This is a solicitation and Statement of Work for electrical construction services at the VA Sierra Nevada Health Care System in Reno, Nevada. The Department of Veterans Affairs seeks a Service-Disabled Veteran-Owned Small Business (SDVOSB) contractor to relocate and add emergency power to water pump systems in Building 12's basement. The project requires installing emergency power capability, relocating normal power onto the existing Motor Control Center (MCC), and installing a manual transfer switch (MTS) to ensure compliance with VA Technical Information Library standards and VHA Electrical Design Manual requirements. The contractor must provide all personnel, equipment, tools, materials, and supervision necessary for completion.
Key requirements include: submission of a detailed project schedule with materials, labor, and construction milestones within two weeks of project start; project completion within 180 calendar days after Notice to Proceed; a General Contractor's Competent Person/Superintendent holding 30-hour OSHA construction safety certification; all on-site employees and subcontractors holding 10-hour OSHA certification; strict adherence to Lock-Out-Tag-Out procedures; work performed Monday through Friday, 0700 to 1700 hours, excluding federal holidays; and provision of comprehensive quality checks, training, and user manuals upon project completion. The solicitation is a firm-fixed-price contract under NAICS code 238210 (Electrical Contractors) with a small business size standard of $19.0 million. Offerors must be verified in the SBA's Dynamic Small Business Search database, submit proposals by August 15, 2026, at 12:30 p.m. Pacific Time, and provide a pre-proposal site visit is scheduled for July 22, 2026. Bid bonds, payment bonds, and performance bonds are required. Wage Determination NV20260093 applies, and VAAR Clause 852.219-75 must be completed with the proposal or the offer will be ineligible.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26126R0050 0002.docx | DOCX document | |
| MCC SCHEDULE 5-6-22.xlsx | XLSX spreadsheet | |
| 36C26126R0050 0001.docx | DOCX document | |
| Bldg 12 Basement Pump Power Brief Routing Diagram.pdf | ||
| GNHA 9-18-19.xls | XLS spreadsheet | |
| S02- Specification 013526-2024-05.docx | DOCX document | |
| S02 - RNLS Zero Floor Plan.pdf | ||
| S02- Specification 260511-2022-11.docx | DOCX document | |
| S02 - Key Personnel Attachment for Evaluation.docx | DOCX document | |
| S02 - Attachment - EMR Sheet.docx | DOCX document | |
| Wage determination NV20260093.docx | DOCX document | |
| S02 - VAAR 852.219-75.pdf | ||
| S02- Specification 260541-2026-01.docx | DOCX document | |
| S02- Specification 010000-2021-11.docx | DOCX document | |
| S02 - RFI FORM.docx | DOCX document | |
| S02 - Attachment - Price Breakdown Sheet.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26126R0050 Attachments
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C26126R0050 X 04-21-2026
TBD
654-26-2-6059-0042 654-26-020 36C261 Department of Veterans Affairs Network Contracting Office (NCO) 21 VA Sierra Nevada Health Care System 975 Kirman Avenue Reno NV 89502-2597 Network Contracting Office 21 Edwin Rivera edwin.rivera@va.gov Jose Hernandez jose.hernandez1@va.gov Edwin Rivera 775-789-7159 Project Title: Building 12 Pump Power Relocation (Project No. NRM 654-26-020) Project Location: VA Sierra Nevada Health Care System, Building 12, 975 Kirman Avenue, Reno, NV 89502-2597
Project Requirement: The contractor shall provide all personnel, equipment, tools, materials, and supervision necessary to relocate and add additional power legs to the water pumps in the building 12 basement. Work includes installing power, relocating normal power onto the Motor Control Center (MCC), and installing a manual transfer switch (MTS) to ensure the system is fully compliant with the VA Technical Information Library (TIL) and the Veterans Health dministration (VHA) Electrical Design Manual.
NAICS with size standards: 238210 - Electrical Contractors and Other Wiring Installation Contractors. Small Business Size Standard: $19.0 Million.
Bid bonds, payment bonds, and performance bonds shall be required under this solicitation and any resultant contract.
Site Visit is scheduled for Wednesday at 0900 PM PST, 22 July 2026 meeting at Reno VAMC, 975 Kirman Rd, Reno, NV 89506 Main building lobby in front of the Coffee shop.
Requests for Information (RFIs) are due Friday at 1000 AM PST, 31 July 2026
Proposal Submission Due date: Friday at 1230 PM PST, 15 August 2026
This project shall be completed within 180 calendar days after Notice to Proceed (NTP).
This is a 100% SDVOSB Set-Aside.
Offerors must be verified in the U.S. Small Business Administration's Small Business seach database.
Wage Determination NV20260093 dated 06/22/2026 applies to this solicitation.
VAAR Clause 852.219-75 needs to be completed when submitting offer; if not provided, offer will not be considered for Award.
Ten (10) x x 52.211-10 X Ten (10) Email 12:00
PDT
08-14-2026 X Sixty (60)
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C261 Department of Veterans Affairs Network Contracting Office 21 VA Sierra Nevada Health Care System 975 Kirman Avenue Reno NV 89502-2597 Department of Veteran Affairs FMS-VA-2(101) Financial Services Center PO Box 149971 Austin TX 78714-9971 Jose Hernandez
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 PRICE/COST SCHEDULE | 9 |
| ITEM INFORMATION | 9 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 9 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 10 |
| 2.1 52.204-7 SYSTEM FOR AWARD MANAGEMENT—REGISTRATION (DEVIATION) (NOV 2025) | 16 |
| 2.2 52.216-1 TYPE OF CONTRACT (NOV 2025) (DEVIATION) | 18 |
| 2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (NOV 2025) (DEVIATION) | 19 |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 19 |
| 2.5 52.228-1 BID GUARANTEE (SEP 1996) | 20 |
| 2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 21 |
| 2.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 21 |
| 2.8 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION) | 22 |
| 2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 26 |
| 2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 26 |
| 2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 26 |
| REPRESENTATIONS AND CERTIFICATIONS | 28 |
| 3.1 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 28 |
| 3.2 52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION (JUN 2020) | 30 |
| GENERAL CONDITIONS | 32 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 32 |
| 4.2 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (NOV 2025) (DEVIATION) | 38 |
| 4.3 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (NOV 2025) (DEVIATION) | 40 |
| 4.4 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (NOV 2025) (DEVIATION) | 40 |
| 4.5 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS (DEVIATION APR 2026) | 42 |
| 4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (DEVIATION) (NOV 2025) | 43 |
| 4.7 52.243-4 CHANGES (JUN 2007) | 47 |
| 4.8 SUPPLEMENTAL INSURANCE REQUIREMENTS | 48 |
| 4.9 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION) | 49 |
| 4.10 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 58 |
| 4.11 VAAR 852.204-72 PERSONNEL VETTING AND CREDENTIALING (DEVIATION) (MAR 2026) | 61 |
| 4.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 64 |
| 4.13 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 67 |
| 4.14 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 67 |
| 4.15 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 67 |
| 4.16 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 69 |
| 4.17 IT CONTRACT SECURITY | 70 |
General Information
1. GENERAL: The Reno, NV Veteran’s Affairs (VA) medical center’s building 12 is needed of relocating the power sources for water pumps in the basement. The current system directly feeds the pumps with normal power and has no emergency power source tied onto the system. In the event of a power outage, the motor control center (MCC) will not be able to provide power onto the pumps for the entirety of the building. The purpose of this Statement of Work (SOW) is to outline the project planning stages, schedule, and important prerequisites of installing emergency power and relocating normal power onto the MCC as well as installing a manual transfer switch (MTS). According to the VA Technical Information Library (TIL) chapter 4 section 4.6, the guide states that all essential electrical systems are to be supplied with additional electrical standby systems. This includes but is not limited to domestic water pumps, equipment, control systems, and the receptacles for the pumps. Relocating the power source for the water pumps will allow the facility to be in proper compliance with VHA guidelines. This power source will directly improve patient safety in an efficient manner while maintaining code compliance.
2. OBJECTIVES: The objective of the project is to relocate and add additional power legs to the water pumps in the BLDG 12 basement. The new emergency/normal power system is to be fully compliant with the VA TIL, Veteran’s Health Administration (VHA) Electrical Design Manual, and up to date safety codes. The following objectives shall be undertaken:
· Schedule: The contractor shall provide a completed scheduled document that includes all required materials, labor, and construction milestones, within the first two weeks of the project start date.
· Projected completion date: The contractor shall complete the project within 180 calendar days after notice to proceed.
· Budget Management: The contractor shall keep the project within budget at the time of the award for the duration of the project.
· Quality Management: The contractor shall ensure that the completed electrical system meets all required specifications by conducting a thorough quality check before and after project turnover. The handover should also include a training session of equipment via in-person training and an included user manual.
· Safety: The contractor shall implement all necessary safety protocols, ensuring zero workplace accidents by conducting regular safety checks throughout the project. This includes but is not limited to facility Lock Out Tag Out procedures.
3. SCOPE: For the process of the statement of work for the relocation of the bldg. 12 pump normal/emergency power legs. The following activities shall be undertaken:
· Initial Review: The contractor shall conduct a thorough review of the status of the facility and will do thorough research of deficiencies within the basement pump areas and surrounding equipment. The contractor shall conduct a thorough review of the work area and existing equipment and identify all potential pathways and hazards that are present in the path of work and determine the most feasible course of action for installation.
· Fix identified issues: If any issues are identified, the contractor shall resolve the problem and continue with proposed plan.
· Provide Drawings and Plans: The contractor will work with the facility to update panel schedules, provide red lines, and assist the facility in updating one-line diagrams.
· Communication: The contractor shall engage with the VA to explain the construction process, ensuring awareness and agreement. Provide feedback regarding potential concerns with going through with the installation process.
· Budget Analysis: The contractor shall provide a Schedule of Values (SOV) that accurately represents project costs and will coordinate with the Contracting Officer Representative (COR) and Contracting Officer (CO) on any budget adjustments for the duration of the project.
Please see images below for Bldg. 12 basement equipment references:
Figure 1.1 Motor Control Center with only normal power feeding pumps
Figure 1.2 GEHE Panel next to MTS that feeds into the MCC
Figure 1.3 Conduit lines for the MCC
By focusing on these tasks, we can ensure that the descoping process is executed efficiently and effectively, maintaining the integrity of the current system while avoiding unnecessary budgets.
3. CONCLUSION:
In summary, this project aims to successfully install a new normal/emergency electrical system in the basement of building 12 to ensure facility compliance. The tasks and deliverables outlined in this Statement of Work (SOW) have been acknowledged and agreed upon by both the VA and contractor.
The responsibilities and obligations detailed in this document are understood and accepted by both parties, ensuring a collaborative and transparent effort towards the successful completion of the project. All terms, conditions, and specifications mentioned in this SOW, including timelines, payment schedules, compliance with safety regulations, and quality standards, are binding and must be strictly adhered to. Any amendments or additions to this SOW will be documented in writing and signed by authorized representatives from both parties. This ensures that any changes are formally agreed upon and integrated into the project plan, maintaining transparency and accountability.
END OF STATEMENT OF WORK
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
654-26-020, BLDG 12 PUMP POWER RELOCATION, 180 calendar day after notice to proceed. Planning UID: VA-26-00049756 Contracting UID: 36C261-26-AP-3341 The Reno, NV Veteran's Affairs (VA) medical center's building 12 is need of relocating the power sources for water pumps in the basement. The current system directly feeds the pumps with normal power and has no emergency power source tied onto the system. In the event of a power outage, the motor control center (MCC) will not be able to provide power onto the pumps for the entirety of the building. The purpose of this Statement of Work (SOW) is to outline the project planning stages, schedule, and important prerequisites of installing emergency power and relocating normal power onto the MCC as well as installing a manual transfer switch (MTS). Plans and specs to be provided to the assigned contracting officer.
PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2JZ - Repair or Alteration of Miscellaneous Buildings
MANUFACTURER PART NUMBER (MPN): N/A
| GRAND TOTAL |
| __________________ |
Statement of Work (SOW)
VA SIERRA NEVADA HEALTH CARE SYSTEM
BUILDING 12 PUMP POWER RELOCATION FOR RENO VA
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
1. INTRODUCTION:
a. These instructions prescribe the format of Offers. Offers are defined as consisting of both Prime Contractor’s Price Proposal and Prime Contractor’s Technical Proposal. These instructions describe the approach for the development and presentation of the required information and documentation. These instructions are designed to ensure the submission of necessary information and documentation to provide for the comprehensive evaluation of offers.
b. Offerors are cautioned to carefully review this solicitation prior to commencing preparation. For offers to receive full consideration for award, offerors shall ensure that the information and documentation furnished in support of the price proposal and the technical proposal are current, factual, complete, and accurate.
c. Offerors are strictly advised to comply with all instructions within this solicitation to ensure submission of a complete Prime Contractor Offer. Failure to furnish a complete offer per the instructions of this solicitation by the required time and date may result in the Offeror’s proposal being determined ineligible.
d. The Government intends to award without discussions, unless discussions are in the best interest of the Government.
2. CONTRACT TYPE:
a. The awarded contract will be a firm fixed price (FFP) contract.
b. This solicitation is a total SDVOSB set-aside. The offeror MUST have an active Unique Entity Identification (UEI) number and be current in System for Award Management (SAM). SDVOSB firms must be U.S. Small Business Administration's Dynamic Small Business Search (DSBS) or VetCert databases verified prior to the submission of proposals.
3. SUBMISSION INSTRUCTIONS:
a. Each offeror shall also provide one (1) emailed copy of the technical proposal and one (1) emailed copy of the price proposal, to arrive on or before the due date/time to edwin.rivera@va.gov.
The subject line of the email must cite RFP: 36C26126R0050. In no circumstances shall file size exceed 10MB. Multiple emails are acceptable.
b. Faxed proposals are not permitted under any circumstances.
c. Please ensure you allow time for email transmission.
d. Offerors MUST mark the subject line of the email as 36C26125R0057 Provide Utility Services Across Kirman Avenue Technical Proposal and 36C26125R0057 Provide Utility Services Across Kirman Avenue Technical Price Proposal.
e. Offer Due date is August 15, 2026, at 12:30 P.M. Pacific Time.
4. QUESTIONS CONCERNING THIS RFP:
All Requests for Information (RFIs) regarding this RFP shall be submitted in writing and received no later than Friday July 31, 2026, at 10:00 AM Pacific Time to allow replies to reach all prospective offerors in a timely manner. All RFIs shall be sent via email to Edwin Rivera at edwin.rivera@va.gov.
5. PRE-PROPOSAL SITE VISIT:
Offerors are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing these services. In no event shall failure to inspect the site constitute grounds for a claim after contract award. A site visit will be held on Wednesday July 22, 2025, at 9:30 AM Pacific Time
6. PROPOSAL FORMAT:
a. All commitments made in the proposal may become a part of the resulting contract. The data submitted with each proposal shall be complete and concise, but not overly elaborate. Reliance on promotional brochures is discouraged.
b. The Technical Volume shall not exceed the page limits stated herein. If the page limits are exceeded, the pages in excess of the limit will not be read or considered. Page limits for entire Technical Proposal shall not exceed thirty (30) pages front and back. The CPARS/Past Performance questionnaires do not count as part of the 30 pages.
c. Page Limits Shall Include: All appendices, charts, graphs, diagrams, tables, photographs, drawings, etc. except as noted in the instructions. Text lines will be single-spaced.
d. Emailed proposals shall be prepared on standard 8.5 x 11-inch format (charts may be landscaped but must be on 8.5 x 11-inch format) and shall be in a legible font size (11 or 12 point). All pages of each proposal shall be appropriately numbered and identified with the RFP number. For ease of reference, consecutive page numbering with tabs is required.
e. Email Copy: Provide one (1) email copy of the complete proposal (Volumes 1 and 2) as specified above.
f. Indexing: Each volume will contain a “Table of Contents” for that volume. The “Table of Contents” will identify major elements of technical and price proposals. Tab indexing will be used to identify Sections as appropriate. Table of Contents and Tab indexes do not count toward page limitation.
g. Offerors may, at the discretion of the Government, be asked to provide information for clarification purposes regarding their proposals. Requests for such clarification information do not constitute discussions.
h. The offeror shall be held responsible for the validity of all information supplied in their proposal, including information provided by potential subcontractors. Should subsequent investigation disclose that the fact and conditions were not as stated, the proposal may be rejected and receive no further consideration.
i. If revised proposals are requested, the number of revised copies to be submitted shall be the same as those of initial proposals unless stated otherwise.
7. PROPOSAL VOLUME CONTENTS:
TECHNICAL VOLUME (PROPOSAL SUBMISSION - 1): Include the following information on the cover:
Company Name Project Title: Building 12 Pump Power Relocation (Project No. NRM 654-26-020)
RFP: 36C26126R0050
Volume 1 – Technical Proposal
PROPOSAL SUBMISSION INDEX:
Tab 1: Copies of certifications and licenses, as specified in “Evaluation” section.
Tab 2: Key Personnel Experience, as specified ...
Tab 3: Technical/Management Approach, as specified ...
Tab 4: Past Performance, as specified ...
Tab 5: Sustainable Acquisition Plan IAW VAAR 852.223-70
a. The Technical volume shall include necessary information regarding the offeror’s ability to fulfil requirements outlined in the solicitation. Failure to provide a Technical Proposal in accordance with the solicitation instructions shall render an offeror’s proposal incomplete and ineligible for award.
b. Similar scope and complexity, when referred to in the evaluation factors, are defined as projects that consist primarily with HVAC, Flooring (same type) and trailer swing space components, modernization, repair, and maintenance.
c. Similar magnitude (size), when referred to in the evaluation factors, is defined as projects that were valued between $250,000 and $500,000.
d. The project personnel included in the offer shall be the personnel that are assigned to the project for the entire project. In the event a substitution must be made during the course of the project, the contractor shall submit to the contracting officer a request that includes a resume of the proposed substitution that indicates the person meets all of the qualifications in the evaluation factor included in this solicitation.
e. This project requires four positions to be assigned: Project Manager, Superintendent, Safety Officer, and Quality Control Officer. The Superintendent must be full-time and dedicated only to this project. The Superintendent must perform full-time in this role and no other role. The Superintendent must not perform other duties or responsibilities, i.e., safety officer, quality control officer, job site or home office project manager during the project duration.
f. The letter of intent for project personnel shall contain the following information:
i. Current Employees - Letter that is signed by both the employee and contractor lists the solicitation the contractor is proposing on and their proposed roll on the project.
ii. Potential Employees - Contractor must provide a letter of intent signed by both the Contractor and potential employee that lists the following:
1. Specific solicitation/project being offered on
2. The position the proposed employee will be taking
3. Statement that the proposed employee has NO known conflicts that would prevent him or her from completing this project if awarded and that this person possesses the skills necessary to perform the required tasks as assigned
g. If proposed as a joint venture, a copy of the executed joint venture agreement shall be included with the proposal.
PRICE VOLUME (PROPOSAL SUBMISSION – 2): Include the following information on the cover:
Company Name Provide Utility Services Across Kirman Avenue
RFP: 36C26122R0053
Volume 2 – Price
PROPOSAL SUBMISSION INDEX
Tab 1: Standard Form 1442 (fully completed and signed); and acknowledgment of all amendments by either entering data in block 19 of the SF1442 or, completing blocks 15 a, b and c of the Amendment(s) (SF30’s) and returning with offer.
Tab 2: Cost Break-Out Sheet (fully completed) Tab 3: SF24 Bid Bond with Raised Seals, and Power of Attorney (original bid bond, fully completed/signed as required) Tab 4: Safety & Environmental Record Documentation Tab 5: Experience Modification Rate (EMR) Documentation Tab 6: Representations and Certifications. as applicable Tab 7: VAAR 852.219-75 (JAN 2023) (DEVIATION) (attached) Offerors must complete and submit the VAAR 852.219-75 document attached to this solicitation to be considered for award. Earlier versions are not acceptable. Be advised:
a. Offeror's Name: The name should match the actual legal name of the offeror as captured in SAM.gov. If the offeror's name is `SDVOSB Craftsman, LLC,' the full legal name of the entity must be entered in each separate section of the certification that contains the following brackets: [Insert Name of Offeror]. It is not sufficient for the offeror's company name to be inserted at the bottom of the certification only. The offeror's name must be entered in the brackets referenced above.
b. Printed Name and Title of Signee: Enter the printed name and job title of the signee.
c. Signature: The certification statement must be signed by an individual who is authorized to execute the certification on behalf of the offeror.
d. Date: The certification must be properly dated.
e. Company Name and Address: The certification must include the signee's complete business name and address.
*Note: Offerors are responsible for insuring and verifying their offer and all required documents are received at the address designated in block 8 of the SF1442 Solicitation (and further specified directly below) by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment).
PROSPECTIVE CONTRACTORS’ RESPONSIBILITY: Purchases shall be made from, and contracts shall be awarded to, responsible prospective contactors only. The presumed winning offer must be determined as “Responsible” by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications. To aid in making this determination, offerors shall provide:
1. Safety & Environmental Record information as specified below
2. Experience Modification Rate (EMR) information as specified below
3. Completed Representations and Certifications; FAR 52.204-8, 52.209-5, and 52.209-7. (See Section K of RFP as appropriate).
This information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines below or submit this information may result in a determination of non-Responsibility and make the offer ineligible for award. The Contracting Officer will obtain additional information as needed and specified in FAR 9.105-1 to make the Determination of Responsibility, to include, but not limited to the Federal Awardee Performance and Integrity Information System (FAPIIS), Excluded Parties List System (EPLS) and Past Performance Information Retrieval System (PPIRS).
PER VHA DIRECTIVE 7715 (06 April 2017: SAFETY & ENVIRONMENTAL RECORD AND EXPERIENCE MODIFICATION RATE (EMR): To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.
All offers shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their proposal.
1. SAFETY & ENVIRONMENTAL RECORD: A self-certification on company letterhead that the Offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
1. EMR: All offerors shall submit information regarding their current EMR. This information shall be obtained from the Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an offeror’s EMR is above 1.0, Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.
ADDITIONAL SOLICITATION INFORMATION: See Provision 52.236-27 for specific information regarding the project pre-proposal site visit. This pre-proposal site visit will be the only opportunity for potential offerors to visit the site. All potential contractors, subcontractors, and suppliers are strongly encouraged to attend this pre-proposal site visit.
REQUEST FOR INFORMATION (RFI): To obtain clarifications and/or additional information concerning the contract requirements, submit a written RFI utilizing the RFI Form included in this RFP, and send it via email to edwin.rivera@va.gov. See RFI Form for specifics.
RFIs will be responded to as necessary in amendment format and will be posted on FBO (now called Contract Opportunities). Deadline for submission or RFIs for this RFP is July 31, 2026, at 10:00 AM Pacific Time. No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone request for information will not be accepted or returned.
SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at https://sam.gov/SAM/ and enter all mandatory information into the system. Award cannot be made until the contractor has been registered. Offerors are encouraged to ensure that they are registered in SAM prior to submitting their offer. (See FAR 4.1102)
ADDITIONAL SBA DSBS INFORMATION:
(a) Eligibility of SDVOSBs continues to be governed by the Small Business Administration regulations, 13 CFR subparts 125.8 through 125.13, as well as the FAR, except where expressly directed otherwise by the VAAR, and 38 CFR verification regulations for SDVOSBs.
(b) At the time of submission of offer, the offeror must represent to the contracting officer that it is a—
(1) SDVOSB concern
(2) Small business concern under the North American Industry Classification System (NAICS) code assigned to the acquisition; and
(3) Verified for eligibility in the SBA DSBS database (https://dsbs.sba.gov/search/dsp_dsbs.cfm).
(c) A joint venture may be considered an SDVOSB or VOSB concern if
(1) At least one member of the joint venture is an SDVOSB or VOSB concern and makes the representations in paragraph (b) of this section.
(2) Each other concern is small under the size standard corresponding to the NAICS code assigned to the procurement.
(3) The joint venture meets the requirements of paragraph 7 of the size standard explanation of affiliates in FAR 19.101; and
(4) The joint venture meets the requirements of 13 CFR 125.15(b), modified to include Veteran-owned small businesses where this CFR section refers to SDVOSB concerns.
(d) Any SDVOSB or VOSB concern (nonmanufacturer) must meet the requirements in FAR 19.102(f) to receive a benefit under this program.
JOINT VENTURES: See 13 C.F.R. § 121.103(h)
(h) Affiliation based on joint ventures. A joint venture is an association of individuals and/or concerns with interests in any degree or proportion consorting to engage in and carry out no more than three specific or limited-purpose business ventures for joint profit over a two-year period, for which purpose they combine their efforts, property, money, skill, or knowledge, but not on a continuing or permanent basis for conducting business generally.
This means that a specific joint venture entity generally may not be awarded more than three contracts over a two-year period, starting from the date of the award of the first contract, without the partners to the joint venture being deemed affiliated for all purposes. Once a joint venture receives one contract, SBA will determine compliance with the three awards in two years rule for future awards as of the date of initial offer including price.
As such, an individual joint venture may be awarded more than three contracts without SBA finding general affiliation between the joint venture partners where the joint venture had received two or fewer contracts as of the date it submitted one or more additional offers which thereafter result in one or more additional contract awards. The same two (or more) entities may create additional joint ventures, and each new joint venture entity may be awarded up to three contracts in accordance with this section. At some point, however, such a longstanding inter-relationship or contractual dependence between the same joint venture partners will lead to a finding of general affiliation between and among them.
For purposes of this provision and in order to facilitate tracking of the number of contract awards made to a joint venture, a joint venture must be in writing and must do business under its own name, and it may (but need not) be in the form of a separate legal entity, and if it is a separate legal entity it may (but need not) be populated (i.e., have its own separate employees). SBA may also determine that the relationship between a prime contractor and its subcontractor is a joint venture, and that affiliation between the two exists, pursuant to paragraph (h)(4) of this section.
NOTICE TO PROCEED (NTP): A notice to proceed (NTP) shall be issued after award of a fully executed contract. The NTP date and time are “to be determined” after award to a successful offeror. Primary factor in determination to issue NTP shall be the Prime Contractor submission of, and the Government review and approval of both Payment and Performance Bonds, both of which are enforceable legal documents.
SECURITY REQUIREMENTS (GENERAL):
1. All personnel employed by the contractor in the performance of work, issued under this contract, or any representative of the contractor shall abide by all security instructions and directives of the Department of Veterans Affairs. Employees are responsible for safeguarding all government property provided for contractor use.
1. At the close for each work period, government facilities, equipment and materials shall be secured, lights, and all doors and window secured.
1. The contractor and, as applicable, subcontractor shall not employ persons for work on this contract if such employee is identified as a potential threat to the health, safety, security, general well-being or operational mission of the station/campus and its population, nor shall the contractor or subcontractor employ persons under this contract who have an outstanding criminal warrant as identified during background checks.
1. Contractors shall ensure their employees and those of their subcontracts have the proper credentials allowing them to work in the United States. Employees and subcontractors later found to be undocumented or illegal aliens will be remanded to the proper authorities.
1. Contractor Badge Policies: All requests for contractor ID badges will be submitted through the station Police/Security office.
1. Vehicle registration, proof of insurance and a valid driver’s license must be presented for all vehicles while operating on the station/campus. All vehicles entering the station/campus are subject to search. Any refusal or non-consent by an employee will result in termination of their access and immediate confiscation of their ID badge.
SYSTEM/POLICY UPDATES
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
2.1 52.204-7 SYSTEM FOR AWARD MANAGEMENT—REGISTRATION (DEVIATION) (NOV 2025)
The Offeror shall have an active Federal Government contracts registration in the System for Award Management (SAM) when submitting an offer or quotation in response to this solicitation and at the time of award. As part of the SAM registration process, the Government collects information, as described in paragraphs (b) through (d) of this provision, that is necessary to identify the Offeror and for the Offeror to be awarded Federal Government contracts. To register in SAM, go to https://www.sam.gov. Allow for processing time when registering in SAM. If the Offeror is not registered in SAM, it should register immediately after receiving this solicitation.
(a) Definitions. As used in this provision— Commercial and Government Entity (CAGE) code has the meaning provided in the clause at the Federal Acquisition Regulation (FAR) 52.204-13, System for Award Management—Maintenance, of this solicitation.
Electronic Funds Transfer (EFT) indicator means a bank account identifier to establish additional System for Award Management records for identifying alternative EFT accounts (see part 32) for the same entity.
Highest-level owner means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest-level owner.
Immediate owner means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees. There may be more than one immediate owner (e.g., joint ventures).
Predecessor means an entity whose assets were acquired by the offeror or another entity (most often through merger or acquisition) and whose affairs are now carried out by the offeror or the other entity under a new name.
Taxpayer identification number means the number required by the Internal Revenue Service (IRS) to be used by the offeror to report income tax and other returns. It may be either a Social Security Number or an Employer Identification Number.
Unique entity identifier (UEI) has the meaning provided in the clause at FAR 52.204-13, System for Award Management—Maintenance, of this solicitation.
(b) Identifiers. The Offeror shall obtain and provide the following identifying information:
(1) Unique entity identifier (UEI).
(i) The Offeror shall obtain a UEI to register in SAM. The Government will independently validate the existence and uniqueness of the Offeror before assigning a UEI to the Offeror. Go to https://www.sam.gov for instructions on obtaining a UEI.
(ii) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “Unique Entity Identifier” followed by the UEI that identifies the Offeror's name and address exactly as stated in the offer. The Offeror shall also enter its EFT indicator, if applicable.
(iii) The Contracting Officer will use the UEI to verify that the Offeror has an active Federal Government contracts registration in SAM.
(2) Taxpayer identification number (TIN).
(i) The Offeror shall provide its TIN or related information to comply with debt collection requirements of 31 U.S.C. 7701(c) and 3325(d); reporting requirements of 26 U.S.C. 6041, 6041A, and 6050M; and implementing regulations issued by the IRS. The Offeror shall consent for TIN validation; and
(3) Commercial and Government Entity (CAGE) code.
(i) The Offeror shall provide a CAGE code and legal business name (Do not use a “doing business as” name) for—
(A) Itself;
(B) Its immediate owner(s), if any;
(C) Its highest-level owner, if any; and
(D) Any predecessor(s), or predecessor of an Offeror’s predecessor, that held a federal contract or grant within the last three years.
(ii) If the Offeror is in the United States or its outlying areas and does not already have a CAGE code assigned, the DLA CAGE Branch will assign a CAGE code to the Offeror as a part of the SAM registration process. For information on obtaining a CAGE code go to https://cage.dla.mil/.
(iii) The Offeror shall get from any immediate and/or highest-level owner(s) their respective CAGE code(s) to provide the code(s) as part of the registration (FAR 52.204-7(b)(3)(i)).
(iv) If the Offeror is located outside of the United States or its outlying areas, and does not already have a CAGE code assigned, the Offeror may obtain a CAGE code as indicated in the following table.
| If the Offeror is… |
| Then… |
| Located in a country that is a member of the North Atlantic Treaty Organization (NATO) or a sponsored nation |
| Contact the appropriate National Codification Bureau (https://www.nato.int/structur/ac/135/about/contacts) |
| Located in a country that is not a member of NATO or a sponsored nation |
| Contact the NATO Support and Procurement Agency (NSPA) (https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx) |
(c) Representations and certifications.
(1) The following FAR solicitation provisions contain entity-level representations and certifications that the Offeror shall submit as part of their Federal Government contracts registration in SAM:
| Provision |
| Title |
| Date |
| 52.204-5 |
| Women-Owned Business (Other Than Small Business) |
| Oct 2014 |
| 52.209-2 |
| Prohibition on Contracting with Inverted Domestic Corporations—Representation |
| Nov 2015 |
| 52.209-5 |
| Certification Regarding Responsibility Matters |
| Aug 2020 |
| 52.209-11 |
| Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law |
| Feb 2016 |
| 52.219-1 |
| Small Business Program Representations |
| Feb 2024 |
| 52.219-1 Alt I |
| Small Business Program Representations, with its Alternate I |
| Feb 2024 |
| 52.219-1 Alt II |
| Small Business Program Representations, with its Alternate II |
| Mar 2023 |
| 52.226-2 |
| Historically Black College or University and Minority Institution Representation |
| Oct 2014 |
(2) By submitting its offer, the Offeror verifies that, as of the date of its offer, its representations and certifications posted electronically in SAM for the provisions listed in paragraph (c)(1) of this provision are current, accurate, and complete. The Offeror’s representations and certifications in SAM are hereby incorporated by reference into its offer.
(d) Other information. The Offeror shall provide more information on its business operations and type that is necessary to be considered for award of certain contracts and financial information necessary to receive payment under contracts.
(End of Provision)
2.2 52.216-1 TYPE OF CONTRACT (NOV 2025) (DEVIATION)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (NOV 2025) (DEVIATION) (a)(1) The offeror must notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror must request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror must request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or 500,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .