This document is a Responses to Late Questions/RFI/Clarifications for a federal solicitation regarding HVAC system replacement. Solicitation Number 36C26326B0021 covers Project Number 568A4-23-207, Replace 1 North HVAC System (HS), located in Hot Springs.
The document addresses four substantive clarifications provided by the government in response to contractor inquiries. Key clarifications include: (1) contractors may work on multiple phases provided work complies with normal working hours and after-hours/weekend requirements; (2) contractors are not responsible for providing UL fire-resistant joint systems at unforeseen or existing penetrations outside the intended scope of work; (3) the government intends for contractors to replace existing suspended acoustical ceiling tile and grid with new materials; and (4) Specification Section 13 05 41 Seismic Restraint Requirements are applicable and must be complied with despite Hot Springs being categorized as seismic design class B. These clarifications establish binding guidance for contractor performance under the solicitation.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number: 36C26326B0021 Project Number: 568A4-23-207, Replace 1 North HVAC System (HS)
Responses to Late Questions/RFI/Clarifications
Question No.
Reference (Sect/Para/Page)
QUESTION GOVERNMENT RESPONSE
1 Phase Plan sheets
12-AE
Can the contractor work on multiple phases?
Yes as long as they are consistent with requirements related to working during normal working hours and working after hours and on weekends.
Sheet 12-AE, plan note #8
It is understood that the contractor is to provide a UL fire-resistant joint system at penetrations associated with the scope of work. However, is it the contractor’s responsibility to provide the UL fire-resistant joint system at any unforeseen or existing penetrations that are outside of the intended scope?
No.
3 The reflected ceiling plan
Is it the intent to replace the existing suspended acoustical ceiling tile and grid with new?
Yes.
Spec Section 13 05 41 Seismic
Restraint Requirements
Is the section relevant, given that the Hot Springs area is categorized as a seismic design class B?
Yes, comply with requirements of this specification.