36C26325B0007_1.docx

DOCX document 109 KB Posted

Attached to
Y1DA--656-19-307 Remodel of Building 51-1, Eastside at the Saint Cloud VA, Saint Cloud, MN
Solicitation number
36C26325B0007
Issued by

About this file

This is a Department of Veterans Affairs (VA) Solicitation for a construction contract to remodel Building 51-1 Eastside at the St. Cloud VA Health Care System in Minnesota. The solicitation (No. 36C26325B0007) is set-aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 236220 with a $45 million small business size standard. The project involves fully demolishing and remodeling the patient care area, with a construction cost range between $2 million and $5 million.

Key contract details include a 456-day performance period, with work to be completed Monday through Friday from 8am-4:30pm. The project will update lighting, wall surfaces, and general environment decor within Building 51 and adjacent spaces. Bidders must be certified SDVOSBs listed in the SBA certification database, with bids due by 9:00 AM (CT) on May 22, 2025. A mandatory pre-bid site visit is scheduled for April 24, 2025, at 9:00am (CT). The contract will be a firm-fixed-price type, with performance and payment bonds required, and bidders must comply with specific subcontracting limitations and reporting requirements.

View the file

Other files

File Type Posted
36C26325B0007 0002.docx DOCX document
36C26325B0007 0001.docx DOCX document
656_19_307 B51_1 E CD 100.pdf PDF
SOW Revised.pdf PDF
Bed Lift Detail 4.png PNG image
Copy of Copy of Price Breakdown blank.xlsx XLSX spreadsheet
656_19_307 Remodel B51_1 E Bed Lifts Manual.pdf PDF
Bed Lift Detail 2.png PNG image
Bed Lift Detail 3.png PNG image
Class Deviation from FAR CAAC 2025-01 Suppl 1 EOs 14173.14168.pdf PDF
656-19-307 B51-1 Staging - Parking Area.pdf PDF
P07 WRD Stearns.pdf PDF
656_19_307 Specfications 1_Rev EDITED.pdf PDF
656_19_307 Specifications 2_Rev EDITED.pdf PDF
Bed Lift Detail 1.png PNG image
656_19_307 Specifications 3_Rev EDITED.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A.1 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

The Contractor shall not make reference in its commercial advertising to Department of Veterans Affairs contracts in a manner that states or implies the Department of Veterans Affairs approves or endorses the Contractor’s products or services or considers the Contractor’s products or services superior to other products or services.

(End of Clause)

A.2 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)

(a) The Contractor shall conform to the standards established by: as to .

(b) The Contractor shall submit proof of conformance to the standard. This proof may be a label or seal affixed to the equipment or supplies, warranting that the item(s) have been tested in accordance with the standards and meet the contract requirement. Proof may also be furnished by the organization listed above certifying that the item(s) furnished have been tested in accordance with and conform to the specified standards.

(c) Offerors may obtain the standards cited in this provision by submitting a request, including the solicitation number, title and number of the publication to:

(d) The offeror shall contact the Contracting Officer if response is not received within two weeks of the request.

(End of Clause)

A.3 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)

The FAR clauses 52.236-2, Differing Site Conditions; 52.243-4, Changes; and 52.243-5, Changes and Changed Conditions, are supplemented as follows:

(a) Submission of request for equitable adjustment proposals. When directed by the Contracting Officer or requested by the Contractor, the Contractor shall, in accordance with FAR 15.403-5, submit proposals for changes in the work exceeding $500,000 in writing to the Contracting Officer or Administrative Contracting Officer (ACO), and to the resident engineer.

(1) The Contractor must provide an itemized breakdown for changes exceeding the micro-purchase threshold (see FAR 2.101).

(2) The itemized breakdown shall include materials, quantities, unit prices, labor costs (separated into trades), construction equipment, etc. Labor costs shall be identified with specific material placed or operation performed.

(3) Proposals shall be submitted to the Contracting Officer or ACO and the resident engineer as expeditiously as possible, but not later than calendar days, after receipt of a written change order by the Contracting Officer.

(4) Proposals shall be signed by each subcontractor participating in the change.

(5) The Contracting Officer will consider issuing a settlement by determination to the contract if the Contractor's proposal required by paragraph (a)(3) of this clause is not received within the time period specified in paragraph (a)(3), or if agreement has not been reached.

(b) Paragraphs (a)(1) through (5) of this clause and the following paragraphs (b)(1) and (2) apply to proposals for changes in the work $500,000 or less:

(1) As a basis for negotiation, allowances not to exceed 10 percent each for overhead and profit for the party performing the work will be based on the value of labor, material, and equipment required to accomplish the change. As the value of the change increases, a declining scale will be used in negotiating the percentage of overhead and profit. This declining scale will also be used to negotiate the prime Contractor's or upper-tier subcontractor's fee when work is performed by lower-tier subcontractors (to a maximum of three tiers) and will be based on the net increased cost to the prime or upper-tier subcontractor, as applicable. Profit (fee) shall be computed by multiplying the profit percentage by the sum of the direct costs and computed overhead costs. Allowable percentages on changes will not exceed the following:

(i) 10 percent overhead and/or 10 percent profit (fee) on the first $20,000.

(ii) 7.5 percent overhead and/or 7.5 percent profit (fee) on the next $30,000.

(iii) 5 percent overhead and/or 5 percent profit (fee) on a balance over $50,000.

(2) The Contracting Officer will consider issuing a settlement by determination to the contract if the Contractor's proposal required by paragraph (3) is not received within 30 calendar days, or if agreement has not been reached.

(c)(1) Overhead and Contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the Contractor's overhead and/or fee percentage.

(2) Where the Contractor's or subcontractor's portion of a change involves credit items, such items must be deducted prior to adding overhead and profit for the party performing the work. The Contractor's fee is limited to the net increase to Contractor or subcontractors' portions of cost computed in accordance with this clause.

(3) Where a change involves credit items only, a proper measure of the amount of downward adjustment in the contract price is the reasonable cost to the Contractor if it had performed the deleted work. A reasonable allowance for overhead and profit are properly includable as part of the downward adjustment for a deductive change. The amount of such allowance is subject to negotiation.

(End of Clause)

FAR Number
Title
Date
52.223-21
FOAMS
MAY 2024
52.223-23
SUSTAINABLE PRODUCTS AND SERVICES
MAY 2024
52.219-8
UTILIZATION OF SMALL BUSINESS CONCERNS
JAN 2025
52.219-9
SMALL BUSINESS SUBCONTRACTING PLAN ALTERNATE I (NOV 2016)
JAN 2025

A.4 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)

(a) Definitions. As used in this clause—

(1) Contract financing payment has the meaning given in FAR 32.001;

(2) Designated agency office means the office designated by the purchase order, agreement, or contract to first receive and review invoices. This office can be contractually designated as the receiving entity. This office may be different from the office issuing the payment;

(3) Electronic form means an automated system transmitting information electronically according to the accepted electronic data transmission methods and formats identified in paragraph (c) of this clause. Facsimile, email, and scanned documents are not acceptable electronic forms for submission of payment requests;

(4) Invoice payment has the meaning given in FAR 32.001; and

(5) Payment request means any request for contract financing payment or invoice payment submitted by the contractor under this contract.

(b) Electronic payment requests. Except as provided in paragraph (e) of this clause, the contractor shall submit payment requests in electronic form. Purchases paid with a Government-wide commercial purchase card are considered to be an electronic transaction for purposes of this rule, and therefore no additional electronic invoice submission is required.

(c) Data transmission. A contractor must ensure that the data transmission method and format are through one of the following:

(1) VA’s Electronic Invoice Presentment and Payment System at the current website address provided in the contract.

(2) Any system that conforms to the X12 electronic data interchange (EDI) formats established by the Accredited Standards Center (ASC) and chartered by the American National Standards Institute (ANSI).

(d) Invoice requirements. Invoices shall comply with FAR 32.905.

(e) Exceptions. If, based on one of the circumstances in this paragraph (e), the Contracting Officer directs that payment requests be made by mail, the Contractor shall submit payment requests by mail through the United States Postal Service to the designated agency office. Submission of payment requests by mail may be required for—

(1) Awards made to foreign vendors for work performed outside the United States;

(2) Classified contracts or purchases when electronic submission and processing of payment requests could compromise the safeguarding of classified or privacy information;

(3) Contracts awarded by contracting officers in the conduct of emergency operations, such as responses to national emergencies;

(4) Solicitations or contracts in which the designated agency office is a VA entity other than the VA Financial Services Center in Austin, Texas; or

(5) Solicitations or contracts in which the VA designated agency office does not have electronic invoicing capability as described above.

(End of Clause)

A.5 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

(a) The Contractor shall furnish to the resident engineer, for each workday, a consolidated report for the preceding workday. Reporting shall begin from date of mobilization until the date of final acceptance except for authorized holidays. VA Form 10101, Contractor Production Report, or a Contractor generated form containing the same type of information shall be signed, dated and submitted by the Contractor superintendent.

(b) Each report shall include and specifically identify at least one safety topic germane to the jobsite that day.

(End of Clause)

A.6 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)

(a) Contract administration functions set forth in FAR 42.302 are hereby delegated to:

Traci Johannes Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

Contract Officer 4801 Veterans Drive St. Cloud, MN 56303

(b) The following functions will be retained by the Contracting Officer or Administrative Contracting Officer (ACO) and are not redelegable to Resident Engineers:

(1) Award of contract modifications either through supplemental agreements or change orders that exceed the ACO’s appointed warrant limitations.

(2) Issuance of default letters.

(3) Issuance of Cure or Show-Cause Notices.

(4) Suspension of work letters and/or modifications.

(5) Issuance of Contracting Officer final determination letters.

(6) Issuance of termination notices.

(7) Authorization of final payment.

(c) The work will be under the direction of a Department of Veterans Affairs Contracting Officer, who may designate another VA employee to act as resident engineer at the construction site who possesses limited warranted authority.

(d) Except as provided below, the resident engineer’s directions will not conflict with or change contract requirements. Within the limits of any specific authority delegated by the Contracting Officer, the resident engineer may, by written direction, make changes in the work. The Contractor shall be advised of the extent of such authority prior to execution of any work under the contract.

(e) The Contracting Officer or an Administrative Contracting Officer identified in paragraph (a) may further delegate limited authority and specialized support services responsibilities below to the following warranted Resident Engineer personnel on site, not to exceed the dollar value and threshold of their warrant:

(1) Conduct post-award orientation conferences.

(2) Issue administrative changes (see FAR 43.101) correcting errors or omissions, contractor address, facility or activity code, remittance address, computations which do not required additional contract funds, and other such changes.

(3) For actions not to exceed negotiate and execute supplemental agreements resulting from change orders issued under the Changes clause.

(4) Negotiate and execute supplemental agreements changing contract delivery schedules where the time extension does not exceed calendar days.

(End of Clause)

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C26325B0007 X 04-15-2025 618-25-3-2425-0006 656-19-307 36C263 Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

Contract Officer 4801 Veterans Drive St. Cloud

MN

56303 Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

Contract Officer 4801 Veterans Drive St. Cloud

MN

56303 Traci Johannes 320-469-4322 Project Number: 656-19-307 Bldg 51-1 Eastside Remodel POC: Traci Johannes; traci.johannes@va.gov; 320-469-4322

Contractor shall provide all tools, materials, equipment, labor, and supervision necessary in accordance with the construction documents for completion of the project. The purpose of this project is to fully demolish and remodel Building 51-1 Eastside with a remodel of patient care area Building 49-1 Eastside at the VA Health Care System campus.

This solicitation is issued in accordance with Public Law 109-461, the Veterans Benefits, Healthcare Information and Technology Act of 2006, Sections 502 and 503, as a set-aside for Service Disabled Veteran Owned Small Business (SDVOSB) concerns. Pursuant to 38 USC 8127(d), Veterans First Contracting Program, competition is restricted to SDVOSB construction firms, as there is an expectation that offers will be received by two (2) or more SDVOSB contractors under this solicitation. In accordance with VAAR 819.7003(b), at the time of submission of offers and prior to award of a contract, the offeror must represent to the Contracting Officer that it is a (1) SDVOSB eligible under VAAR 819.70; (2) small business concern under the NAICS code assigned to this acquisition; and

(3) listed as a verified SDVOSB in VetCert (formally VIP) database at https://www.veterans.certify.sba.gov.

The applicable NAICS Code for this acquisition is 236220 with a $45.0 Million small business size standard. The magnitude of construction cost range is between $2,000,000.00 and $5,000,000.00.

See Contracting Officer's Special Information and Instructions for more information pertaining to this solicitation.

X X 52.211-10 X ten (10) 16:30

CDT

05-22-2025 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

CLIN 0001 Base Project ___________________

656-3650162-2425-854200-3220 23NR9WA34

Purchase Order Number: TBD Dept of Veterans Affairs Network Contracting Office 23 316 Robert Street North, Suite 506 Saint Paul

MN

55101 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin

TX

78714 Traci Johannes

VA-VHA-RPOC-2025-0004

Table of Contents

A.1 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)1
A.2 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)1
A.3 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)1
A.4 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)3
A.5 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)4
A.6 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)4
PART I - THE SCHEDULE6
SECTION A - SOLICITATION/CONTRACT FORM6
A.7 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)6
A.8 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK7
A.9 PRICE/COST SCHEDULE16
ITEM INFORMATION16
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS16
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS17
2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)17
2.2 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)17
2.3 52.216-1 TYPE OF CONTRACT (APR 1984)18
2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)18
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)18
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)19
2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)20
2.8 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)21
2.9 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)21
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)21
2.11 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023)22
REPRESENTATIONS AND CERTIFICATIONS23
3.1 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)23
3.2 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)25
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)27
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)28
GENERAL CONDITIONS31
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)31
4.2 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)31
4.3 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—PROHIBITION (DEC 2023)33
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)37
4.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)37
4.6 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)39
4.7 52.223-20 AEROSOLS (MAY 2024)43
4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)44
4.9 52.236-4 PHYSICAL DATA (APR 1984)48
4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS49
4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)50
4.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)53
4.13 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (NOV 2022)56
4.14 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)57
4.15 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)58
4.16 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)59
4.17 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)60
4.18 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)60
4.19 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)60
4.20 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)60
4.21 ADDITIONAL ATTACHMENTS63

CONTRACT AWARD

Award may only be made with the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the government, considering only price (see FAR 52.214-19). The low price will be evaluated by the Contracting Officer prior to award to confirm that it is “a fair and reasonable price that is most advantageous to the Government.”

CONTRACTOR'S SIGNATURE

Contractual documents (e.g. bids, proposals, awards, modifications, etc.) shall be completed and signed by the Contractor as follows (see FAR 4.102):

· Individuals. Signed by the individual. Individual doing business as a firm. Signed by that individual, and the signature shall be followed by the individual's typed, stamped, or printed name and the words, "an individual doing business as __________________ (insert name of firm)".

· Partnership. Signed in the partnership name. Prior to award, provide list of all partners and designate which partners have authority to bind the partnership.

· Corporations. Signed in the corporate name followed by the word "by" and the signature, and title of the person authorized to sign. Prior to award, provide list of individuals who have authority to bind the corporation.

· Joint Ventures. Signed by each participant in the joint venture in the manner prescribed in (a) through (d) above.

· Agents. When an agent is to sign the contract, other than as stated in paragraph (a) through (e) above, the agent's authorization to bind the principal must be established by evidence satisfactory to the contracting officer.

SITE VISIT

A formal site visit has been scheduled for this project (see FAR 52.236-27). The pre-bid site visit will be at 9:00am (CT) on Thursday April 24, 2025 at the St Cloud VA Health Care System, 4801 Veterans Drive, St Cloud, MN, in building 3, room 207c. This will be the only opportunity for potential bidders to visit the site. All potential bidders, subcontractors, and suppliers are strongly encouraged to attend this site visit.

TECHNICAL QUESTIONS AND INQUIRIES

Questions of a technical nature and inquiries concerning this solicitation must be provided in writing and shall be submitted by the prospective offerors to the Contract Specialist, Colin Moening. Questions shall be submitted only via email to: colin.moening@va.gov. The subject line must read: PN: 656-19-307 Remodel Building 51-1 Eastside Questions. Telephone inquiries will not be accepted. Questions, inquiries, or such are due no later than May 2nd, 2025, at 4:00 PM (CT). No late questions will be accepted or answered after this deadline. All questions will be answered and/or responded to via an amendment after the closing date.

YOU ARE INSTRUCTED SPECIFICALLY TO CONTACT ONLY THE CONTRACTING OFFICER ISSUING THE SOLICITATION ABOUT ANY ASPECT OF THIS REQUIREMENT PRIOR TO CONTRACT AWARD.

BIDDING MATERIAL

Bidding materials consisting of Invitation for Bids, drawings, specifications, and contract forms will be available on https://sam.gov in electronic format only. All interested parties (subcontractors & primes) should register at https://sam.gov as an “Interested Vendor” so that others will know of your interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contracting Officer.

Amendments to the solicitation will be posted at https://sam.gov. Paper copies of the amendments will NOT be individually mailed. No other notification of amendments will be provided. By registering to “Receive Notification”, you will be notified by email of any new amendments that have been issued and posted. Offerors are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of offers. Failure to acknowledge an amendment may result in the offeror’s bid being considered non-responsive.

PREPARATION OF BIDS

The Government will not pay for any costs incurred in the preparation and submission of bids.

BID SUBMISSION DOCUMENTS

Files should be in Adobe* PDF (Portable Document Format) Files: Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. If the size limits are exceeded, the VA may not receive the file and/or you may not be considered. Only one email is permitted. This email should contain at least the following:

· Standard Form (SF) 1442 Solicitation, Offer, and Award: The offeror shall complete and sign the “OFFER” section of the SF 1442. Please include your company’s Unique Entity Identifier associated with SAM.gov in Block 14.

· Acknowledgement of All Amendments: The offeror shall agree to and acknowledge all amendments by either 1.) completing block 19 of the SF 1442, or 2.) returning the signed amendment form(s) with the submission.

· Price Schedule: The offeror shall complete the Price Schedule which is provided with the solicitation.

· Bid Guarantee: The offeror shall furnish a bid guarantee (see FAR 52.228-1). The bid guarantee shall be provided on Standard Form 24. The Power of Attorney document will be included with the bid guarantee.

· Tax on Certain Foreign Procurements – Notice and Representation: The offeror shall provide their response to FAR 52.229-11 (d).

· Representations & Certifications: As the provision at FAR 52.204-7 is included in the solicitation, FAR 52.204-8 (d) applies and the fill-in for FAR 52.204-8 (b)(2) does not need to be completed. The offeror is required to complete the annual representations and certifications electronically at https://sam.gov.

· Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment: The offeror shall provide their response to FAR 52.204-24 (d) Representations.

· Information Regarding Responsibility Matters: The offeror shall provide their response to FAR 52.209-7 (b).

· Violation of Arms Controls Treaties or Agreements: The offeror shall provide their response to FAR 52.209-13 (b) Certification.

· Post Award Small Business Program Representations: The offeror shall provide their response to FAR 52.219-28 (h), if applicable.

· Limitations on Subcontracting: The offeror shall complete and sign the VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction required in VAAR 852.219-75 and return it with their bid submission. A copy of the clause to be completed and included with the bid is attached as a separate document (Limitations on Subcontracting Cert of Compliance (2pages)). The completed and signed form will become part of the official award documentation.

· Experience Modification Rate: The offeror shall provide the Safety and Environmental Violations and Experience Modification Rating (EMR) information, including filling out the attached document (Safety or Environmental Violations and EMR Information (2 pages)).

DELIVERY OF BIDS

In accordance with FAR 14.202-8, send all submission documents via email to the Contract Specialist, Traci Johannes at traci.johannes@va.gov by 9:00 AM (CT), Thursday, May 22nd, 2025. The subject line must read: PN: 656-19-307 Remodel Building 51-1 Eastside.

Bids received after this time may be rejected. Bidders are responsible for ensuring and verifying their bid and all required bid documents are received at the email address designated in block eight (8) of the SF 1442 solicitation and by the date and time specified in block thirteen (13)a of the SF 1442 solicitation (subject to amendment).

BID OPENING

There will not be a face-to-face public bid opening. All Contractors providing an electronic bid submission must still meet all requirements listed under “Bid Submission Documents” in the solicitation. The bid opening and public reading of the bids will be via teleconference. Bidders may call 1-872-701-0185 on Thursday , May 22nd, 2025 at 9:00 AM (CT) and enter participant code 355369213# to join.

The bid submission emails will be kept in an electronic folder unread until the stated date and time at which time they will be opened and read to the public.

In the event there are any concerns with the bids, in accordance with FAR 14.402-1 (c), Microsoft Teams will be used to assist in the examination of the bid(s).

INFORMATION REGARDING BID GUARANTEE AND BONDS

Offerors are to ensure the most current version of SF24, SF25, and SF25A bond forms are used. Current versions of these forms can be found and downloaded from the GSA Forms Library (https://gsa.gov/reference/forms).

A bid guarantee (SF24) is required in an amount not less than 20 percent of the bid price but shall not exceed $2,000,000.00. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. A copy of the bid guarantee shall be submitted as part of the electronic submission and the original hard copy of the bid bond shall be retained by the Contractor.

Failure to provide electronic bid guarantee by the date and time set for receipt of bids may deem the bid non-responsive.

Performance bond (SF25) and payment bond (SF25A) in the penal sum of 100% of the awarded contract amount shall be submitted within ten (10) calendar days after award to the Contracting Officer for approval. Commencement of construction is contingent upon approval of required bonds. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

DETERMINATION OF NON-RESPONSIVE

Bids received pertaining to this solicitation will be reviewed for responsiveness. Failure to provide documentation as outlined in the Bid Submission Documents section of the solicitation by the date and time set for receipt of bids may deem the bid non-responsive.

Any exception to the terms and conditions of this Invitation for Bid (IFB) will result in a nonresponsive bid.

Failure to provide a definitive price will result in a nonresponsive bid.

DETERMINATION OF RESPONSIBILITY

A Determination of Responsibility will be conducted for the apparent low bidder/awardee prior to award of the project. The above information, along with other information obtained from Government systems, such as, but not limited to the OSHA and EPA online inspection history databases, as well as any other information the Contracting Officer has determined to be valid, will be used to make the Determination of Responsibility. Note: Any information received by the Government that would be cause for a negative Determination of Responsibility may make the offeror ineligible for award.

The winning bidder must be determined as "responsible" by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.

To be determined responsible, a prospective contractor must –

1. Have adequate financial resources to perform the contract, or the ability to obtain them.

1. Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments.

1. Have a satisfactory performance record.

1. Have a satisfactory record of integrity and business ethics.

1. Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).

1. Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them.

1. Be otherwise qualified and eligible to receive an award under applicable laws and regulations.

Note: The contracting officer shall obtain information regarding the responsibility of the prospective low bidder, including requesting pre-award surveys, when necessary, promptly after a bid opening in accordance with FAR 9.105-1—Obtaining Information. The prospective low bidder shall be prepared to provide documentation to support this determination within two business days following bid opening.

VETS 4212

Title 38, USC Section 4212(d), codified at 41 CFR Section 61-300, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS-4212 reporting information can be done electronically (https://www.dol.gov/vets/vets4212). Award cannot be made unless the awardee has filed their VETS-4212 report. Therefore, all offerors are encouraged to file every year. The Contracting Officer may request a copy of the email confirmation of receipt notification prior to awarding the project.

SYSTEM FOR AWARD MANAGEMENT (SAM)

Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database (https://sam.gov) and enter all mandatory information into the system. Offerors are required to be registered in SAM at the time an offer is submitted in order to comply with the annual representations and certifications requirements (see FAR 52.204-7). System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS) As prescribed in Federal Acquisition Regulation (FAR) Part 42.1502(e), the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement, VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS is available to all Federal agencies and is the system used to collect and retrieve performance assessment reports used in source selection determinations. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.

Each contractor whose contract award is estimated to exceed $750,000 is required to register with CPARS database (https://cpars.gov) Help registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207- 438-1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor’s registered representative.

For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.

Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.

BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS

All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform all work as identified in the solicitation documents. This requirement is applicable to all subcontractor personnel requiring the same access. As per VA Directive 0710, costs of background investigations will be borne by the contractor. Please be advised the awardee will need to coordinate with the VA Medical Center concerning badging requirements.

HHS/OIG EXCLUSIONS

To ensure the individuals providing services under the contract have not engaged in fraud or abuse regarding Sections 1128 and 1128A of the Social Security Act regarding federal health care programs, the contractor is required to check the Exclusions Database – U.S. Department of Health and Human Services (HHS), Office of Inspector General (OIG), List of Excluded Individuals/Entities on the website (https://exclusions.oig.hhs.gov) for each person providing services under this contract. Further the Contractor is required to certify in its proposal that all persons listed in the contractor’s proposal have been compared against the OIG list and are NOT listed. During the performance of this contract the contractor is prohibited from using any individual or business listed on the List of Excluded Individuals/Entities.

REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, OR PROJECT MANAGER

Any reference contained within the solicitation/contract specifications and/or drawings to the “VA Engineer,” “Resident Engineer,” or “Project Manager,” or their abbreviations shall be replaced with “Contracting Officer’s Representative (COR).”

PRE-CONSTRUCTION CONFERENCE

Before any work is started, a Pre-Construction Conference between the Contractor, Contracting Officer, and Project Engineer will be arranged through the Contracting Officer. Such matters as work commencement, sequence of work, estimated time for accomplishment, subcontractor information, and the overall responsibilities of the Contractor, Contracting Officer, and Project Engineer in the fulfillment of all aspects of the contract will be discussed.

A.9 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

PROJECT# 656-19-307; REMODEL BUILDING 51 FIRST FLOOR EAST SIDE FOR CLC; CONTRACTOR SHALL FURNISH ALL LABOR, MATERIALS, TOOLS AND EQUIPMENT REQUIRED TO REMODEL THE EXISTING LOCKED DEMENTIA WARD ON THE EAST SIDE OF BUILDING 51, FIRST FLOOR. THIS PROJECT SHALL ALSO UPDATE LIGHTING, WALL SURFACES, AND THE GENERAL ENVIRONMENT DECOR. THIS PROJECT WILL INCLUDE IMPACTED SPACE WITHIN THE ADJACENT BUILDING 48 FIRST FLOOR SPACE AT THE ST. CLOUD VA HEALTHCARE SYSTEM. 4801 VETERANS DRIVE, ST. CLOUD, MN 56303. ALL WORK IS TO BE PERFORMED ACCORDING TO THE SCOPE OF WORK. CONTRACT SPECIFICATION AND DRAWINGS. ALL WORK SHALL BE PERFORMED MONDAY THROUGH FRIDAY 8AM-4:30PM UNLESS OTHERWISE APPROVED. PERIOD OF PERFORMANCE - 456 DAYS AFTER NTP PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Y1DA - Construction of Hospitals and Infirmaries

GRAND TOTAL
__________________

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.2 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

(a) The Contractor shall comply with agency personal identity verification procedures identified in the contract that implement Homeland Security Presidential Directive-12 (HSPD-12), Office of Management and Budget (OMB) guidance M-05-24, and Federal Information Processing Standards Publication (FIPS PUB) Number 201.

(b) The Contractor shall account for all forms of Government-provided identification issued to the Contractor employees in connection with performance under this contract. The Contractor shall return such identification to the issuing agency at the earliest of any of the following, unless otherwise determined by the Government:

(1) When no longer needed for contract performance.

(2) Upon completion of the Contractor employee's employment.

(3) Upon contract completion or termination.

(c) The Contracting Officer may delay final payment under a contract if the Contractor fails to comply with these requirements.

(d) The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts when the subcontractor's employees are required to have routine physical access to a Federally-controlled facility and/or routine access to a Federally-controlled information system. It shall be the responsibility of the prime Contractor to return such identification to the issuing agency in accordance with the terms set forth in paragraph (b) of this section, unless otherwise approved in writing by the Contracting Officer.

(End of Clause)

2.3 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

FAR Number
Title
Date
52.228-1
BID GUARANTEE
SEP 1996
52.228-17
INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
FEB 2021

2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Traci Johannes traci.johannes@va.gov Hand-Carried Address:

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

Contract Officer 4801 Veterans Drive St. Cloud MN 56303-2099 Mailing Address:

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

Contract Officer 4801 Veterans Drive St. Cloud MN 56303-2099

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

FAR Number
Title
Date
52.236-27
SITE VISIT (CONSTRUCTION) ALTERNATE I (FEB 1995)
FEB 1995

2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer.

This is the start of the file's text. The full file is on GovTribe.