G-030.
Specific exhaust requirements are detailed per each Class of precautions
103 Background: Spec mentions pressure monitoring but not device models or methods. Question: What models or types of devices are acceptable for pressure monitoring, and is continuous logging required?
ICRA barrier example indicated negative pressure gauge with posed log. Gauge to have visible display for period checking by VA or GC staff. Log to be updated min once per day by GC. GC may use any manufacturer’s device.
104 Background: Specs reference permits but not how they’re issued. Question: Who issues the ICRA permit, and must it be renewed for each phase or room?
VA infection control staff issues ICRA permits. Permits are required for each individual TR and each building floor for cabling operations.
105 Background: Data outage constraints were mentioned but are not in specs. Question: Does the data outage restriction apply to all areas, and what is the process for requesting variance?
Cut-over procedures are the same for all buildings.
Coordinate with COR for potential variances.
106 Background: Four-room rule not documented in contract.
Question: Does the four-room limit apply to all types of work (framing, cabling, testing), or only active construction?
Not applicable
107 Background: Short-term corridor work may not justify full containment build-outs. Question: Are portable containment carts acceptable in lieu of full anterooms for short-term corridor work?
HEPA carts are required for Corridor work.
108 Background: Sticky mat count and replacement policy is not defined. Question: What is the required number and location for sticky mats per room entrance, and how often must they be replaced?
1 per entrance. Per ICRA permit application form mats “must be changed routinely and when visibly soiled”.
109 Background: Specs do not clarify approval sequencing before barrier removal. Question: Must contractor, EMS, and inspection approvals be completed per room or per project phase before barrier removal?
YES, each separate ICRA permitted work zone must get full COR approvals before removing barriers installed under that permit.
110 Background: Extended above-ceiling runs are not clearly addressed in containment requirements. Question: Is hard containment required for extended above-ceiling runs or can plastic sheeting be reset daily in occupied areas?
HEPA carts are required for Corridor work.
111 Background: Monitoring responsibility is not clearly assigned. Question: Who is responsible for maintaining air pressure logs and in what format must they be submitted?
The general Contractor to maintain and log daily. Logs to be displayed at the barrier entrance. Readings shall be included in daily reports.
112 Background: Specs reference HEPA filters but not certification process. Question: Is third-party certification required for HEPA filters, or are factory certificates sufficient?
Factory rating, verification by particulate measurement when required. See provided ICRA precautions for each Level of prevention.
113 Background: Specs do not clarify room-level vs. phase sign-off. Question: Will complete telecom rooms be signed off and released individually, or must they be bundled by phase/floor?
TR’s must be accepted by BUILDING/FLOOR as represented by cabling zone.
114 Background: Specs do not describe EMS cleaning coordination. Question: Is the contractor responsible for coordinating EMS terminal cleaning, and what is the inspection sequence?
Terminal cleaning when required will be scheduled by COR after final Contractor cleaning and VA acceptance for turn-over.
115 Background: Specs do not define allowed hours for containment setup. Question: Can containment barriers be installed during regular hours, or is after-hours work required for all such setup?
After-hour work requirements will be defined by hospital area. Not work type. Outpatient clinic areas will require after hour work for cabling and cut-over.
116 Background: Specs do not identify material requirements for protecting adjacent finishes. Question: Are specific materials required to protect existing adjacent ceiling tiles and flooring not to be demolished?
Material used for protection is a means and methods consideration. Any damage to the existing materials and replacement of damaged material is the sole responsibility of the Contractor
117 Background: Specs do not address obstruction of existing fire alarm devices. Question: Are temporary fire detection systems required if existing fire alarm devices are obstructed by containment walls?
Yes. In the event that the construction of containment walls obstructs existing fire alarm devices, the Contractor is required to relocate or provide new temporary fire alarm appliances to retain notification or initiating coverage. The Contractor is required to test the affected devices during the temporary and final installations.
118 Background: Egress impacts from barriers are not addressed. Question: How should egress routes be maintained or redirected during containment wall installation in corridors?
Illustration on G-030 states 44” min clearance to be maintained
119 Background: Specs call for PPE but do not define by ICRA class. Question: Are shoe covers and Tyvek suits mandatory in Class IV and V ICRA zones at all times?
See requirements based on class outlined in ICRA application forms provided on G-030
120 Background: Specs do not define acceptable noise levels near patients. Question: Are there noise limits (dBA) for negative air machines near patient care areas?
There are no quantifiable acceptable DBA limits. Any noise deemed to interfere with patient care will be required to be rescheduled. Public shall not be exposed to sound levels above OSHA, PEL.
121 Background: No protocol is defined for accidental dust/fluid releases. Question: What is the contractor’s responsibility if hazardous dust or fluids are accidentally released outside containment?
Protocols vary by released contaminant.
EPA, OSHA and VA Guidelines apply.
Immediate VA notification required for any event.
122 Background: Administrative zones are included but barrier requirements unclear. Question: Please confirm if infection control barriers must be fire-rated or just airtight in administrative zones.
Rating requirement for temporary barriers are defined in notes 2 and 5 of G-031.
In accordance with NFPA 241-2022, 4.12.3, if construction requires the impairment of the fire sprinkler system, the temporary barriers shall have at least 1-hour fire resistance rating. Opening protectives shall have at least a 45-minute fire resistance rating.
If construction requires the impairment of an existing fire barrier, the fire rating of the temporary barrier must match the impaired barrier to provide a continuous rated partition. Opening protectives shall have at least a fire resistance rating commiserate with the rated partition.
If the fire sprinkler system is not impaired, and the construction does not affect a rated partition, the temporary construction barrier is permitted to be of non-rated non-combustible or limited-combustible material.
123 Background: Telecom closet ICRA level is not confirmed in ICRA drawings. Question: What ICRA Level should be assigned to telecommunication closets?
ICRA level is dependent on patient risk group. See applications form provided on G-030. TR construction work Type C or D, therefore ICRA min Class III in low risk areas, Class IV in Medium and Class V in high and highest risk areas.
124 Background: No template or format is provided for ICRA plans. Question: Will an ICRA plan template be provided by the VA or should the contractor submit their own for approval?
ICRA application forms are provided, template Infection control measures plan provided on G-031. Contractor to provide detailed plan outlining specific precautions required for each TR as classified in ICRA/PCRA summary
125 Background: Negative pressure scope is unclear for telecom-only spaces. Question: Is negative pressure required for all telecom closet work or only those adjacent to clinical spaces?
Read the minimum protection control precautions by class on the provided forms on sheet G-030 level of prevention of each TR defined in ICRA/PCRA Summary.
126 Background: Ceiling removal requirements for Class III/IV not stated. Question: Do ceiling removals in corridors require full barrier containment and air scrubbers?
FULL CEILING REMOVAL outside TR’s is not permitted.
Limited ceiling removal for access to pull cabling can be done with mobile HEPA carts
127 Background: No permit submission procedure is defined in the spec. Question: What is the procedure for obtaining ICRA permits or approval prior to demolition in patient care zones?
Application must be submitted and approved by the VA infection prevention control staff and COR prior to start of work. All applications are initiated through the COR.
128 Background: Inspection frequency is not stated. Question:
Are ICRA inspections to be performed daily by the VA or only prior to major scope shifts?
Contractors are expected to self-inspect daily and correct deficiencies. COR will perform spot checks for compliance. Standard VA safety inspections occur weekly.
129 Background: Role of SSHO during inspections is not mentioned. Question: Is the contractor’s SSHO required to be present during all government ICRA inspections?
YES, SSHO to accompany VA staff on weekly safety inspections
130 Background: ILSM and ICRA submittals not clearly connected. Question: Please confirm if ILSM documentation must be submitted alongside ICRA or separately in daily logs.
ILSM and ICRA are separate required submittals but may be submitted simultaneously. ILSM and ICRA permits are required to be submitted 14 calendar days in advance.
131 Background: Sheet G-005 ICRA matrix may not be final.
Question: Please confirm if the ICRA classifications indicated on Sheet G-005 are definitive or if the contractor is expected to coordinate with VA Infection Control for formal approval of risk levels by area.
Contractor must submit ICRA permits for each TR and floor for cabling operations. VA infection control will make final decision on classification and issue permits.
Preliminary classifications for TR work issued with bid documents