This document is a Pre-Bid Request for Information (RFI) Response Log related to a federal contract opportunity for the Prescott EHRM Data Center VA Project Number 649-22-701. The key details are:
The RFI responses provide clarification on various aspects of the project, including ductbank and manhole details, fiber optic cabling requirements, video surveillance and access control system specifications, and construction phasing and coordination. The project involves upgrading the IT infrastructure at the Prescott, Arizona VA campus, including a new data center in Building 166 and fiber optic cabling connections to multiple existing buildings. The government has provided additional details and drawings in response to the RFI questions to assist bidders in preparing their proposals for the solicitation. The related federal contract opportunity is Solicitation Number 36C77624B0008 for the EHRM Infrastructure Upgrades - Tier 2 project.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: Prescott EHRM Data Center
VA Project Number: 649-22-701
Pre-Bid RFI Response Log
Item
# RFI VA Response
There are not any drawings and details for the duct bank areas that are to be added. Can we get drawings and details of the duct banks with conduit sizes and layouts? The only information we have is its either 2 x 3, 2 x 2, or
2 x 1 duct bank. How deep will it need to be? What size conduits? Will they be Schedule 40 conduits?
Follow ductbank details previously on 3/E-502. Detials have been moved to T-503 in revised plan set for clarity. Schedule 40 conduit is acceptable. Ductbank must have 24" of cover.
Can we get details and detail drawings on the new manholes? Drawings call for 4’ x 8’ but doesn’t state how deep it needs to be? However, the specs call for 6’ x 9’ x 7’ manholes. Which is correct? Manhole details have been added for duct bank to sheet DT101.
On the fiber riser drawings T-601 it shows some 24 strand MM OM4 fiber appearing in what I believe to be in building 107 out to other Tr’s in Building
107 but not sure which TR they are originating from in 107. Can we get more clarification as to where these MM fibers will originate from?
Disregard multimode fiber reference. Has been removed in revised drawing.
Specs call for the MM fiber to be preterminated armored fiber with MPO connections on each end. Can we get floor layouts for Building 107 with TR locations so we can figure out the footage we will need for each run and to be able to identify the room locations and pathways during installation?
Pre-terminated fiber is only required in the data center to connect network cabinets to HDA's fiber from data center to TR's does not need to be provided. Drawings of floorplans will be provided for footages.
Can we get floor layouts of all the buildings with TR locations that fiber will be running to, to figure out the footage in the buildings and be able to identify the room locations and pathways during installation?
T-401-404 sheets have been added to the sheets to depict this information for each building
Specifications call for loose tube gel filled SM OS2 fiber, but they also call for armored indoor/outdoor rated fiber? Which is the preferred fiber for this application between building? Is loose tube or tight buffered preferred? Indoor/Outdoor armored loose tube gel filled is required.
Will innerduct be required in the newly added duct banks? If so what kind and size and how many will need to be installed either per conduit or total for that section of the duct bank? No, not required.
Will inner duct need to be installed in any portions of the existing duct bank? If so, what kind and size and where in the existing duct bank will it need to be installed? How many will need to be installed either per conduit or in total for those areas? No, not required.
REQUIRED
Some of the markings on drawing CU101are off. For instance, new manhole T-4 near building 70 shows it in the middle of nowhere. Should it be in line with the duct bank? Or does the duct bank need to be in that location and then into building 70? Or is it supposed to be where I have the red arrow going to on the attached drawing? T-4 Label moved to correspond with correct manhole location.
In the attached drawing is the assumption as its laid out the correct assumption? All of the duct banks are new. 2 x 3 in the right areas, 2 x 2 in the right areas, and 2 x1 in the right areas? New and existing manholes in the correct locations? Duct bank sizing has been confirmed on updated plans.
Will the New manhole on the backside of Building 166 heading to building
12 be labeled manhole ‘T – 8’? There is not a ‘T – 8’ on Fiber Riser drawing T-601?
Route from data center to building 115 is just for power. Data will run through proposed manhole E-1 to building 12. Need to clarify this on our plans. Proposed fiber optic manhole changed to electric manhole and lines changed from fiber optic to electric.
On drawing T-601 it shows (1) fiber pull per comm room, On Drawing T-
504 it shows (2) of each SM pulled from building 166 to each telecom room. (1) for A and (1) for B which is correct?
One run of fiber will be run from building 166 all the way to the TR's .
The other run of fiber will be extended from building 12 to the new data center. this has been clarified on T-601 and TS102
Will the same be for the MM fiber (1) per room or (2) per room? (1) for A and (1) for B?
New fiber runs from the DC to the closets will noly be 24 strand single mode. Existing 28 fibers that will need to be spliced and extended from building 12 are 24 SM/ 24 MM hybrid fiber cables. there are 28 cables needing to be spliced and extended.
Where are the racks located on Drawing T-505? Some of them state where the fiber is either coming from or heading to and the others just say fiber distribution. Can we assume these are the Tr’s we are running the new fiber to and some of these are existing fiber? These cabinet numbers do not match up to the ones on drawing T-504. So, there is some confusion with these locations. Can we get more clarity?
B01 would be B1 on T-101. The b side string has been mirrored and the syntax clarified on the revised drawing set.
Some of the manholes on drawing T-601 do not matchup to the locations on drawing CU101. Can we get some accurate drawings that matchup?
There is not a building 12 on the T-601 drawings but we are running a duct bank to it on the CU101 drawings. Is there supposed to be SM fiber running to building 12? There is also not a building 115 on the fiber riser drawing T-601 but duct bank is being installed to it on drawing CU101. Is there supposed to be SM fiber running to it also? Ductbanks have been clarified. Run to 115 is for electrical
If the fibers in building 107 originate from one of the TR’s on the first floor is there supposed to be (1) or (2) mm fibers that run to the other TR on the first floor? If they originate on the second floor do both TR’s on the first floor get (1) or (2) mm fibers to each of them?
Disregard multimode fiber reference. Has been removed in revised drawing.
The plumbing drawings show a roof drain, with no overflow. Typically, we see an overflow for roof drains. Please confirm no overflows are required.
NO roof drains are shown on Plumbing drawings. The roof is drained by external gutters and downspouts (see architecture drawings). There are two AREA drains in the service yard (ground level). No overflow is required for the area drain.
Drawing T-601 the callout “(7) 24 MMFO AND 24 SMFO” this appear to be a typo as it conflicts sheet note “B”. Please confirm this should read “(7) 24
SMFO” and update the drawing accordingly.
Disregard multimode fiber reference. Has been removed in revised drawing.
Drawing T-601 the callout “(19) 24SM OS2” appears not to include (1) SM
OS2 for Building 162 Room 1E-134. This miscalculation continues in following aggregation of cables to Bldg 166. Please confirm the number of cables being placed for this project and update the drawing accordingly.
Include (1) 24SM OS2 from building 162 room 1E-134 back to building
166.
Drawing T-504/Detail 1- Cabinet “A04” indicates a Fiber Aggregation Panel for Cabinets “B11,B12,A11,A12”. On drawing T-101 cabinets “B11,B12 &
A12” are not shown, should these cabinets be marked as future. and update the drawings accordingly.
A11 is not future. All others would be future. Have updated drawing accordingly.
Drawing T-504/Detail 2- Cabinet “B04” indicates a Fiber Aggregation Panel for Cabinets “B11(FUTURE),B12(FUTURE),A11,A12”. On drawing T-101 cabinets “B11,B12 & A12” are not shown, should cabinet “A12” be marked as future, and update the drawings accordingly.
A11 is not future. All others would be future. Have updated drawing accordingly.
Please provide the sizes and configurations of the MDA/HDA/EDA cabinets depicted on Drawing T-101 buildout.
Network cabinets are basis of design Chatsworth ZB14-A222A-E1 or equal. HDA and MDA cabinets to be Great lakes GL840ES-2442-W-
MSS with sidecars SC128442 OR SC68442 or equal on both sides
Drawing T-101 indicates the installation of 30”x4” and references Detail3 on T-503. Which shows two-tier white powder coat basket tray. Please confirm white powdering coating is required as is not called out in project specification. Confirmed, powder coating is required.
Drawing T-504/Detail 1- Cabinets “A01&A02” depicts the “A-Loop” OSP
Fiber Distribution Racks and Enclosures. For the fiber cables which are to be intercepted and rehomed to the new DC. The note on the drawing TS-
102 “Tech Site Plan” states (28) 24MMFO/24SMFO are to rehomed. Per
Detail 1 there are (37) cables to be rehomed.
a. Please confirm the correct number of cables that are to be rehomed to the new DC?
b. Please provide details on the desired orientation of MM/SM splice cassettes in the individual enclosures.
50 is the correct number of 24 SMFO/ 24 mmfo cables. Splice cassettes should be horizontial.
Drawing T-504/Detail 2- Cabinet “B03” fiber aggregation panels appear to be duplicates of panel in Cabinet “B04”. Please confirm if these are required? B03 fiber aggrigation panels are redundant.
Drawing T-504/Detail 2- Cabinets “B01&B02” depicts the “B-Loop” OSP
Fiber Distribution Racks and Enclosures. It includes panels for Buildings
12,13,15,16, 20, 22, 28 &105. Connections to these buildings are not shown on the Drawings T-601 & TS-101. Please confirm they are to be included as part of this project, and update the drawings accordingly.
Noted buildings get connected to the new data center thrtough splicing and extension of the fibers from building 12 to the new data center.
They don't receive redudant fiber which is why they are excluded from the T-601 & TS-101 routing plans
Drawing T-504/Detail 2- Cabinet “B02” multiple fiber aggregation panels appear to be duplicates of panels in Cabinet “B01”. Please confirm if these are required? Detial has been clarified in revised set
Drawing E-502/Detail 3 shows the construction details for required concrete encased duct banks. Note#5 states “innerduct quantity and size as indicated on plans”. The civil and technology drawings do not indicate this.
Please provide the required quantity and configuration of the innerducts for each section of new OSP duct system, and update the documents accordingly. No innerduct is required.
Drawings for CCTV cameras & Bid spec documents do not specify what
Camera system is currently in place for this project, please answer the following questions:
a. What is the manufacturer of the current video management system?
b. On what existing software version is the current video management system operating?
c. Are we expected to support version upgrades as part of this contract?
d. Are there sufficient existing Camera icenses to support the new cameras?
Existing camera paltform is Vision by Identive.
All cameras to be dome type.
POrovide all cameras as multisensor.
All storage capacity exisits.
Provide a network switch and patching to connect camra switch to the police building using existing fiber pathway.
Question 30: Drawings for card reader/pin pad, & Bid spec documents do not specify what Access Control system is currently in place for this project.
Please answer the following questions:
a. Who is the manufacturer of the current access control system?
b. What is the existing software version of the access control system operating?
c. Are we expected to support version updates as part of this contract?
d. Are there sufficient licenses to support the new doors?
e. Is there any existing integration between the access control and CCTV systems?
f. If so, what is the base platform (Access Control or Video) that operate both?
g. Is there a current vendor/installer of this system that we can contact?
h. Is there an existing SSA in place for Access Control, and who is vendor servicing SSA?
i. Are there existing software licenses available from the VA that can be used for new reader / Controllers?
j. Does new access control need to be FICAM Compliant? Is there a current FICAM License?
k. Is CESIP Certification required?
Existing system is Hirsch.
Will need to support version updates.
New licenses will need to be provided. no integration with CCTV is needed. Cannot provide existing vendor. Sytem does need to be
FICAM under the existing license compliant and CESIP certification is required.
Is the new fire system to be tied into existing system for the facility? (it is noted that it is Notifier) Or will it be a standalone system? See TS102 for connection detail to building 12
Are there any specifications on the security system manufacturer? I have gone through and only found general references to (PACS) which is just an acronym for reference to the security system. Is this stand alone or again like fire tied to the existing system?
Physical Access Control System for doors will need to be tied through door control system. Current system is hirsch.
33 Can you provide any pictures of the existing system for the main campus?
Request is not clearly defined as to which system. IT spaces are controlled spaces and images of the equipment are not permitted.
34 Please advise on deck height between floors in the existing buildings. Assume 15' for bidding
Please provide as-built drawings that show the locations of all existing
IT/TR rooms in each building affected by this project.
T-401-404 sheets have been added to the sheets to depict this information for each building
Please advise on the existing manufacturers for the Fire Alarm, DDC
Controls, CCTV and Access Controls systems. Fire alarm is notifier, Access controls is Hirsch.
Please confirm there are enough existing licenses available for the Access
Control additions based on this project's scope of work.
Please confirm there are enough existing licenses available for the CCTV additions based on this project's scope of work. Existing license will accommodate additions.
Please confirm that stored materials can be billed for on this project.
Please advise of any procedures or verifications required to submit for stored materials billing This will be determined by the Contracting Officer at the time of award.
Please confirm work within building will be completed during normal hours.
If not, please provide a phase requirement for each building.
It is anticipated that work can be completed during normal hours, but may need to be adjusted to off-hour work if necessary due to need.
Please advise if road patching is acceptable or if the entire road should be repaved from curb to curb
Road patching is acceptable. Road patching of subbase and asphalt/concrete to match existing conditions of road. VA details added to plans, see sheet DT101.
Please provide a road patching detail that includes asphalt type
(specification), asphalt thickness with subbase and base requirements along with any other related requirements.
Road patching is to match existing cross section. Refer to Geotech report for additional guidance on road cross sections. VA details added to plans, see sheet DT101.
Please provide a geotech report for all excavation and ductbank areas as related to this project.
Note referencing past geotechnical report added to sheets CG100, CU100, and CU101.
Please confirm that the entire ductbank can be worked on at once. If not please advise on phasing requirements- ie number of phases, length available per phase etc A note has been added to sheet CU101 regarding phasing.
Please confirm that there are no fire extinguishers required in the service yard, secured storage and/or storage areas.
There are three fire extinguishers located in the new facility and all are withing the travel distance of the spaces in question.
Sheet CD101 is labeled as "Demolition & Stormawater Management Plan" which shows a line labeled "SF" indicating silt fence locations. However, it is not clear where silt fence is required. Please clarify the extent of the silt fencing and indicate the locations(s), if any are necessary.
Contractor to use BMP to protect all existing inlets and catch basins during construction of duct bank. Silt fence is to be installed on open space areas with a downward slope to ensure sediment does not enter existing storm infrastructure.
Per note at top of page near building 14 we are to tap into existing MH14 for the fiber ductbank. Please provide tapping/penetration/patching detail, existing manhole construction details, and advise what side of the structure to tap.
Tapping of the existing manhole should be achieved by a core drill or sawcutting the side of the manhole to allow for a clean connection of the proposed duct bank. Contractor to ensure a straight connection at the existing manhole and to limit any large angle differences.
Existing license will accommodate additions.
Please provide fiber optic manhole detail/constrction type. Or are the fiber manhole on plan supposed to be handholes? 4' Flat Top Variable Depth Manhole detail added. See sheet DT101.
Please provide building connection/tap/stub out/wireway detail for ductbank connections to buildings
Civil scope stops 5' from building foundation. This electrical line looks to be within 5' of the building foundation. Storm Profile shows 6" depth of 5' so dry utilities should not be in conflict. City of Prescott requires 2' of vertical clearance between utilites.
Between station markers 11.00 and 11.50 (between MH-01 and MH-02), it shows an existing electrical line crossing the new sanitary line, but the existing electrical line is not shown on the conflict details. Please provide detail for this conflict.
Storm Profile shows 6" depth of 5' so dry utilities should not be in conflict. City of Prescott requires 2' of vertical clearance between utilites. Crossing is now shown in profile.
Between station markers 100 and 101, it shows an existing electrical line crossing the new 6" PVC storm line leading to the water basin, but the existing electrical line is not shown on the conflict details. Please provide detail for this conflict.
Civil scope stops 5' from building foundation. This electrical line looks to be within 5' of the building foundation. Storm Profile shows 6" depth of 5' so dry utilities should not be in conflict. City of Prescott requires 2' of vertical clearance between utilites. Crossing is now shown in profile.
Sheet CU-100 calls out a wet tap connection for the domestic water.
Please provide a wet tap connection detail includng the sizing and material of the existing watermain and fittings required to provide 2" copper water service to the building.
COP Standard Detail 316P will be provided on Civil Detail Sheets, See sheet DT101.
Sheet CU-100 calls out a wet tap connection for the fire water. Please provide wet tap connection detail including the sizing and material of existing pipe and fittings required to provide the new 6" DIP fire service.
COP Standard Detail 340Q-1 will be provided on Civil Detail Sheets, see sheet DT101.
Per Sheet CG-100 (Note #1) shows a new Gravel access road. Please advise on the thickness of the gravel access road should be and provide specifications on the material.
Gravel Access road to be constructed per COP Standard Detail 612P.
Standard Detail will be added to Civil plans, see sheet DT101.
Per Sheet CS-100, Note #14 states a new driveway cut but Note #14 is not located on the Site Plan. Please clarify this note. Note #14 added to driveway cut location.
Per Sheet CS-100, the Access Road is shown as a gravel road per the legend but Sheet CG-100 shows very specific elevations and slopes, possibly implying a hardscape finish. Please confirm the construction materials of this Access Rroad and if it is to be gravel please confirm that the sloping of gravel is not expected to be maintained as a warranty item.
Gravel Access road to be constructed per COP Standard Detail 612P.
Standard Detail will be added to Civil plans on sheet DT101. Note regarding maintenance added to sheet.
Per Sheet DT-100, the Low Tail Water Basin detail indicates a concrete headwall. Please provide all necessary construction details and specifications, wall sizing, rebar requirements, concrete requirements,...
Please clarify if this headwall is to be poured in-place concrete or a CMU structure with concrete filled cells.
Dimensions of concrete headwall have been provided. No rebar reinforcement required and to be cast-in-place.
Per Sheet S-001 (Foundation Notes), note #1 references a Geotechnical
Evaluation Report dated November 10, 2017. Please provide referenced report since it is applicable to this project.
Reference spec sections 02 41 01, 02 41 02, and 02 41 03 for geotechnical reports to be utilized.
Under foundation notes it references dewatering requirements. Please provide the water table elevation that we should utilize during the bid process. Please also advise on dewatering discharge approved location in order to properly price this item which needs to include pump size, discharge pipe length, gas, No specific borings have been advanced on the project site. Extent of dewatering, if any, is unknown.
Per Sheet S-001, Concrete Notes - #16, it requires slab modifications if the
"flatness and levelness are not accepted" by the Architect. This leaves the requirements to be subjective. Typically a variance per foot is provided as a standard. Please advise on the allowable variance for slab levelness and flatness.
See specification section 03 30 53 part 3.4 for required values. Note
#16 is related to to not meeting these requirements.
Per Sheet M-001, Mechanical General Note #27 seems to imply that BIM or coordination drawings for above ceiling systems need to be provided for this project and that these drawings must be approved prior to starting any fabrication of materials. Since the building is under 2,000SF, please advise if BIM engineering is required and if so do the BIM drawings need to be approved prior to starting the fabrication of materials or can this note be voided in the Bid Documents.
Yes. Coordination drawings are required since it is a data center and is a critical use. It doesn't have to be BIM specifically, but it does need to be coordination across disciplines to ensure everything will fit.
Drawings need to be approved prior to installing materials otherwise contractor retains liability that it will all fit.
Per Sheet M-501, Details #3 and #4 are illegible. Please provide legible details. We will reissue details sheet in its entirety.
Per Sheet E-502, Note #2 on Detail #3 states that reinforcement is required in the ductbank in all roadways. However, in the civil details on Sheet DT-
100 shows no reinforcement. This entire ductbank is below a roadway.
Please confirm if rebar is required for the entire ductbank.
Reinforcement will be required for all ductbank sections. Rebar detialing added to detials on T-503
If Concrete Reinforcement is required for the ductbanks, please provide a proper detail and sizing requirements (Reference note #2 on Sheet E-502) which will need to include proper steel grade selection, reinforcement sizing, specifications and reinforcement details.
Reinforcement will be required for all ductbank sections. Rebar detialing added to detials on T-503
Per Sheet TS-101 (Note B), please advise on construction of floor type for buildings 117, 160, 148, 14, 70, 161, and 151 in order for the Contractor to determine proper lengths and routing.
T-401-404 sheets have been added to the sheets to depict this information for each building
Per Sheet TS-101 (Note B), please advise on firewall locations in buildings
117, 160, 148, 14, 70, 161, and 151 in order for the Contractor to determine the proper lengths and routing.
T-401-404 sheets have been added to the sheets to depict this information for each building
Per Sheet TS-101 (Note B), the Contractor needs to verify exact locations of the TR Rooms and is responsible for verifying legths and routes. Since this is a Bid Requirement, please provide accurate as-built drawings for all floors of all buildings affected by this project in order for the Contractor to properly determine this information.
T-401-404 sheets have been added to the sheets to depict this information for each building
Since all the rooms and ceiling spaces that would need to be accessed for conduit runs were not available for review during the site walk, will there be a follow-up site walk scheduled in the near future prior to bid so we can access and review these spaces?
T-401-404 sheets have been added to the sheets to depict this information for each building
Please confirm if directional boring can be utilized at the road crossings and that the steel reinforcement in the ductbank would be omitted at these locations. If required, per previous RFI- Specifically the road between new
MH T6 and TR rooms 1E-134 and 1E-241. Directional boring is not allowed.
Per Sheet T-601, the one line diagram shows room A-135 in Building 148 but floor plan calls it room A-134 in Building 148. Please clarify. See T-400 sheets for physical location.
Per Sheet FA-101, Fire Alarm General Note #4 states that the Contractor is to "Before starting work, test existing fire alarm system in work area and adjacent areas." Please clarify what areas buildings that this note applies
to. Do we have to test all buildings within the scope of work or just some?
if so which ones?
Only need to test the fire alarm tie in point at building 12 to ensure it is working prior to begining work
Per Sheet FA-101, Fire Alarm General Note #7 requires the Contractor to
"Make repairs to resolve incorrect system operations at no additional cost."
Since this scope of work cannot be identified until we test the existing system (and per previous RFI, what buildings need to be tested is undefined), please confirm this note only applies to new devices within the new building.
Notify COR of any difficencies discovered. Bid work as shown on plans and specs.
Per Sheet FX-001, Fire Suppression General Note #14 states that the
Contractor is to "Repair or replace any non-conforming and inadequate work at no additional cost to the VA." Please confirm that this note only applies to work installed under these Bid Documents and that existing condition deficiencies are not the responsibility of the Contractor.
Notify COR of any difficencies discovered. Bid work as shown on plans and specs.
Per Sheet FA-101, please confirm that there are no pull stations required in the Secure Storage Room (#106). No bid as shown.
Per Sheet A-601, the Door Schedule states that Door Opening #106 is to be a type B door. Per Sheet A-101 (Note #4), this opening is within a fence for the secure storage area and should include a "gate." Please confirm that this door is to be a gate matching the fence type and profile being installed for the secure storage area. If this opening is to be a solid door, please provide a proper elevation and related details of the fence to door frame or door condition which will include any required engineering to hold the door up within the fencing structure (i.e. concrete filled posts or frames....). In addition, if this opening is confirmed to be a door, please provide door materials (i.e. galvanized steel per the Door Schedule).
The elevation is representation of the door and the 106 door is a gate that is part of the chain link fence spec, thisi s noted in the remark section. See Specification 32 31 40.
During the sitewalk it was noted that there is a "Serenity Pad" and monument in line with the new building/ductbank locations. Please provide scope of work and corresponding design drawings for this item (see picture labeled "RFI#43 - Serenity Pad). Ductbank Routing will be altered to avoid. See sheet CU101.
During the sitewalk it was noticed there was a directory or monument sign within the sitewall to be demolished. Please provide scope of work and corresponding design drawings for this item (see picture labeled "RFI#44 -
Monument Sign). Ductbank Routing will be altered to avoid. See sheet CU101.
Per Sheet ES-101 (Note #5), please provide pictures of the existing UPS to be relocated in Building 12 as this area was not accessible during the site walk.
Access to the UPS system was part of the site walk-through. All participants were given an opportunity to see the system.
Per Sheet CD-101, it shows the ductbank crossing into a courtyard before entering Building 151. Please provide a complete civil design for the landscaping including hardscapes in this area. (see picture labeled
"RFI#46 - Courtyard 151). Ductbank Routing will be altered to avoid. See sheet CU101.
Per sheet ES-101, please provide pictures of the inside and outside of normal power panels (115-1X-2 and SES-12 ) as they were not accssible during the site walk.
At the site walk it was noticed at some buildings there was a drainage ditch surrounding the building(s). Please provide a detail for ductbank connections at this condition. Please clarify if the Contractor should go below or through the space (see picture labeled "RFI#48 - Drainage
Ditch).
Routing adjustments have been made so that this condition should not exist.
Please provide as-built drawings that show the RCP/ceiling types in all the existing buildings and floors in order to properly price this work as the existing buildings were not accessible during the site walk.
T-401-404 sheets have been added to the sheets to depict this information for each building
Per Sheet CD-100 (Key Note #6), staes "Existing electric line to be relocated." This scope of work does not appear on the Electrical drawings.
Please clarify scope of work and provide engineering and design for this scope electrically.
Sanitary sewer alignment has been adjusted so that electrical line does not need to be relocated. See sheet CU100.
Per Sheet CD-100 (Key Note #3) states "Existing sign to be removed."
The plan shows two (2) building sign locations to be removed but during the site walk there was only one (1) building sign present. Please provide pictures of the signs to be removed and clarify the scope of work (see picture labeled "RFI#51 - Missing Signs). Sign demolition has been updated. See sheet CD100.
Since this is private property can owner have private blue stake mark all utilities in duct bank path for conflict crossings prior to bid opening
No. Contractor will be responsible for providing private utility locate prior to digging.
The specifications do not list requirements for archaeology monitoring for earthwork operations. Please confirm that any fees archaeology/ monitoring related to this project will be a paid for by the Government and will not be the responsibility of the contractor.
The requirement for archaeological monitoring is indicated in the SOW indicating the responsibility and cost on behalf of the contractor.
Please provide a phasing plan for roadway closures related to trenching activities. A note has been added to sheet CU101 regarding phasing.
Pictures are provided in attachment ELEC-A. Internal pictures of SES-12 are not provided due to inaccessibility.
Will we be able to shut down the roadways in the areas of trench excavation?
Contractor to be responsible with creating Traffic Control plan and implementation and ensuring crew safety during construction.
Coordinate Traffic Control Plan with VAMC
89 Will a 3rd party traffic control plan be required for this project?
Contractor to be responsible with creating Traffic Control plan and implementation and ensuring crew safety during construction.
90 Please provide as built plans for the VA site utilities/underground.
We have this included as an overlay on the site plans. If there are other pertiant maps that the VA feels are appropriate it may be helpful to the contractors.
Note 10 on sheet CD100 says to remove existing communication line. Is this line abandoned? Please provide clarification for removal of existing cabling in this raceway including locations of each end termination and affected buildings and services.
Communications line to be removed and relocated outside of building footprint/foundation.
Note 9 on sheet CD100 shows a sanitary sewer line to be rerouted, please provide the expected flow rate/volume for this line and affected buildings.
Does the VA expect temporary pumping to be required to maintain service to the affected buildings?
Expected flow rate/volume are not required as Civil is proposing the same size piping that is existing, and re-routing is to ensure sewer main does not run under building footprint/foundation. Sanitary Sewer additional flow is the equivalent of one single use bathroom.
Note 2 on sheet CD100 calls for an existing landscape wall to be removed.
What is the composition and dimensions of the existing landscape wall? Plans have been revised and wall is now called out as protect-in-place.
Note 4 on sheet CD100 calls out an existing light pole to be relocated, however the light pole is not shown on the electrical site plans, please verify circuiting, conduit routing and new location of the light pole. Demo on sheet CD100 has been updated regarding this comment.
Please provide a plan detail for the new light pole base required at the new light pole location. Plan has been adjusted so that pole no loger needs to be relocated.
Note 6 on sheet CD100 calls out an existing electric line to be relocated.
This line is not shown on sheet ES101, and no details have been provided.
Please provide a one line drawing, conduit and wire details, depth of raceway information for the existing electrical line. Is the conduit encased?
Sanitary sewer alignment has been adjusted so that electrical line does not need to be relocated. See sheet CU100.
97 Where is the going to be relocated to? Reroute information is not shown. Question cannot be answered.
At the site visit, it was observed that the existing UPS to be located will require the existing door frame to be removed to enlarge the opening to allow for the UPS to be removed. Please confirm if the UPS can be removed without enlarging the door opening, and what the existing wall construction type is if the frame will require removal.
Existing door frame will not need to be removed to relocate UPS.
Sheet DT100 shows ductbank details as well as a sewer manhole detail, but does not show a detail for the new fiber optic manholes. The electrical plans do not show the manhole detail. Please provide a plan detail for the fiber manholes. Please also include drainage and subgrade details for setting the manholes.
A detail for the electic manholes have been added to Sheet DT101.
Installation and site prep needs to be done per the Quad City Standard
Details for manhole installation.
100 Will existing native soil be acceptable to use as trench backfill? See trench detail for backfill requirements.
Note 15 on sheet FX101 states that “all windows/ceilings/doors shall be reinforced to withstand pressure spike during clean agent discharge”. The plans/specs do not provide any information for this requirement. Please confirm that the contractor is not required to provide anything beyond what is shown on the plans.
Note 15 is provided on a plan of data center room on FX101 as a requirement and should be performed.
5/P-502 shows a water treatment cabinet/system, however this cabinet/system is not listed in the specifications and cannot be found on the plans provided. Please confirm that this is not applicable to this solicitation.
Detail 5/P-502 of water treatment cabinet/system will be removed from the sheet since water treatment cabinet type has been changed. Water treatment cabinet is labeled as WT-1 and is shown on Plumbing and
Mechanical drawings (PW101 (see note 7), PP101 (see note 3), MH101 (see note 7)).
Remark note 9 on sheet E-601 says that indicated feeders are to be aluminum. Please confirm if aluminum conductors are to be used for the cabling shown on the feeder schedule, or if conductors are to be aluminum. No. Utilize copper.
Please confirm if there is existing cable tray/pathways to be used for new fiber optic feeds inside each existing building that is refed.
Bid installtion fo j-hooks for all fiber install above ceiling. Install hooks every 5 feet.
Is conduit required for fiber optic pathways to be installed inside the existing buildings? No armored fiber can be run outside of conduit
106 Please provide fiber optic routing plans for each existing building.
T-401-404 sheets have been added to the sheets to depict this information for each building
Please provide details and drawings for the penetration/transition of exterior site underground raceways to each existing building for the new fiber optic raceways.
T-401-404 sheets have been added to the sheets to depict this information for each building
Will cable pulling operations for the existing buildings be allowed to be done during daytime hours?
The general answer is yes, but does not eliminate the possibility based on VA need that pulling may occur outside of normal business hours.
109 Will innerduct be required for all new fiber optic underground raceways? No innerduct is required.
Note 1 on sheet T-601 says that no new cabling is installed for this contract, however fiber optic cabling is shown on the one line drawing on sheet T-601. Please clarify.
Note 1 refers only to copper ethernet cable in the buildings outside the data center. Fibner optic cabling is required poer the drawings.
111 Is the steel fabricator required to be AISC certified? Yes
Please confirm that the VA will provide the commissioning agent per 01 91
00 and that the contractor will not be required to provide the CXA or fees for the commissioning agent.
Confirmed. VA will provide commissioing agent. Contractor will need to porovide contractors comissioning representation per commissioing specifications and will need to conduct all tests required by specs for observation by the comissioning agent.
Please provide a hazardous materials survey for buildings where new fiber optic pathways will be installed.
Available survey information in Attachment ENV-A
Will the VA provide keys to each Telecommunication Room in order to allow the general contractor access to each room without the COTR present? This is a possibility but may not occur due to security reasons.
Will the VA require every person (including all general contractor and subcontractor employees) to have a PIV Badge in order to enter and work in a Telecommunication Room?
Access will be granted through contractor badges provided by VA Police and may be monitored by VA staff.
116 Will the VA provide a power source for the hook up of a jobsite trailer? Electrical power for job-site trailer will be the contractor's responsibility.
Where, on property, will the VA allow the general contractor to set up a jobsite trailer and laydown yard? To be determined after award.
118 Will the VA require a cost loaded project schedule for this project?
Reference spec 01 32 16.15 Project Schedules.
Section 01 00 00, Paragraph 1.10, requires the contractor to provide a testing and commissioning plan. Please confirm that the VA will enforce the requirements of Paragraph 1.10 on this project.
Yes contractor will be required to follow the comissioning requirements of this job.
120 Will the VA provide the HEPA Carts? This will be a contractor responsibility.
121 Will the VA require a cost loaded project schedule for this project?
Reference spec 01 32 16.15 Project Schedules.
Will the VA permit the use of Procore for the FTP file sharing system, the processing of RFIs, Submittals, and other project related functions?
VA will accept the use of Procore for project functions, but does not specify the platform for use.
Will the VA permit the Project Superintendent to act as the Site Safety and
Health Officer?
Reference spec section 01 35 26-10. The requirement for the SSHO to be an individual separate from the superintendent has been added.
Will the VA require a second person onsite full time to act as the Quality
Control Manager?
Reference spec section 01 45 00. Highlighted portions in the attached document indicate that this should be a separate individual.
Please provide the ICRA level expected for each existing building area for new fiber optic cabling routing.
Assume all work outside of buidlnig 166 is medium risk group 2 per
ICRA on G-003
In what areas of the hospital, if any, will the VA require work to be performed from a HEPA Cart?
Assume all fiber pulling outside of building 166 to be performed in a
HEPA cart.
127 Will the VA provide the HEPA Carts? This will be a contractor responsibility.
Will the VA require Construction Quality Control Management per Section
01 45 00 on this project? Yes
Will the VA require a Stormwater Pollution Prevention Plan for the exterior duct bank installation work?
Contractor to use BMP to protect all existing inlets and catch basins during construction of duct bank. Silt fence is to be installed on open space areas with a downward slope to ensure sediment does not enter existing storm infrastructure.
Will the VA require the general contractor to secure a Stormwater Pollution
Prevention Permit from the local government agency? Yes
If the VA is hiring the commissioning agent, please identify the name of the firm that will act as the commissioning agent? The A/E firm Apogee will be the comissioing agent.
Please confirm that where the specifications provide for a warranty over 1 year in duration that the warranty period beyond 1 year can be satisfied by a manufacturer’s issued warranty.
Correct, construction warranty is one year. Manufacturer warranty will extend beyond one year based on material or equipment.
Are all cameras required to be Multi Sensor as per plan page T-502 Detail
Notes E. Some of the cameras on plan page T-101 don’t have the (MS)
Multi Sensor symbol. Yes, provide all cameras as multi-sensor.
134 What Video Surveillance VMS are we using Hirsch Vision or Vivotek? Cameras are Vivotek on the Hirsh Vision server.
Does the existing Video Surveillance server have room for the cameras proposed on this project? Yes.
Does the existing Video Surveillance server have storage room for the cameras proposed on this project? Yes.
137 Is an additional Video Surveillance workstation needed for this project? No.
Who is providing network switches for Card Access and Video
Surveillance?
Contractor to provide switch to be patched to fiber network in 166 to connect to the existing police building on existing fiber.
139 Who is providing the UPS for the network switches? Network switch will be connected to the central UPS for the building.
Detail 11 on sheet A-601 shows a resinous wall coating above the prefabricated cove base, however the finish schedule does not call for a resinous wall coating. Please clarify. No resinous wall coating, shall be paint.
Please confirm that all steel joists and decking are to be painted per section 09 06 00
Yes, steel joists and decking to be painted P-2 in rooms with exposed structure except Data Center.
Please confirm if Stonhard is the basis of design for the Res-1 and Resb-1 finishes. Yes, it is both.
143 Are we required to use “Creative Signage” for the building sign?
Contractor to match Creative Signage design as they are campus standard.
Please provide the thickness and profile of the existing roadway asphalt.
No thickness for the existing asphalt paving has been provided.
Civil does not have existing asphalt cross sections. Roadway patchwork to match existing depths and cross section of exisiting. VA patchback details added to sheet DT101.
I have not found a chilled water piping diagram or design for piping from chillers to CRAC units. Will there be one coming out?
The units are DX so from each Condensing unit, refrigerant piping
(sized, pitched, and routed based on manufacturer recommendations) is to be connected to indoor CRAC units.
The plans are not clear on the supply discharge from the CRAC units into the it room. I am assuming they are directly discharged into the room from the side of unit.
Per the CRAC schedule on M-601, the units are downflow configuration. Yes, the unit will directly discharge into the room.
Spec sections 02 41 01, 02 41 02, and 02 41 03 have no bearing for this project. These soil reports are only relative to “Emergency Expansion”, “Lab Pharmacy”, and “Radiology” buildings. Is it the government's intention to rely on the GC to provide adequate geotechnical evaluation/reports throughout the campus for determining appropriate compaction requirements for Bldg. 166 and duct banks?
Those reports are on adjacent parcels of land and are to be utilized for this project.
Plans say to remove com line from Bldg. 152. Are there any considerations for com for 152 during construction? No.
Plans dictate removal and relocation of sewer line from Bldg. 152. Will the
VA provide temp facilities for Bldg. 152 during construction? Contractor to maintain service to all facilities during construction.
Entrance to Bldg. 152 (Chapel). The sidewalk is slated for partial removal for construction. Will access be required into Bldg. 152 during construction? If so, please clarify the requirements for pedestrian routing.
Entrance requirement will be worked through between the GC and
COR during construction. Chapel is not utilized every day and alternate routing is available.
151 Recently installed Chapel Sign to be removed and relocate? Plans have been updated to avoind demolition. See sheet CD100.
There is an existing Korean Zen pad located by Bldg. 152. This is not mentioned in the plans or SOW. Please clarify the disposition of this pad for construction. This will be re-routed to avoid.
153 CU100 and ES100 Do not match
Will coordinate with MEP to ensure routing and proposed improvements match.
DT100, Ductbank details appear to represent a formed pad below the ductbanks and the ductbanks to be formed and poured separately. Please clarify the design intent.
Details on civil plans are for representation only. A note has been added to sheet DT100 to refer to Tech/electrical plans for design of duct bank.
Please clarify feeders to new ATS B116 (1) feeder from Building 12 SES and one from Building 115? Drawings show Building 12 room 100 and building 12 basement. This has been clarified in the overall routing plans.
Sheet DT100 (trench 1, 2, and 3 details) states “Contractor to match existing conditions” for restoring surface conditions above the new duct bank. (roadways etc.)
Please clarify “existing conditions” or specify the desired quantities of backfill and asphalt.
Contractor to match existing cross section of trench. Details have been updated and VA patchback details added to sheet DT101.
Sheet DT100 Trench detail calls out 12” separation between conduits
(TYP). Sheet E-502 calls out 3” separation. Please advise on which detail we are to be using.
Refer to MEP for conduit spacing. Civil will make changes to detail to call out technology and electrical plans on sheet DT100.
Sheet E-502, Detail 3, note 2, calls out for rods in roadways but doesn’t list what size. Please specify what size rod is required. Duct bank detialed have been altered to clarify this.
ES101 shows panel 115-1X-2 in building 115. E-601 says it is in building
12. Please clarify where the panel is located and identify correct routing for emergency power. It is in building 115.
Sheet E 502 detail 4 shows 3 #2 with a #4 ground feeding the UPS cabinets. Sheet E601 calls out 3-4/0, 1 4/0 neu and 1#4 ground. Please verify the correct wire size. 3-4/0. 1-4/0 Neutal and #4 ground is correct.
Sheet E 602 equipment conductor schedule calls out 4 #3 and a #8 ground in a 1 ¼ conduit on a 200-amp breaker. Please verify the correct conductor size. 3-4/0. 1-4/0 Neutal and #4 ground is correct.
ES101 note 5 says “existing location of ups’s to be relocated.” Where are they to be located? What is to be done with existing wires as indicated on sheet ES101?
Locate to UPS klocations shown in the new data center andf per the data center sinlge line.
Sheet CU101 verbiage depicts a proposed 2x3 fiber optic route from new fiber manhole (between Bldg.’s 166 and 12) to Bldg. 12. The hash marks on that trench depict a 2x1 conduit configuration. Please clarify. Hatching has been updated.
SOW calls out a medium voltage transformer and three generators. I do not see any details or locations of the transformer and generators. Please advise. Generators and transfomers are not part of the scope.
Sheet TS101 identifies existing IT rooms to receive new fiber optics. Are the vertically aligned rooms in Bldg. 107 connected by existing com chases?
T-401-404 sheets have been added to the sheets to depict this information for each building.
Sheet TS101 identifies fiber routing to various rooms in various Bldg.’s.
Will ICRA measures be required to perform work in those areas?
Assume all work outside of buidlnig 166 is medium risk group 2 per
ICRA on G-003. Assumne all work to be performed out of a HEPA cart.
Will core drilling be required to access Bldg.’s for fiber optic noted on sheet
TS101? If so, please provide environmental reports showing composition of foundation walls to confirm any LBP’s or asbestos containing products.
Yes access has been noted on routing plans for each building.
hazarous material survey included for determinuing impacts.
Will the VA provide exact locations for fiber optic penetrations in all Bldg.
foundations? Direct routing to IT rooms would be desirable…
T-401-404 sheets have been added to the sheets to depict this information for each building.
Conflict between drawings CU101 and TS101 at Bldg. 70 – Cu101 depicts proposed 2x2 duct bank to existing manhole at parking lot near the west side of Bldg. 70. TS101 depicts 2x2 duct bank entering MH-70-1, then proceeds to Bldg. 70 with a continuation from manhole to the west with no destination. Please provide additional information, as this will impact appropriate pricing due to the unknown distance and termination point.
Will coordinate with MEP to ensure routing and proposed improvements match.
T-101 shows nine 4” conduits and four 2” conduits to campus, then refers you to sheet TS101 for continuation. CU101 references proposed 2x3 fiber optic duct bank. 2x3 fiber optic apparently does not have enough conduits to support the thirteen conduits as indicated on sheet T-101. The same condition exists from Bldg. 166 to Bldg. 12. Please update Drawings to depict appropriate information.
Overall routing plans have been updated to ditinguis the…