This document contains technical questions and responses related to a federal contract opportunity for a minor construction project to infill Building 26 at the Wichita VA Medical Center. The project involves constructing new dental clinics, a police office, and renovating for specialty care services. Key details include:
The contractor must coordinate crane operations, laydown areas, access to the service dock, and maintain emergency egress during construction. Responses address technical specifications for equipment, materials, security systems, and IT infrastructure. Clarification is provided on the required equipment and systems, including cameras, access control readers, and network integration. The contractor is allowed to propose alternate products that meet the specifications. The project has defined phasing requirements to maintain operations during construction. Relevant specification sections and drawings are referenced throughout the responses.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Minor Construction-589-704 Wichita VAMC-Technical Questions
1. On Sheet T-601, Detail 5. It is titled BUILDING 6, AREA A IT ROOM A115 TECHNOLGY RISER DIAGRAM. Building 6 is on the other side of the campus. Need clarification on this detail. Where is the VAPD FIBER-OPTIC ENCLOSURE located. Assuming the 4” conduit with (4) innnerducts, connects VAPD FIBER-OPTIC ENCLOSURE to IT Room 030, which is actually Room 049, and then 4” conduit between IT Room 049 and IT Room 119.
RESPONSE:
VAPD fiber optic enclosure located in Building 6 IT room A115, VA to confirm exact location. 4” conduit with four (4) innerducts shall be installed from building 6 A115 to IT room 049, then a 4” conduit connection shall be installed between IT Room 049 and IT Room 119.
2. There is not any cable tray shown. With the quantity of CAT 6a cables may be necessary. RESPONSE:
Use cable tray through main corridor areas. Utilize j-hooks from cable tray to conduit to work area outlets.
3. If I submit pricing on some equipment other that the BOD and it meets specs will it be considered? Quantech Chillers, PACE AHU’s and ZCU Fan terminal Units.
RESPONSE:
Yes. To be confirmed during the submittal process post contract award.
4. Regarding the anti-ram gate and security fence shown on Drawing SS101; specifications have not been identified in the solicitation documents. Please provide relevant specification section. RESPONSE:
Specification Section 34 75 13 provided in Addendum 01.
5. Reference sheet CS100. The new 18’ wide sliding gate on the east side is not identified as to its construction including the foundation indicated on these plans. Please provide more directions as well as the foundation structure for this gate. Sheet AE125 also indicates that the gate is a sliding anti-climb/anti-ram security gate.
RESPONSE:
Specification Section 34 75 13 provided in Addendum 01.
6. At the walk through, it was indicated that the crane work would need to happen after hours and through the night for swinging product overhead. Please confirm this is required.
RESPONSE:
Reference spec section 01 35 26-D.1 for crane operations over occupied spaces. Coordinate with the VA for working hours.
7. At the walk through, it was indicated that the service dock to service the canteen would need to always remain open. We are anticipating that the area identified as phase 4 would be our crane and pump truck location which would not be able to be moved easily. Also, this seems to be the area for laydown in our eyes. Please confirm possible crane ‘lay-down’ locations?
RESPONSE:
This area may be utilized as laydown/crane location. Coordination efforts to be made with VA prior to taking over space.
8. Is it possible to place a crane between Bldg. 26 and Bldg. 19 for mechanical or steel erection operations?
If contractor can fit a crane in that location, it is permissible. Contractor will be responsible for ensuring adequate protection for all utilities, above and below grade. Contractor also responsible for repairing any damage that may occur to sidewalk, grass, etc.
9. More than likely, much of the concrete around the phase 4 area and the paving between Bldg. 26 and Bldg. 19 will be removed and replaced due to the number of utilities and traffic in this area. Are we to assume that this area will not be used as an emergency egress during our construction operations?
RESPONSE:
Emergency egress to be maintained at the sidewalks. Coordinate exact paths with VA COR and Safety prior to demolition.
10. Sheets AE401 through AE418 indicate equipment schedules. Can you give a better detail of whom provides and who installs this equipment? There is no legend that indicates this. RESPONSE:
Reference abbreviations on sheet GI001.
11. Reference sheet G-000. In the bid deduct notes, it indicates that the area will have metal walls and gyp board around the exterior walls of the space. Are all future utilities to be constructed in these wall spaces? New ceilings are to be installed in this area with minimum lighting also. RESPONSE:
No in-wall electrical required in bid deduct.
12. Reference sheet G-000. Is the shared waiting room 100A required for the base bid renal care unit? Should this space not be part of the bid deduct alternate?
RESPONSE:
100A is part of the base bid. NOT part of the bid deducts.
13. Reference sheet SF102. Note 5 indicates fiber reinforced polymer to support additional loading as noted on the plan and ‘designed by others’, for proposal purposes, are we to assume the entire FRP footprint is to be priced?
RESPONSE:
Yes. Please include in base bid pricing.
14. Please identify where the security doors and frames are located. The specs refer to the drawings and I cannot find them on the drawings unless they are for the security fence.
RESPONSE:
No interior security doors or frames required; coordinate with fence manufacturer regarding gate panels, gate frames, protection of PACS conduit and protection of egress device from access outside fence. Section 08 34 53 to be removed per Addendum 01.
15. Please confirm that there are no additional sheets for Civil for this project. It was indicated at the walk-thru that crane locations were shown on the civil drawings, but we cannot find anything indicating that on our drawings.
RESPONSE:
Crane location are means and methods of construction. To be coordinated with the VA COR.
16. For possible structure shoring/under-pinning/helical requirements; please provide existing Building 26 foundation profile to include Grid A/4 and A/10 as the viewable profile seems to differ at B through H.
RESPONSE:
Existing structural/ foundation profiles and sections to be provided by VA record drawings.
17. Drawing TY101, Note 57 indicates ‘provide EAS Security System’, is this system contractor supplied / contractor installed?
RESPONSE:
Yes.
18. The new underground fuel tank requires a base pad for anchoring – what is the required pad size, thickness, and depth?
RESPONSE:
See “SA031-Pad Details”
19. In Drawing Title Technology Schedules, Drawing Number T-602, CR-01, and CR-02 the color states white. Checking with multiple manufacturers there is not a white badge reader to meet the specifications set in this document. Would a black badge reader be an acceptable or would the customer prefer a custom faceplate to be installed on the badge reader?
RESPONSE:
Black is acceptable.
20. In Drawing Title Technology Schedules, Drawing Number T-602, the camera schedule states that camera type C-01 minimum resolution is 12MP. Would the customer accept a 2MP, 4MP, or 8MP camera instead?
RESPONSE:
Yes.
21. In Drawing Title Technology Schedules, Drawing Number T-602, the camera schedule states that camera types C-03, C-04 minimum resolution is 12MP. Would the 12MP be for each single sensor or 12MP total for all sensors?
RESPONSE:
For C-03 and C-04, 2MP, 4MP, or 8MP per sensor is acceptable.
22. In Drawing Title Technology Schedules, Drawing Number T-602, C-WP the model states, Avigilon H4 multi-sensor camera. Would the customer accept a different manufacturer that would be able to meet the same requirements but have a camera that will work better with the VMS platform?
RESPONSE:
New cameras must integrate with existing SSTV system. A/E has no issue with other manufacturer being used as long as it can be integrated into the existing system. A/E and VA station stakeholders must approve before procurement of new cameras.
23. Specifications state the fire protection system & fire alarm will be ‘maintained in operation’ and that the contractor’s employee or ‘watchman’ will respond to alarms. Will 24/7 fire watch be required throughout construction?
RESPONSE:
Firewatch required until suppression system is operation at infill (Phase 1).
24. Drawing schedule AE401 through AE418 are unclear as to contractor supplied/installed, canteen supplied/installed, VA supplied/installed. Please clarify equipment schedules.
RESPONSE:
Reference abbreviations on sheet GI001.
25. Previous experience at building 26 ground floor identified a waterproof membrane on top of SOG with final concrete slab on top of waterproofing – will the same installation manner be required at ‘cut & patch’ locations at ground floor level?
RESPONSE:
Yes.
26. Can you provide specifications for camera, C-02 due to this being on one of the document pages but having no reference in the camera schedule.
RESPONSE:
Dual view 2 X 1/3” / 2MP (MIN) sensors.
27. Drawing AD111 indicates demo at room 015 and 015B, what are the room finish requirements? RESPONSE:
Existing finishes to remain at these rooms.
28. What is the extent of finishes in the corridor (north) of these rooms? RESPONSE:
Reference C2 on AF 711.
29. Are all floors adjacent to ‘infill’ proven to match ‘0’ or 10’-8” elevation? RESPONSE:
Contractor to field verify and match existing elevation.
30. It is unclear whether there is access to the mechanical room roof elevation via ladder – please clarify?
RESPONSE:
Reference 1/ AE 113, keynote 5.04 indicates wall mounted ladder location.
31. Demolition drawings AD111 & AD113 indicate the demolition of windows throughout. Many of these windows are shown in ‘grayed out’ areas of work that are not included in the project SOW. What is the interior (existing) room requirements for infection control and finishes at removed windows?
RESPONSE:
Infill windows with gyp on adjacent sides. ICRA requirements to be maintained and coordinated with VA COR.
Mechanical Technical Questions
32. Due to underground utilities around and possibly over the existing fuel tank, hydro excavation will be the safest way of tank removal. Will there be any disposal requirements for the removed material?
RESPONSE:
Please refer to Civil Spec Section 312011 Earthwork for excavation and backfill requirements. If the removed material is still considered “suitable” it could be reused, if it is deemed “unsuitable” after removal, disposal is subject to the contractor, specifications, and environmental considerations/regulations.
33. Specification 23-10-00 is fuel related information. It calls out for a concrete anchor will there be a detail showing the concrete pad dimensions, per specified tank?
RESPONSE:
Please refer to Civil plans and specifications for concrete anchors and pad dimensions.
34. If the ground around the existing fuel tank is contaminated what is the contractors responsibility and will a modification to the contract be issued? Spec 31-20-11 refers to unsuitable material, would fuel contamination fall under this specification?
RESPONSE:
Please refer Spec Section 312011-1.2.A.1 Unsuitable Materials.
35. Will the grease pipe have heat trace? Current elevations show just over 1/8 per foot of fall with a total distance of 183’ +/-
RESPONSE:
Due to space and placement constraints, that is the closest and most suitable place for the interceptor. Neither ASME A112.14.6 nor the manufacturer’s instructions indicate a maximum length/fall for this system. So, while it was not included in the design drawings, the inclusion of heat trace piping (through an ASI or addendum) to the grease pipe would make the likelihood of grease build-up happening during a longer run less likely, therefore decreasing the risk of backup or the need for more frequent maintenance and cleaning of pipe. Not required from all that could be referenced and found, but also used as an industry practice to mitigate issues. If heat tracing is deemed most effective for this system by the contractor and the owner, coordination with the electrical engineer and contractor will need to occur.
36. Per PG 101 phase 2 ground floor, hose reels are indicated as (typical) detail P-401 shows 4 hose reels. Are these considered “medical air” hose reels and will they be specified?
RESPONSE:
These are for dental air, so they would be considered “medical air.” These hose reels should be owner/contractor selected and provided as they are specific to the internal equipment needs of the space.
37. Per MH 101 ground floor mechanical PH 1- shows 4 temporary duct (34x14, 22x12, 22x12, and ?) will these be installed during normal working hours? During the walk, it did not appear space was available for the additional duct. would flex duct be acceptable in certain areas?
RESPONSE:
Temporary flex duct can be acceptable if intent is relayed and agreed upon by the owner and Engineer in advance of installation, for confirmation of sizing and airflow needs. Timing of installation shall be coordinated with the owner and stakeholders of the spaces it will affect.
38. Are new openings in the existing building required for the temporary duct or will they be allowed to exit a window within the cafeteria?
RESPONSE:
Coordinate with VA for preference of that means/method.
39. Will more information be provided for the relocation of the dust collection unit? RESPONSE:
Coordinate with owner for additional information on dust collection equipment and locations.
40. A note is provided for the fire dampers when penetrating the floor but this note is not represented at all duct penetrations. Will all fire damper, smoke dampers, fire & smoke dampers be listed on a schedule page and located?
RESPONSE:
Floor penetrations are to be provided with fire dampers and the note is to be typical for all floor locations. Fire dampers, Smoke damper and combination fire/smoke dampers are not scheduled but are located on the floor plans.
41. Where the underground chilled water connects to the existing, does it pass under the existing steam trench?
RESPONSE:
The buried chilled water is routed above the steam trench per site utility drawings. Request for the latest site utility drawings from the VA as they are updated.
42. What is expected for the “direct buried” chilled water piping? RESPONSE:
Piping to be directly buried in the ground with proper packing and jacketing to protect pipe from movements and temperatures.
43. During the transition from phase one and phase two, how many days are projected for the completion of the grease line in phase 2 and setting the new grease trap and lift station? During this transition the kitchen will not be operational. RESPONSE:
Construction durations at the behest of the contractor schedules, methods, and owner coordination.
44. In the existing court yard there is a condensate tank vent along the south wall at 4’ above ground. Where should this be re-routed? At this location there is also a domestic water outlet, will this outlet demo?
RESPONSE:
Demo domestic water outlet back to nearest main to remain. Please provide more info on the condensate tank vent or cate to the nearest acceptable location if not indicated on drawings.
45. Per MP101 note 58, will a chase be provided for the existing chilled water lines on ground floor? The current layout indicates the chilled water lines and the freezer (025D) wall occupying the same space. Other floor has chase. RESPONSE:
Existing to remain, lines appear to stop above the freezer on the ground floor. Contractor to verify. Space to the north of the freezer is a mechanical chase between buildings. Lines may reside in this space as well.
46. Per MHD101 note D15 (demolish existing exhaust fan and associated accessories) from the prints it is unclear what this serves. Will a temporary exhaust system need to be provided during phase one construction?
RESPONSE:
Appears to be the pump room. Should be okay as is during construction, confirm with VA. Small temporary system would also be appropriate to keep heat and fumes from building in pump room if phases are extended. Plan to attach new exhaust system and quickly as possible in the transition.
47. Just to the north of the above mentioned exhaust fan there is a 12x12 wall louver that was noticed during the walk. Will this item be identified and instructions provided?
RESPONSE:
Not part of scope area. Appears to be on other side of stairwell, possibly for ventilation.
48. M503 detail 4 and 5 refer to trench piping and hanger support. Please provide a location for the two types of trench details.
RESPONSE:
Unknown. Detail for reference.
49. The Fuel Tank Needs a Pad under it to be Anchored. Is a new pad required or is there one existing, and is it big enough for the New Fuel Tank?
RESPONSE:
Plans show underground storage tank and generator on pad. Refer selected generator and verify with pad to confirm adequate pad for new equipment.
50. Will we be able to use an existing window in the dining area for the temporary Duct or will we have to cut an opening for it and patch the wall after it is not in use?
RESPONSE:
Preference to window for minimal patch and repair needs. Confirm with VA.
Electrical Technical Questions Division 26:
51. Sheet E-601. No information on feeder schedule for MV feeder from SWGR-55 to TX-26-INFILL. Need conductor and fusing size.
RESPONSE:
Design intent is to provide MV feeders and duct to match existing MV feeders serving service transformers on this campus. Field-verify and provide accordingly.
52. Electric Room 033 is needed for placement of electrical panels in Phase I. Per Mechanical demo drawing MHD-101, the air handler unit in that space is not demoed until Phase II.
RESPONSE:
Design intent is to build out electrical rooms during each phase to serve new work installed during the respective phase. Electrical contractor’s bid shall make provision(s) to include phasing of electrical installations for continuous operation during construction. Addendum drawings will be provided for additional phasing clarification.
53. The existing generator has a day tank in an outside enclosure. Can’t find any information on drawings or specifications pertaining to a new day tank.
RESPONSE:
Details of day tank will be provided in mechanical drawings in addendum.
54. Sheet EP102, Keynote 47 states an Estop for X-ray equipment. Does the X-ray equipment in this room require other electrical shunt trip devices and wireway?
No other shunt trip or wireway are required for this X-ray.
Division 27:
55. Sheet E-401, Keynote 24, states 5KW rack mounted UPS. Are these to be similar to the 5 KW Eaton BLADEUPS that are currently in all IT racks?
Yes, refer to div. 26.
56. There are no Wireless Access points shown on TN Sheets. Need info on quantity, and where they are to be installed.
No new wireless access points to be provided existing wireless access points to be remove and retained during the demolition phase and reinstalled in the new work. Provide two Category cables to each wireless access point.
Division 28:
57. The hardware schedule in Division 8, and the security drawings do not completely match. There are doors on schedule that are not on drawings, and doors on drawings that are not on schedule. Please clarify.
RESPONSE:
Updated drawings to be submitted with forthcoming addendum.
58. All of the card readers in the driveway parking areas on TY103 are shown as combination PIV Keypad & Biometrics. The other parking lot card readers around the VA campus are just standard PIV CR w/ Keypad. Please confirm the card readers on this project need to have built-in biometrics?
RESPONSE:
Dual authentication PIV PIN code and keypad is acceptable.
59. Some cameras have the letters “MA” next to them. What does this stand for? RESPONSE:
MA stands for motion activated.
60. The VA currently has a dedicated security fiber running throughout the campus. Where will the new security network switches for this project tie into that existing security fiber?
RESPONSE:
New network switches to be added in Building 6 IT room A115, VA to confirm exact location.
61. Do the video Aiphone units need to report back to the video Aiphone master station being installed in Building 1 security office? Or just to Room 032?
RESPONSE:
Yes.
62. Does the existing CCure Software license have capacity to add the panels/readers for this project?
RESPONSE:
Software license is the most-current version as of 03/15/2024. Unsure of the capabilities to expand the current system. To be confirmed by software/security provider.
63. Are any additional CCure licenses to be included as part of this project? RESPONSE:
Licenses are to be obtained as required for a fully functional system.
64. The card reader schedule on T-602 calls for white and black card readers? Confirm if white card readers will be enforced?
RESPONSE:
Black is acceptable.
65. The card reader schedule on T-602 under the “Model” column says UPGRADE EXISTING VA MODEL TO DUAL AUTHENTICATION. Please confirm what this is instructing the contractor to do? RESPONSE:
Single authentication card readers are not compliant. All card readers shall be dual authentication (PIV and PIN code).
66. The camera schedule on T-602 states that Camera C-04 for be a 360-degree panoramic mini dome camera. Is the intent to use a fisheye lens style camera? Or a 4-lens 360-degree camera. A standard 360 degree multi-lens camera will not be a “mini dome” form factor.
RESPONSE:
4-lens 360-degree camera. Mini dome not required.
67. The specs call for 24/7 recording. Please confirm this is desired over motion activated recording? RESPONSE:
Cameras shall record 24/7 unless noted otherwise. Motion activated cameras marked as “MA”.
68. What is the minimum frame rate for the cameras to record at? RESPONSE:
15 frames per second.
69. How many days of video retention will be required for recorded video on the NVR? RESPONSE:
60 days of video retention minimum.
70. What type of analytic licenses/functions will be required for the cameras? RESPONSE:
Artificial intelligence based facial, trespass, behavior, go/no-go, and unknown object/vehicle analytics.
71. Will there be any new client PC’s required? What about Victor client licenses? RESPONSE:
PCs and licenses shall be provided as required for a fully functional system.
72. On sheet T-601 Typical # 2, it calls for Triple authentication between CR, LPR and Facial camera. The facial camera is referring to the Aiphone station at the gate. This station will not be connected to the camera system nor would it be capable or analytic trigger. Please confirm if a different facial camera will be required in addition to the Aiphone.
RESPONSE:
Aiphone can support facial analytics. Provide integration as required.
73. Is the existing VA CCure & Victor currently integrated to allow for authentication across card readers and cameras?
RESPONSE:
Yes.
74. On the security diagram on page T-601 is calls for the equipment to be located in Electrical Room B101. Where is this room located?
RESPONSE:
Electrical B101 labeled in error. Equipment should be installed in Telecomm or Security room.
75. Is the existing security fiber network and network switches at the VA designed for a 10G uplink/downlink or 1G uplink/downlink?
RESPONSE:
Contractor to confirm requirements.
76. Will the VA provide IP information, VLAN setup, etc, to the security contractor for connection to the existing VA security network?
RESPONSE:
VA will assist in the coordination of obtaining IP addresses and configuration states required. Contractor responsible for all configurations and set ups.
77. What is the existing version of Victor and CCure at the VA hospital?
RESPONSE:
Software license is the most-current version as of 03/15/2024.
78. The hardware schedule in Specification 08 71 00 appears to call out Falcon as the manufacture for the door hardware. Is this correct?
This is a typographical error. Falcon hardware is not acceptable. Robert J. Dole VA station standard hardware is Corbin-Russwin.