Price Breakdown Worksheet updated 8 13 2025.docx

DOCX document 24 KB Posted

Attached to
Z2DZ--ATS Replacements for Boiler Plant B3 B25 and T5 | 570-25-501 | Fresno VA
Solicitation number
36C26125R0068
Issued by

About this file

The document is a Price Breakdown Worksheet for Solicitation No. 36C26125R0068, detailing cost allocations for a VA medical center project involving Automated Transfer Switch (ATS) replacements. The worksheet breaks down costs across four divisions: General Requirements, Existing Conditions, Thermal and Moisture Protection, and Electrical, with separate columns for material, labor, equipment, and other expenses. The pricing template includes subtotals for overhead, profit, bonds, and insurance, with specific line items for ATS replacements in two buildings (ATS Building 2 Interior and ATS Building 22 Exterior).

The associated federal contract opportunity is a firm-fixed price construction requirement set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) in VISN 21, MACC GROUP 2. The project involves installing and replacing several Automated Transfer Switches at the Fresno VA Medical Center, with a 366-calendar day performance period. The procurement is being conducted by the Department of Veterans Affairs Veterans Health Administration, with award based solely on price. Eligible offerors must be verified in the SBA's Dynamic Small Business Search, and the project is located at VA Central California Health Care System in Fresno, California.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 36C26125R0068 Attachment - Price Breakdown Worksheet

DESCRIPTION
MATERIAL
LABOR
EQUIPMENT
OTHER
TOTAL

Division 01 -General Requirements

$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Division Total
$
$
$
$
$
Division 02 – Existing Conditions
MATERIAL
LABOR
EQUIPMENT
OTHER
TOTAL
$
$
$
$
$
$
$
$
$
$
Division Total
$
$
$
$
$
Division 07 – Thermal and Moisture Protection
MATERIAL
LABOR
EQUIPMENT
OTHER
TOTAL
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Division Total
$
$
$
$
$
Division 26 – Electrical
MATERIAL
LABOR
EQUIPMENT
OTHER
TOTAL
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Division Total
$
$
$
$
$
SUB TOTAL
$
$
$
$
$
Overhead
$
$
$
$
$
Profit
$
$
$
$
$
Bonds and Insurance
$
$
$
$
$

TOTAL COST FOR LINE ITEM 0001,

ATS Building 2 Interior - Serving MCC1 Only.

$
$
$
$
$

TOTAL COST FOR LINE ITEM 0002,

ATS Building 22 Exterior – Serving B3, B25 and T5 Only.

$
$
$
$
$
TOTAL PROPOSAL
$
$
$
$
$

NOTE: All other costs may be included as a separate item and must be specified in this breakdown. Please ensure a total price is provided for line items 0001 and 0002, along with the total proposal cost.

File details come from the government source that posted it. Updated .