S05 - Clarification and Answers Stockton 36C77624Q0127 - 5.9.24.docx
DOCX document 35 KB Posted
- Solicitation number
- 36C77624Q0127
About this file
This document is a set of clarifications and answers provided by the Department of Veterans Affairs (VA) in response to questions about Solicitation 36C77624Q0127 for the Stockton Community Living Center (CLC) and Engineering and Logistics Building (ELB) projects.
The key details are:
- The anticipated Beneficial Occupancy Date (BOD) for the CLC is 01/05/2027 and the anticipated BOD for the ELB is 10/31/2025. These dates differ from the timeline given in the Performance Work Statement (PWS), which indicated the ELB would be completed prior to the CLC. The VA clarified that the BOD and first patient day are not synonymous, and the activation timeline is typically 60 days, so patient day one is expected 60 days after BOD.
- The solicitation is for Initial Outfitting, Transition, and Activation (IOT&A) services for the Stockton CLC and ELB, to be provided to the VA Northern California Health Care System.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C77624Q0127 Veterans Affairs (VA) Northern California Health Care System Stockton Community Living Center & Engineering and Logistics Building Support Solicitation Clarifications & Answers
1. Question #85 Please provide anticipated BOD dates for both the CLC and ELB projects ORIGINAL VA Response - The anticipated BOD for the CLC is 10/31/2025 and the anticipated BOD for the ELB is 01/05/2027.
Please confirm the above dates in the VA response. These dates appear to conflict with the timeline given within the PWS for first day of clinical services. ELB appears to be completed prior to the CLC.
The beneficial occupancy day (BOD) and first patient day, or patient day one, are not synonymous. BOD is the first day the construction company turns over the finished building to the VA and activation begins. First day of clinical services is the first day the building is ready for patients. The Activation timeline is typically 60 days. Generally, patient day one is 60 days after beneficial occupancy. There is individual reference to both the BOD and Patient day one as those dates differ. The timelines for completion provided are correct. The ELB is projected to be completed well before the CLC.
CORRECTION TO ORIGINAL VA Response:
The anticipated BOD for the ELB is 10/31/2025 and the anticipated BOD for the CLC is 01/05/2027.