36C26223Q0307 Question and Answers.docx

DOCX document 17 KB Posted

Attached to
J041--CHILLER MAINTENANCE & REPAIR JMVAMC RFQ Due Date Update Site Visit Notification
Solicitation number
36C26223Q0307
Issued by

About this file

This solicitation requests quotations for chiller maintenance and repair services. The Department of Veterans Affairs seeks monthly and annual maintenance as well as emergency repair for four chillers totaling 3,300 tons located at the Jennifer Moreno VA Medical Center in San Diego, California. Quotations are due by January 13, 2023. Interested vendors must possess C-20 HVAC and C-10 electrical licenses and submit pricing for routine maintenance of three 1,350-ton centrifugal chillers, one 500-ton absorption chiller, and chiller control system maintenance. The solicitation is set aside for Service-Disabled Veteran Owned Small Businesses.

View the file

Other files

File Type Posted
36C26223Q0307 0004.docx DOCX document
Question and Answers 0004 - Chiller Maintenance.docx DOCX document
COMBINED SYNOPSIS - Amendment 3 - Chiller Maintenance.docx DOCX document
SOW - Revised.docx DOCX document
COMBINED SYNOPSIS - Amendment 2 - Chiller Maintenance.docx DOCX document
36C26223Q0307 0001.docx DOCX document
Site Visit - Chiller Maintenance.doc DOC document
RFQ - 36C26223Q0307 - Chiller Maintanence.pdf PDF
36C26223Q0307_1.docx DOCX document
RFQ - 36C26223Q0307.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Vendor Question & Answers 36C26223Q0307

Q. - As a SDVOSB, are we able to subcontract a portion of the work to the manufacturer?

A. - Subcontracting is address throughout the RFQ with provisions and clauses. It would be very lengthy for me to address them all, please reference the RFQ to answer the subcontracting inquiry.

Q. - Any changes after site walk?

A. – Yes, see SOW – Revised posted in Amendment.

Q. - Will a C-10 license be needed with a C-20 and C-38?

A. – The revised SOW does not specify a specific license but states “Contractor shall obtain all necessary licenses required to perform this work”, therefore, the contractor is responsible for adhering to California licensing requirements.