This document provides details for a federal contract opportunity to construct an adult day health and extended care support building at the St. Cloud VA Medical Center. The solicitation number is 36C77621B0002 and involves general construction work including alterations, walks, grading, drainage, necessary removal of existing structures and construction of certain other items. The work also includes all labor, material, equipment and supervision to perform the required electrical and mechanical construction. The contracting agency is the Department of Veterans Affairs Technology Acquisition Center located in Austin. The project scope involves building a new structure adjacent to Building 116 to house the Adult Day Health Care operation of the Extended Care Service Line.
View the file
Other files
Show 40 more
Latest 50 of 74 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build paradigm
PRODUCTS/MATERIALS
EXECUTION
TESTS AND INSPECTIONS
1. DOMESTIC WATER SYSTEM - STERILIZE THE ENTIRE WATER DISTRIBUTION SYSTEM
THOROUGHLY WITH A SOLUTION CONTAINING NOT LESS THAN 50 PARTS PER MILLION OF
AVAILABLE CHLORINE. USE EITHER LIQUID CHLORINE OR CALCIUM HYPOCHLORITE
CONFORMING TO FEDERAL SPECIFICATIONS. ALLOW THE STERILIZING SOLUTION TO
REMAIN IN THE SYSTEM FOR EIGHT HOURS. DURING WHICH TIME ALL VALVES AND
FAUCETS SHALL BE OPENED AND CLOSED SEVERAL TIMES. AFTER STERILIZATION, THE
SOLUTION SHALL BE FLUSHED FROM THE SYSTEM WITH CLEAN WATER UNTIL THE
RESIDUAL CHLORINE CONTENT IS NOT GREATER THAN 0.2 PARTS PER MILLION UNLESS
DIRECTED OTHERWISE. TEST SYSTEM HYDROSTATICALLY AT 100 PSIG MINIMUM FOR A
PERIOD OF 24 HOURS WITH A PRESSURE LOSS NOT TO EXCEED 1 PSIG.
2. SANITARY DRAINAGE SYSTEM - SHALL BE WATER TESTED BEFORE FINAL CONNECTION TO
THE SANITARY SEWER. ALL OPENINGS SHALL BE PLUGGED EXCEPT THE HIGHEST
OPENING WHICH SHALL PRODUCE A MINIMUM OF A 10 FOOT HEAD. THE SYSTEM SHALL
RETAIN THE WATER LEVEL FOR AT LEAST 15 MINUTES AT WHICH TIME ALL JOINTS SHALL
BE INSPECTED AND ALL OBSERVED LEAKS CORRECTED.
3. FINAL INSPECTION - BEFORE FINAL INSPECTION, CERTIFY IN WRITING THAT ALL SYSTEMS
ARE INSTALLED, ADJUSTED, TESTED AND READY FOR USE.
1. PLUMBING FIXTURES/EQUIPMENT
a. ALL PLUMBING FIXTURES/EQUIPMENT SHALL BE AS INDICATED ON THE FIXTURE
SCHEDULE AND IN SPECIFICATIONS.
1. DRAWINGS:
a. PLUMBING DRAWINGS ARE TO BE CONSIDERED DIAGRAMATIC AND INDICATE GENERAL
ARRANGEMENT OF WORK AND SYSTEMS. IT IS NOT POSSIBLE TO INDICATE EVERY
FITTING, VALVE, OFFSET, TRAP, ACCESS PANEL, ETC. THAT IS REQUIRED FOR A
PROPER WORKING SYSTEM AND MAINTENENCE THEROF. NO ADDITIONAL COST WILL BE
ALLOWED FOR SUCH ITEMS.
b. FOR EXISTING SYSTEMS, ALL LINES AND CONDITIONS SHOWN ON THE DRAWING HAVE
BEEN SHOWN IN GOOD FAITH. HOWEVER, THERE IS NO IMPLIED GUARANTEE AS TO
THEIR SIZE, LOCATION, ELEVATION, COMPLIANCE WITH CURRENT CODES OR
CONDITIONS. THE CONTRACTOR SHALL INVESTIGATE ALL EXISTING CONDITIONS AND
SHALL MODIFY THE PROPOSED WORK AS REQUIRED OR DIRECTED.
c. REFER TO ARCHITECTURAL DRAWINGS FOR EXACT EQUIPMENT LOCATIONS, ETC. AND
OTHER SPACE CONDITIONS. CHECK DRAWINGS OF OTHER TRADES TO COORDINATE
PLUMBING WORK.
2. FEES/INSPECTIONS:
a. PAY ALL FEES AND ARRANGE FOR ALL INSPECTIONS. SUCH INSPECTIONS ARE TO BE
CONDUCTED BY AUTHORITIES HAVING JURISDICTION. ADVISE THE COR/G.C. OF ANY
MODIFICATION TO OR DEVIATION FROM THE CONTRACT DOCUMENTS IN ORDER TO
COMPLY WITH CODES. ENTERING INTO A CONTRACT WILL BE DEEMED AS EVIDENCE OF
COMPLIANCE WITH THE REQUIREMENTS OF AUTHORITIES HAVING JURISDICTION OVER
THE WORK.
3. QUALITY ASSURANCE:
a. ALL PLUMBING WORK SHALL COMPLY WITH ALL APPLICABLE STATE AND LOCAL CODES
AS WELL AS ALL UTILITY COMPANY REGULATIONS. THESE CODES SHALL SUPERCEDE
ANY INFORMATION CONTAINED WITHIN THE DRAWING SET CONTRADICTING THESE
CODES.
b. EACH PIECE OF EQUIPMENT SHALL HAVE MANUFACTURER'S NAME, ADDRESS, SERIAL, AND MODEL NUMBERS ON A PLATE SECURELY ATTACHED TO IT.
c. ALL PIPING ABOVE GRADE SHALL HAVE AN EXPOSED TAG TO IDENTIFY THE PIPE.
d. EACH PIECE OF EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE WITH THE
MANUFACTURERS RECOMMENDATIONS OR AS INDICATED ON PLANS.
e. ALL PLUMBING WORK SHALL BE PERFORMED BY INDIVIDUALS SKILLED IN THIS TRADE
AND COMPLETED IN A PROFESSIONAL MANNER.
f. EACH PIECE OF EQUIPMENT SHALL BE INSTALLED AS FREE FROM NOISE AND VIBRATION
AS POSSIBLE.
4. EQUIPMENT DELIVERY AND STORAGE:
a. DELIVER EQUIPMENT TO THE SITE IN MANUFACTURER'S ORIGINAL PACKAGING.
CLEARLY MARK EACH ITEM WITH THE PROPER IDENTIFICATION NUMBER. STORE IN
SAFE DRY AREA.
1. LAYOUT: PLUMBING
a. PRIOR TO INSTALLATION, LAYOUT ALL PLUMBING WORK IN A MANNER THAT
WILL ALLOW INSTALLATION OF ALL OTHER WORK INDICATED.
b. COORDINATE AND COMMUNICATE INSTALLATION OF PLUMBING WORK WITH
THAT OF OTHER TRADES, SO THAT ALL WORK MAY BE INSTALLED IN SPACE
AVAILABLE.
c. PROVIDE ALL ADA INSULATION PROTECTION AS REQUIRED.
2. EQUIPMENT:
a. INSTALL ALL MATERIAL AND EQUIPMENT IN A NEAT AND WORK- MANLIKE MANNER IN
STRICT ACCORDANCE WITH MANUFACTURER'S RECOMMENDATIONS AND PROVIDE FOR
THE FOLLOWING:
i. CONNECTION OF PIPING AND ACCESSORIES TO EQUIPMENT SHALL PERMIT EASY
REMOVAL WITH MINIMUM OF DISTURBANCE TO OTHER EQUIPMENT AND MATERIALS.
ii. ITEMS REQUIRING INSPECTION, ADJUSTMENT, MAINTENANCE, SERVICING OR
REPLACEMENT SHALL BE EASILY ACCESSIBLE.
b. SLEEVE TO BE INSTALLED (2" MINIMUM AFF) FOR ALL PENETRATIONS.
UPDN
3.2
1.1
A D E F G JB
2.1
3.7
4.4
3.1
C H
5.8
5.9
5.5
P114A
P103
P103
P414
P414
P414
P414
P524
P604
P808
2"CW
1/2"CW
1-1/2"HW
1-1/2"CW
1-1/4"HW
1/2"CW&HW
C
W
1-1/2"CW
1"HW
3/4"CW&HW
1-1/2"CW
1"HW3/4"CW
3/4"HW
P414 P414 P414
P414
P414
P
P103 P103 P103
P103
1-1/2"HW
2"CW
3/4"HWR
3/8"CW&HW
P103
P414
P414
P414
P501
1-1/2"CW
1-1/4"HW
P414 P414
P414
3/4"CWR
P529
P804
SEE PP102 FOR
CONTINUATION
P414
3/8"CW&HW
P801
P103
P414
P801
P808A
1/2"CW&HW
P801
1/2"CW
CT-3
HT-3
CT-2
HT-2
A H
U
AREA OF
FUTURE STAIR #2
CORRIDOR
C112
ADHC
CORRIDOR
C130
TREATMENT
ROOM
MULTIPURPOSE
STORAGE
128B
DATA
ROOM
FUTURE
ELEVATOR
#1
FUTURE
ELEVATOR
#2
STAFF
LOUNGE
FEMALE STAFF
LOCKERS
EXERCISE ROOM
ELEC.
ROOM
PARTICIPANT
QUIET RM
ENGINEERING
UTILITY
EQUIP ALCOVE
C129
PROGRAM SUPPLY
EQUIP. RM
CONNECTING
CORRIDOR
C101
DINING/
ACTIVITY AREA
SCALE
ALCOVE
141A
CART
HOLDING
141B
BATHING RR #1
127A
VESTIBULE
BATHING
ROOM #1
CORRIDOR
C100
COAT
STORAGE
RECEPTION
WORKSTATION
SCOOTER
STORAGE
CORRIDOR
C112
MULTIPURPOSE
ROOM
SOILED
HOLDING
LAUNDRY
CLEAN
LINEN
OXYGEN
STORAGE
ADHC
CORRIDOR
C130
CLEAN
SUPPLY
UNISEX
RESTROOM
ADHC
TOILET #8
ADHC
TOILET #7
ADHC
TOILET #6
ADHC
TOILET #5
ADHC
TOILET #4
ADHC
TOILET #3
ADHC
TOILET #2
ADHC
TOILET #1
119A
ADHC
ENCOUNTER #3
ADHC
ENCOUNTER #2
ADHC
ENCOUNTER #1
NURSE WORK
AREA
OFFICE SUPPLY
STORAGE
MEDICATION
ROOM
KITCHENETTE
MALE STAFF
LOCKERS
STAIR #1
STAFF RR
MECHANICAL
BATHING RR #2
126A
P528
P528
P505
P528
P114A
P414
P414
P114A
C
W
P808A
1/2"CW
1/2"HW
1"CW
3/4"HW
A. ALL WASTE PIPING SHOWN IS LOCATED BELOW FINISHED FLOOR UNLESS
NOTED OTHERWISE. ALL, VENT, GAS, AND WATER PIPING SHOWN ARE
LOCATED ABOVE FINISHED FLOOR/CEILING.
B. CONTRACT DOCUMENTS CONSIST OF BOTH THE PROJECT MANUAL AND
DRAWINGS, AND BOTH ARE INTENDED TO BE COMPLEMENTARY -
ANYTHING APPEARING ON EITHER MUST BE EXECUTED THE SAME AS IF
SHOWN ON BOTH.
C. THE CONTRACTOR SHALL INCLUDE IN BID PROPOSAL ALL COSTS REQUIRED
TO COMPLETELY AND PROPERLY INSTALL ALL WORK REQUIRED FOR THE
PROJECT, AND SHALL EXAMINE THE SCOPE OF WORK OF OTHER TRADES
PRIOR TO SUBMITTING A BID PROPOSAL.
D. AFF = ABOVE FINISHED FLOOR.
E. PROVIDE PIPE MARKERS ON ALL PIPING; SEE SPECIFICATIONS.
F. FIRE CAULK WHERE REQUIRED.
3/8"CW&HW TO FIXTURE(S), PROVIDE MIXING VALVE AT FIXTURE.
1/2"CW&HW TO P-808A BOX, CHANGE TO 3/4" PIPE 12" BEFORE CONNECTION BOX.
1"CW TO FIXTURE.
1"CW AND 3/8"HW, PIPE 1"CW TO W.C. AND 3/8"CW&HW TO LAV. PROVIDE MIXING
VALVE AT LAV.
1"CW AND 1/2"HW DOWN, PIPE 1"CW TO W.C. AND 1/2"CW&HW TO MOP SINK.
WHA-B AT THIS LOCATION.
1/2"CW (NON-POTABLE) DOWN; SEE SHEET PP102 FOR CONTINUATION .
INSTALL AN OSHA CAUTION SIGN LIKE COMPLIANCE SIGNS.COM NON-POTABLE
WATER DO NOT DRINK BILINGUAL SIGN OCB-4980, ALUMINUM 7"x 5"; SEE DETAIL
B2/PP101. PLACE SIGN 3" ABOVE HYDRANT ON WALL.
1/2"CW DOWN.
14"X 14" HINGED STAINLESS STEEL AND LOCKABLE ACCESS PANEL FOR FLUSH
VALVE.
CONNECT TO ICE MAKER FILTER AND ICE MAKER AS REQUIRED.
1"CW AND 1/2"HW DOWN. PIPE 1" CW TO FLUSH VALVE AND 1/2"CW&HW TO
FAUCET.
SENSOR(S); TYPICAL. SEE SHEET PP501.
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build paradigm
1"CW
2"CW UP
F F
F
F
F
F
3.2
1.1
A D E F G JB
2.1
3.7
4.4
3.1
C H
5.8
5.9
5.5
2"CW
BASEMENT
MECHANICAL
B001
CRAWL SPACE
B002
STAIR #1
ST-1
CONNECTOR TUNNEL
CRAWL SPACE
B003
FUTURE
ELEVATOR SHAFT
#2
FUTURE
ELEVATOR SHAFT
#1
DCWP-1 & 2
DHWP-1 & 2
STEAM TO HOT WATER HEAT
EXCHANGER HE-1
1-1/2"HW UP
3/4"HWR UP
3/4"CWR UP
1/2"CW (NON-POTABLE)
1/2"CW (NON-POTABLE)
3/4"CW (NON-POTABLE)
1/2"CW (NON-POTABLE)
3"CW
SEE PP103 FOR
CONTINUATION
HT-1
1-1/2"CW
CP-3 CT-2
HT-4
HF-1
CF-1 CP-2
3"CWBUILDING
METER AND
BACKFLOW
DEVICE; SEE
DETAIL
F8/PP502
1" MECHANICAL
EQUIPMENT
BACKFLOW DEVICE
CP-1
CT-1
CQ-1
3" BUTTERFLY BUILDING SHUTOFF VALVE .
SEE CIVIL DRAWING FOR CONTINUATION.
SEE DETAIL D7/PP503.
1/2"CW (NON POTABLE) UP.
ROUTE PIPING BEST WAY; TYPICAL.
FOR MECHANICAL EQUIPMENT CONNECTION.
3/4" UP TO EXPANSION TANK ET-1, MOUNTED AS HIGH AS POSSIBLE.
SENSOR(S); TYPICAL. SEE SHEET PP501.
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build
SEE PP102 FOR
CONTINUATION
3"CW3"CW
EXISTING 4"CW RISER
EXISTING 4"CW RISER
3"CW
CT-4
3" BUTTERFLY
SHUTOFF VALVE
FOR ADH BUILDING
ROUTE PIPING BEST
WAY; TYPICAL
EXISTING BUILDING DOMESTIC
WATER SUPPLY AND BACKFLOW
PREVENTER; SEE DETAIL C6/PP103
SENSOR; TYPICAL.
SEE SHEET PP501
RAISE NEW 3"CW UP AS HIGH AS POSSIBLE.
C
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build
CT-3
CF-1
CT-1
CT-2
INCOMING DOMESTIC
WATER SERVICE
HT-2 HF-1HT-4
STEAM HOT WATER
GENERATOR
HT-3
DOMESTIC HOT WATER
RETURN PUMP
DOMESTIC COLD
WATER RETURN PUMP
HOSE END BALL
VALVE WITH GASKET
CAP AND CHAIN
HT-1
COLD WATER
CHECK VALVE
MIXING VALVE
HOSE-END BALL
VALVE; TYPICAL
FLOW METER; TYPICAL
DOMESTIC COLD
WATER MAIN (RISER)
DOMESTIC COLD
WATER SUPPLY
CP-2 CF-1
DOMESTIC COLD WATER
RETURN PUMP (NOT A
BOOSTER PUMP)
CHECK VALVE; TYPICAL
BALL VALVE; TYPICAL
CT-2CP-3
TEMPERATURE
METER; TYPICAL
PRESSURE
METER; TYPICAL
FLOW ARROW;
TYPICAL
DOMESTIC COLD
WATER RETURN
INCOMING
SERVICE
C P
C T
C Q
DIELECTRIC
UNION; TYPICAL
STRAINER WITH HOSE
END BLOW DOWN
WATER METER
WITH METERING
PRESSURE
REDUCING VALVE
Purpose
Veteran's Health Administration (VHA) Policy establishes guidelines for the prevention and control of healthcare-associated Legionella disease in
VHA buildings.
The efficacy of biocides on suppressing or killing waterborne pathogens is dependent on multiple factors such as water quality, organic and inorganic contaminants, pH levels, disinfectant concentrations, and contact time. Water entering the building shall be continuously monitored for the following by means of gauges, sensors, and a grab sample port:
Temperature, Oxidant level (water disinfectant), pH, and Pressure
Water systems within the building shall be monitored as follows in the table below. Temperature and oxidant levels are the two primary engineering controls to limit bacterial growth. Oxidant levels shall be measured continuously as water enters the building and through grab samples taken from building plumbing fixtures. Temperature shall be measured throughout the domestic water system (hot and cold). In addition to being a primary control measure, temperature can be a secondary indicator of flow since temperature of stagnant water will lower for hot water and rise for cold water.
Background
Legionella is a bacterium that causes respiratory diseases collectively referred to as Legionellosis that includes Legionella pneumonia. Legionella pneumonia is also known as Legionnaires Disease (LD). Legionella bacteria are found naturally in water and have been associated with disease from building water distribution systems. LD occurs after inhalation or aspiration of contaminated water. Legionella bacteria are not transmitted from person to person. The elderly and persons with immune compromised systems are most at risk. Legionella bacteria growth increases in tepid water in a range from 20 deg C [68 deg F] to 50 deg C [123 deg F].
Given the various factors and complexities associated with LD, 100% prevention of LD is likely not possible. However, prevention and control practices can be implemented to reduce the risk of exposing people to Legionella in building water distribution systems. The following are engineering controls that will suppress Legionella growth. More than one control may be necessary for successful inhibition of Legionella growth.
(a) Temperature
· Maintenance of appropriate water temperatures is required. Water above 51.1 deg. C [124 deg. F] inhibits growth of Legionella in hot water systems. Precautions for the prevention of scalding shall be included in the hot water distribution system.
· Cold water temperatures below 19.4 deg. C [67 deg. F] inhibit the growth of Legionella.
(a) Flow
· Recirculation of water distribution systems is a means of limiting Legionella growth due to low flow or non-use periods. Recirculation aids in maintaining required water temperatures. Hot and cold water distribution systems shall be continuously circulated and piping insulated.
(a) Oxidant (Disinfectant)
· Maintenance of disinfectant at a sufficient level to control Legionella growth may be required. The minimum level required to suppress bacterial growth will vary from building to building and by the type of oxidant (disinfectant) used. Monitoring of levels is required.
Piping Installation Guidelines for Legionella Mitigation:
· The need to chill or cool the domestic cold water supply shall be evaluated at the schematic phase. Legionella can propagate in temperatures exceeding 20 deg C [67 deg F]. The domestic cold water distribution system shall have a recirculation system. For cold water systems, although circulation back to the source location for the building is ideal, for renovation efforts, recirculation within the department (or floor) area of renovation would be acceptable.
· Ice maker water supply lines shall be copper and insulated. Avoid routing water lines near source of heat such as the compressor system of the ice maker.
· Cold and hot water piping systems shall be insulated in accordance with the latest version of ASHRAE 90.1.
· To enable thermal eradication and emergency shock chlorination, consider providing taps for connection of temporary booster heaters. Provide adequate electrical connections.
· PVC pipe shall not be used for sanitary and vent lines because of the high temperature water during thermal eradication. Cast iron shall be used.
· Aerators are prohibited in order to reduce exposure to Legionella contaminated water.
· Piping materials shall be in accordance with VA Master Spec 22 11 00 Facility Water Distribution.
· Piping and components must be cleaned and protected from accumulation of debris and contamination prior to and during installation.
· Ensure that newly installed piping and components are flushed of debris and disinfected prior to being placed into service.
Supplemental Water Disinfection Methods
In addition to maintaining the appropriate water temperatures, minimum concentrations of various biocides (e.g. oxidizing agents such as chlorine) can inhibit the growth of Legionella in building potable water distribution systems. When considering the use of supplemental water disinfection methods for the prevention of Legionella, plumbing designers and the VA project manager (in collaboration with other facility stakeholders such as infectious diseases and infection prevention and control) shall review the merits of the many types of supplemental systems available prior to making a final selection. VHA recognizes United States (U.S.) Environmental Protection Agency (EPA) approved oxidants
(chlorine, monochloramine, and chlorine dioxide) as acceptable disinfectants for use in potable water distribution systems.
Selection of the necessary equipment, piping and controls and adequate space for the maintenance and operations, are a must. The EPA regulates contaminant levels and disinfectant treatment for use under the Safe Drinking Water Act. Usually, the EPA delegates primacy to States for the regulation and enforcement of the Act within individual State boundaries. Systems must be specifically approved or recognized for the intended use by the State regulatory water authority. Federal and state safety regulations and permitting shall be followed. Designers shall coordinate permitting requirements with the local authority having jurisdiction. The facility must consult with the State (or its delegated local water authority) for regulating drinking water for guidance on system selection, achieving an appropriate biocide residual level at building outlets for
Legionella growth suppression, system design, system operation, and ensuring compliance with regulations regarding water treatment system(s) and safety. Once a type of system is selected, either the State (or its delegated local water authority) or the manufacturer of the system must provide the minimum and maximum outlet biocide levels in writing for both hot and cold water.
Design parameters to evaluate for supplemental water disinfection include:
· Potential impact of supplemental disinfectant on special use water systems.
· Need for emergency power.
· System may need to be duplex for redundancy and maintenance.
· Spare parts may need to be purchased and stored locally.
· Federal and state safety regulations and permitting must be observed.
· Interaction of supplemental disinfection if shock chlorination is used as an emergency remediation method.
· Ensure enough maintenance access is provided around equipment.
· Provide sample points throughout the system to monitor effectiveness. Some critical points should be provided with automated data collection and alarm.
· Operational and maintenance requirements must be maintained to ensure system effectiveness.
· System must be equipped with automated features to ease of use and proper maintenance and operation.
· Requirements for off gassing associated with the specific chemicals (for example Sodium hypochlorite).
· Chemical spill containment systems must be provided.
· Chemical storage requirements.
Emergency Water Disinfection Methods
Emergency disinfection is the process of implementing immediate, temporary actions to reduce the amount of Legionella in a water distribution system.
Thermal Eradication
Requires potable water in the system to be raised to 71 - 77 deg C [160 - 170 deg F] and flushed through every fixture for 30 minutes. Some design considerations are as follows:
· Central water heating equipment must be capable of raising water temperature to 82 deg C [180 deg F].
· Master thermostatic mixing valve located in the hot water distribution system may have to be bypassed to allow hot water to circulate in the distribution system.
· Select point-of-use thermostatic mixing valves that are amenable to thermal eradication procedures. See VA Master Specification 22 05 23 for required mixing valves.
· Provide taps for a connection of temporary booster heater to facilitate thermal eradication.
· Provide adequate electrical connections for temporary booster heaters. Coordinate with electrical engineer.
· All equipment and appurtenances in the system will need to be reviewed for operation at elevated temperature (e.g. ensure water supply stops can withstand required temperatures).
· Means of tempering discharge will need to be considered to accommodate code requirements on discharge to sanitary sewer (max temp of
60 deg C [140 deg F]). Ensure discharge is compliant with the local requirements.
Shock Chlorination
Installation of a chlorinator is required. Shock chlorination involves the addition of chlorine to the water system in one of the forms listed above.
Some design considerations are as follows:
· Provide taps for connection of temporary equipment.
· All equipment and appurtenances in the system will need to be reviewed for operation at elevated oxidant levels.
Special Use Water Systems (e.g., hemodialysis, laboratory, pharmacy compounding) It is important to consider the implications of Legionella mitigation strategies on special use water systems within the building. Special use water systems include: Hemodialysis, Laboratory Service, Pharmacy Compounding, and Supply Process Service (SPS). Water treatment strategies and chemical disinfectants may result in the introduction of products into, or the formation of disinfection byproducts in, the building water supply at concentrations that may be toxic to patients on hemodialysis. Accordingly, the impact of mitigation strategies must account for potential toxicity, methods for removal of the chemical agent and byproducts from the special use water system, and availability of assay methods to measure the chemical agent and byproducts for assuring patient safety. VA authorities responsible for the oversight of special use water systems are to be consulted during design development of the project and prior to any final decisions regarding water treatment strategies for Legionella.
INSPECTIONS AND WITNESS OF TESTS
The inspection plan needs the approval of the project technical COR. Frequency and requirements for inspections and testing must be added to the construction documents. Regarding inspections and test witnessing, the plumbing drawings and specifications shall coordinate with the VA
Manual on Systems Commissioning and the project's commissioning specifications.
Ensure that newly installed piping and distribution system components are flushed of debris and disinfected prior to being placed into service.
Piping and components must be cleaned and protected from accumulation of debris and contamination prior to and during installation.
Documentation of flushing and disinfection must be maintained. Disinfection for new installations or maintenance of piping, equipment, and components shall be conducted in accordance with the requirements of the IPC, American Water Works Association (AWWA C651-05), and VA
Master Construction Specifications.
WATER DISTRIBUTION SYSTEMS
Water Storage Tanks: Provide adequate space for maintenance access to clean the interior of all water storage tanks. Tanks shall be provided with a man way access to allow for inspection, maintenance and cleaning. Tanks shall be constructed to minimize stagnation and thermal gradients. Mechanical cooling may be needed to maintain water temperature.
Measuring and Indicating Devices
Analog gauge and electronic sensors/devices shall be used in tandem as much as is practicable. The gauge device will provide a local or immediate indicator of current conditions for troubleshooting and verification purposes. The electronic sensor/device will be used for continuous monitoring of water conditions and shall be connected to the building automation system. All electrical devices shall be on emergency power. All measuring devices shall be calibrated in accordance with the manufacturer's recommendations.
Domestic Cold Water Sequence of Operation (See schematic detail CA and service detail B4)
Water will flow as required for fixture use. Water temperature will be measured at a minimum of three locations:
CT-1 at the meter; CT-2 on the return pipe; CT-3 near the midpoint of piping, and CT-4 at main tap in the rehab building basement.
Once all fixture use has stopped as measured by flow meter CF-1, the flow meter will send a signal to the Domestic Cold Water Pump to start. Pump will circulate domestic cold water until flow meter CF-1 senses fixture usage and pump will stop.
Water pressure will be monitored at 3 locations, before and after meter/RPZ and at suction size of return pump.
Water quality shall be monitored before meter, CQ-1.
Domestic Hot Water Sequence of Operation
(SEE SCHEMATIC D4)
Water will flow as required for fixture use. Water temperature will be measured at a minimum of four locations:
HT-1 near the water heating source; HT-2 after mixing valve; and HT-3 near the middle of the domestic hot water piping; and HT-4 at the farthest point from the heating source. Domestic hot water piping will be looped to feed all fixtures before returning back to the water heating source.
Domestic Hot Water Return Pump shall circulate hot water continuously (no shut down or aqua senser). Water flow shall be monitored by HF-1. Once flow stops, HF-1 shall send a signal to the Building Control System indicating a flow failure.
BACKFLOW PREVENTOR (RPZ)
THERMOMETER;
TYPICAL
SEE DETAIL F8/PP502
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
o c q
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090 220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
UPDN
3.2
1.1
A D E F G JB
2.1
3.7
4.4
3.1
C H
5.8
5.9
5.5
P102
P414
P414
P103
P414
P604
P808
RD
OD
RD
OD
4"ST
DOWN
4"ST
DOWN
P524
CO @
GRADE
P103 P103 P103 P103 P103
P103
P414
P414
P414
P414
P414
P414
P103
P414
FD-2
FD-2
P414
P414
CO
STM
P414
P502
P529
2"V DOWN
FD-1
FD-1
FD-1
FD-1
FD-1
FD-1
FD-1
FD-1
CO @
GRADE
2"V
2"V
2"V 3"V
2"V
2"V3"V
2"V
2"V
2"V
2"V
2"V
2"V
P414
2"V DOWN
FD-1
P103
P414
A H
U
AREA OF
FUTURE STAIR #2
CORRIDOR
C112
ADHC
CORRIDOR
C130
TREATMENT
ROOM
MULTIPURPOSE
STORAGE
128B
DATA
ROOM
FUTURE
ELEVATOR
#1
FUTURE
ELEVATOR
#2
STAFF
LOUNGE
FEMALE STAFF
LOCKERS
EXERCISE ROOM
ELEC.
ROOM
PARTICIPANT
QUIET RM
ENGINEERING
UTILITY
EQUIP ALCOVE
C129
PROGRAM SUPPLY
EQUIP. RM
CONNECTING
CORRIDOR
C101
DINING/
ACTIVITY AREA
SCALE
ALCOVE
141A
CART
HOLDING
141B
BATHING RR #1
127A
VESTIBULE
BATHING
ROOM #2
BATHING
ROOM #1
CORRIDOR
C100
COAT
STORAGE
RECEPTION
WORKSTATION
SCOOTER
STORAGE
CORRIDOR
C112
MULTIPURPOSE
ROOM
SOILED
HOLDING
LAUNDRY
CLEAN
LINEN
OXYGEN
STORAGE
ADHC
CORRIDOR
C130
CLEAN
SUPPLY
UNISEX
RESTROOM
ADHC
TOILET #8
ADHC
TOILET #7
ADHC
TOILET #6
ADHC
TOILET #5
ADHC
TOILET #4
ADHC
TOILET #3
ADHC
TOILET #2
ADHC
TOILET #1
119A
ADHC
ENCOUNTER #3
ADHC
ENCOUNTER #2
ADHC
ENCOUNTER #1
NURSE WORK
AREA
OFFICE SUPPLY
STORAGE
MEDICATION
ROOM
KITCHENETTE
MALE STAFF
LOCKERS
STAIR #1
STAFF RR
MECHANICAL
BATHING RR #2
126A
P414
2"V
P414
2"V
FD-1
FD-1
FD-1
RD
OD
STM
STM
RD
OD
CO
P808A
P114A
P414
P414
P114A
P808A
P528
P505
P528
STM
S
T
M
S
T
M
P528
2"V
4"ST
FCO
FCO
2"V
TD-1
LT-1
4"ST
4"ST
4"ST
4"ST
4"ST
4"ST
FD-1
A.
B.
C.
D.
E.
F.
G.
H.
ALL WASTE PIPING SHOWN IS SERVING THE FLOOR ABOVE UNLESS NOTED
OTHERWISE. ALL, VENT, GAS, AND WATER PIPING SHOWN ARE LOCATED
ABOVE FINISHED FLOOR/CEILING.
CONTRACT DOCUMENTS CONSIST OF BOTH THE PROJECT MANUAL AND
DRAWINGS, AND BOTH ARE INTENDED TO BE COMPLEMENTARY - ANYTHING
APPEARING ON EITHER MUST BE EXECUTED THE SAME AS IF SHOWN ON
BOTH.
THE CONTRACTOR SHALL INCLUDE IN BID PROPOSAL ALL COSTS REQUIRED
TO COMPLETELY AND PROPERLY INSTALL ALL WORK REQUIRED FOR THE
PROJECT, AND SHALL EXAMINE THE SCOPE OF WORK OF OTHER TRADES
PRIOR TO SUBMITTING A BID PROPOSAL.
AFF = ABOVE FINISHED FLOOR. EX = EXISTING.
INVERT IS SHOWN IN ELEVATION (FEET).
PROVIDE PIPE MARKERS ON ALL PIPING; SEE SPECIFICATIONS.
PIPE COOLING CONDENSATE WITH P-TRAP; SEE DETAIL.
ALL SANITARY AND STORM PIPING TO BE CAST IRON UNLESS NOTED
OTHERWISE.
PLAN NOTES:
2"W DOWN AND 2"V UP.
4"W DOWN AND 2"V UP.
SEE ROOF OVERFLOW NOZZLE DETAIL ON PP502. PROVIDE AND INSTALL
SPLASH BLOCK UNDER SPOUT.
4"ST UP TO ROOF DRAIN/OVERFLOW DRAIN. SEE ROOF PLAN PS103.
2"V UP TO 4"VTR.
3"V UP TO 4"VTR.
14"x 14" HINGED STAINLESS STEEL AND LOCKABLE ACCESS PANEL FOR FLUSH
VALVE.
2"V DOWN.
3"W DOWN.
SEE DETAIL B6/PP502.
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build
F F
F
F
F
F
3.2
1.1
A D E F G JB
2.1
3.7
4.4
3.1
C H
5.8
5.9
5.5
4"CO
8"ST
6"ST
6"ST 6"ST
4" CO @
GRADE
2"W 2"W 2"W
2"W
2"W
4"W
4"W
4"W
4"W
4"W
4"CO
4"CO
4"W 4"W
4"W
4"W
FD-2
FD-2
4"W
4"W 4"W
3"W
BASEMENT
MECHANICAL
B001
CRAWL SPACE
B002
STAIR #1
ST-1
CONNECTOR TUNNEL
CRAWL SPACE
B003
FUTURE
ELEVATOR SHAFT
#2 FUTURE
ELEVATOR SHAFT
#1
COCO
CO
CO
CO
DROP DOWN TO A
MINIMUM 24" BELOW
EXTERIOR GRADE
3"W
3"W
2"V UP
2"V UP
KEEP PIPING AS HIGH AS
POSSIBLE IN CRAWL SPACE
4"W
CO @
GRADE
8"ST
4"W
2"W
FD-2 2"W
3"W
FD-2
UP TO FD
UP TO FD
2"V UP
2"V UP
3"W
8"ST
CO
CO
CO
2"W
CO
2"W
CO
2"W
CO
2"W
4"W
FINISHED FLOOR/GRADE
IS 93'-0" (1038.71)
2"W UP2"W UP
2"W UP
2"W UP
3"W
FINISHED
FLOOR SLAB IS
88-0" (1033.71)
INV. 96.85'(1042.01)
FCO
2"W
CO
2"W
2"W
4"W
CO
3"W
2"W
2"W
2"W
3"W
CO
2"W
CO
CO 3"W
3"W
2"V UP
2"V UP
DROP DOWN TO
97.0'(1042.17)
LT-1
EFFLUENT PUMP
SYSTEM EPS-1
A.
B.
C.
D.
E.
F.
G.
H.
ALL WASTE PIPING SHOWN IS SERVING THE FLOOR ABOVE UNLESS NOTED
OTHERWISE. ALL, VENT, GAS, AND WATER PIPING SHOWN ARE LOCATED
ABOVE FINISHED FLOOR/CEILING.
CONTRACT DOCUMENTS CONSIST OF BOTH THE PROJECT MANUAL AND
DRAWINGS, AND BOTH ARE INTENDED TO BE COMPLEMENTARY - ANYTHING
APPEARING ON EITHER MUST BE EXECUTED THE SAME AS IF SHOWN ON
BOTH.
THE CONTRACTOR SHALL INCLUDE IN BID PROPOSAL ALL COSTS REQUIRED
TO COMPLETELY AND PROPERLY INSTALL ALL WORK REQUIRED FOR THE
PROJECT, AND SHALL EXAMINE THE SCOPE OF WORK OF OTHER TRADES
PRIOR TO SUBMITTING A BID PROPOSAL.
AFF = ABOVE FINISHED FLOOR. EX = EXISTING.
INVERT IS SHOWN IN ELEVATION (FEET).
PROVIDE PIPE MARKERS ON ALL PIPING; SEE SPECIFICATIONS.
PIPE COOLING CONDENSATE WITH P-TRAP; SEE DETAIL.
ALL SANITARY AND STORM PIPING TO BE CAST IRON UNLESS NOTED
OTHERWISE.
PLAN NOTES:
2"W UP.
2"W UP TO FLOOR DRAIN TRAP.
4"W UP AND 2"V UP.
SEE CIVIL DRAWINGS FOR CONTINUATION.
4"W UP TO FCO.
SANITARY PIPE/STORM PIPE CAN BE PVC UNDER GROUND AT THIS LOCATION
AND/OR EXTERIOR OF BUILDING.
PVC CAN START AT THIS POINT DOWNSTREAM.
3"W UP.
2"V UP.
1. EFFLUENT PUMP SYSTEM EPS-1
BASIS OF DESIGN:
(2) LIBERTY PUMPS LE51M, 120V, 12 HP, 10'-0" POWER CORD.
(1) LIBERTY PUMPS AE21L-4 NEMAI DUPLEX ALTERNATING CONTROL PANEL
INCLUDING FOUR FLOATS, AUX. CONTACTS, AND INTEGRAL AUDIO/VISUAL
HIGH LEVEL ALARM
(1) LIBERTY PUMPS K001210 BASIN, 36"X48" FIBERGLASS W/ ANTI-FLOAT, INLET
HUM, 4" PIPE SEAL, GR20 LUGS.
(1) LIBERTY PUMPS K001639 36" DUPLEX STEEL COVER WITH ACCESS
INCLUDING TWO 2" DISCHARGE FLANGES, 2" VENT FLANGE AND CORD
GROMMETS.
(2) LIBERTY PUMPS BVC200, 2 INCH SOCKET WELD BALL AND CHECK
COMBINATION VALVE.
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090 220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build
3.2
1.1
A D E F G JB
2.1
3.7
4.4
3.1
C H
5.8
5.9
5.5
4" RD-1
4" OD-1
4" RD-1
4" OD-1
4" RD-1
4" OD-1
4" RD-1
4" OD-1
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090
220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
Architecture Engineering Design-Build
P528
P505
P528
Email: dae@design-aire.comwww.daengineering.com voice (317) 464-9090 220 North College Avenue Indianapolis, Indiana 46202 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC.
| P-001 |
| PP101 |
| PP102 |
| PP103 |
| PP501 |
| PP502 |
| PP503-add2 |
| Sheets and Views |
| PP503 |
| PP601 |
| PS101 |
| PS102-add2 |
| PS103 |
| PS501-add2 |
File details come from the government source that posted it. Updated .