S05 - Clarification and Answers Stockton 36C77624Q0127 - 5.7.24.docx

DOCX document 36 KB Posted

Attached to
Q702--Initial Outfitting, Transition, and Activation (IOT&A) services for the Stockton Community Living Center and Engineering and Logistics Building
Solicitation number
36C77624Q0127
Issued by

About this file

This document is a set of clarifications and answers related to Solicitation 36C77624Q0127, which is for Initial Outfitting, Transition, and Activation (IOT&A) services for the Stockton Community Living Center (CLC) and Engineering and Logistics Building (ELB) for the Department of Veterans Affairs (VA) Northern California Health Care System.

The key details are:

  • The anticipated Beneficial Occupancy Date (BOD) for the CLC is 10/31/2025 and the BOD for the ELB is 01/05/2027. The BOD is when the construction company turns over the finished building to the VA, with activation taking about 60 days before the first patient day.
  • Relocation services are required to be completed within 30 days after BOD, even though installation and outfitting may not be fully complete at that time. The VA will not extend the 30-day relocation services deadline.
  • The solicitation is for the activation of the Stockton CLC and ELB facilities for the VA Northern California Health Care System.

View the file

Other files

File Type Posted
S05 - Questions and Answers Stockton 36C77624Q0127 - 5.13.24.docx DOCX document
36C77624Q0127 0008.docx DOCX document
36C77624Q0127 0007.docx DOCX document
S05 - Clarification and Answers Stockton 36C77624Q0127 - 5.9.24.docx DOCX document
36C77624Q0127 0006.docx DOCX document
ATTACHMENT V2b - Phase A CLC -Vol_A1_Drawings.pdf PDF
36C77624Q0127 0005.docx DOCX document
ATTACHMENT V2e - Phase A CLC - Vol_A1_Drawings.pdf PDF
ATTACHMENT V2d - Phase A CLC -Vol_A1_Drawings.pdf PDF
ATTACHMENT V2c - Phase A CLC -Vol_A1_Drawings.pdf PDF
36C77624Q0127 0004.docx DOCX document
ATTACHMENT V1 - Phase E ELB - Drawings.pdf PDF
ATTACHMENT V2a - Phase A CLC -Vol_A1_Drawings.pdf PDF
ATTACHMENT P2 - 21-09-21 Contents Acq Plan Phase A_4.29.24 REVISED.xlsx XLSX spreadsheet
S05 - Question and Answers Stockton 36C77624Q0127 .docx DOCX document
ATTACHMENT A - Final PWS - Stockton - FINAL-REVISED.docx DOCX document
ATTACHMENT B - Stockton Activation Project Timelines REVISED 4.30.24.xlsx XLSX spreadsheet
36C77624Q0127 0003.docx DOCX document
ATTACHMENT P1 - 21-09-21 Contents Acq Plan Phase E_4.29.24 REVISED.xlsx XLSX spreadsheet
36C77624Q0127 0002.docx DOCX document
36C77624Q0127 0001.docx DOCX document
ATTACHMENT R - PDAT Summary - Stockton.pdf PDF
ATTACHMENT C - Travel Authorization Request.pdf PDF
36C77624Q0127_1.docx DOCX document
ATTACHMENT N - Procurement Package Template 2022.pdf PDF
ATTACHMENT U - Wage Determination 2015-5653 Stockton.pdf PDF
ATTACHMENT H - Room Contents and Acq Plan Template.xlsx XLSX spreadsheet
ATTACHMENT K - Proposed FTE Report.xlsx XLSX spreadsheet
ATTACHMENT G - WBS Template.pdf PDF
ATTACHMENT P2 - DVA Livermore Phase A - Equipment List (2022-04-15).xlsx XLSX spreadsheet
ATTACHMENT J - Integrated Move Plan Template.xlsx XLSX spreadsheet
ATTACHMENT L - Furniture IDIQ Templates.pdf PDF
ATTACHMENT P1 -Phase E-Equipment List.pdf PDF
ATTACHMENT E - Risk Management Plan and Register Template.xlsx XLSX spreadsheet
ATTACHMENT T - Pricing Worksheet.xlsx XLSX spreadsheet
ATTACHMENT B - Stockton Activation Project Timelines.xlsx XLSX spreadsheet
ATTACHMENT D - Contract Staff Roster.pdf PDF
ATTACHMENT Q - QASP.docx DOCX document
ATTACHMENT M - JSN Responsibility Matrix.xlsx XLSX spreadsheet
ATTACHMENT A - Final PWS - Stockton - FINAL.docx DOCX document
ATTACHMENT O - 6500.6 Contract Security Appendix A.pdf PDF
ATTACHMENT I - Equipment Inventory_ReUse and Disposal Plan Template.xlsx XLSX spreadsheet
ATTACHMENT F - Change Management Plan and Log Template.xlsx XLSX spreadsheet
ATTACHMENT S - VSC Security Package.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C77624Q0127 Veterans Affairs (VA) Northern California Health Care System Stockton Community Living Center & Engineering and Logistics Building Support Solicitation Clarifications & Answers

1. Question #85 Please provide anticipated BOD dates for both the CLC and ELB projects VA Response - The anticipated BOD for the CLC is 10/31/2025 and the anticipated BOD for the ELB is 01/05/2027.

Please confirm the above dates in the VA response. These dates appear to conflict with the timeline given within the PWS for first day of clinical services. ELB appears to be completed prior to the CLC.

The beneficial occupancy day (BOD) and first patient day, or patient day one, are not synonymous. BOD is the first day the construction company turns over the finished building to the VA and activation begins. First day of clinical services is the first day the building is ready for patients. The Activation timeline is typically 60 days. Generally, patient day one is 60 days after beneficial occupancy. There is individual reference to both the BOD and Patient day one as those dates differ. The timelines for completion provided are correct. The ELB is projected to be completed well before the CLC.

2. Question #49 - PWS; 18.1 Deliverable Schedule (pg. 26-28); The deliverable schedule indicates that relocations should occur no later than (NLT) 1 month post BOD, however installation and outfitting would not be completed at this time. Will relocations occur closer to First Patient Day?

VA Response: Relocation will occur closer to First Patient Day.?

3. Question #72. PWS, 18.1. Deliverables 17.3.1 and 17.3.2, Relocation Services due date of NLT 1 month post BOD. ... Would you consider this and extend these two due dates to a time closer to the end of activation and just prior to Day 1 (at the end of the Relocation CLIN POPs)? (PWS Page 28) VA Response: At this time, we will not consider an extension of these due dates.

For the purpose of providing the VA an optimal and accurate initial schedule with our proposal, can you please clarify on the deliverable due date for Relocation Services.

The timeline for activation is typically 60 days. To meet this goal, installation and service relocation should occur as soon as possible after BOD. Therefore, the deliverable schedule for relocation services should remain as NLT than 30 days post BOD.