PN 636-25-301 Addendum 01 - 1 page.pdf
PDF 49 KB Posted
- Solicitation number
- 36C326326B0031
About this file
This is Addendum No. 01 to federal contract 36C26326B0031 A0001 for project PN: 636-25-301, Correct HVAC Deficiencies. The addendum modifies mechanical demolition specifications for Building 17 at the mezzanine level by revising control valve requirements on two related drawings.
The addendum revises Sheet Note 19 on Drawing 17-MD102 (Building 17-Mezzanine Level-Mechanical Demolition) and Sheet Note 14 on Drawing 17-MD102-A (Building 17-Mezzanine Level-Mechanical Demolition-Deduct Alternate A) to clarify that existing chilled water control valves shall remain in place and be reused for new work, while existing glycol heating hot water control valves shall be removed and replaced with new valves. These identical revisions apply to both the base scope and the deduct alternate configuration.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 01
36C26326B0031 A0001 PN: 636-25-301 Correct HVAC Deficiencies
Mechanical Addendum items:
1. Drawing Number: 17-MD102 – Building 17-Mezzanine Level -Mechanical Demolition
Revise Sheet Note 19 to read:
EXISTING CHILLED WATER CONTROL VALVES TO REMAIN IN PLACE AND BE REUSED FOR
NEW WORK. EXISTING GLYCOL HEATING HOT WATER CONTROL VALVES TO BE REMOVED
AND REPLACED WITH NEW.
2. Drawing Number: 17-MD102-A – Building 17-Mezzanine Level -Mechanical Demolition- Deduct Alternate A
Revise Sheet Note 14 to read:
EXISTING CHILLED WATER CONTROL VALVES TO REMAIN IN PLACE AND BE REUSED FOR
NEW WORK. EXISTING GLYCOL HEATING HOT WATER CONTROL VALVES TO BE REMOVED
AND REPLACED WITH NEW.