S06 VA Response to RFIs 15-19 Solicitation No. 36C26125Q0949.pdf

PDF 288 KB Posted

Attached to
N045--36C26125Q0949 | Replace safety valves on 3 Boilers | FR
Solicitation number
36C26125Q0949
Issued by

About this file

This document contains Requests for Information (RFIs) for VA Solicitation No. 36C26125Q0949 for replacing safety valves on 3 boilers. The key RFIs address technical specifications and testing requirements for the safety valves. Specifically, RFI #15 seeks clarification on valve and discharge piping sizes, with the VA indicating that union fittings may require height adjustments and providing specific inlet/outlet measurements for two boilers. RFI #16 requests detailed testing procedures, with the VA specifying that valves must lift at no more than 3% over set pressure and reseat at no more than 6% over set pressure, with testing to be conducted using steam and visual confirmation.

Additional RFIs address project timeline and compliance issues. RFI #17 concerns the 30-calendar-day completion period, with the VA agreeing to allow reasonable extensions to accommodate manufacturer lead times. RFI #18 highlights that the originally selected 1.5" x 2.0" valves do not meet minimum capacity requirements, and the discharge piping must be replaced to ensure code compliance. The document includes a detailed checklist for steam safety valves on boilers, outlining requirements for installation, testing, and safety considerations. The VA will allow flexibility in meeting manufacturer lead times and ensuring proper valve and piping specifications.

View the file

Other files

File Type Posted
Attachment -VA NOTICE OF LIMITATIONS ON SUBCONTRACTING_CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION JAN 2023 DEVIATION.pdf PDF
36C26125Q0949_5.docx DOCX document
Attachment - Amended Combined Synopsis-Solicitation RFQ 36C26125Q0949 09-23-25.pdf PDF
Attachment - Amended Combined Synopsis-Solicitation RFQ 36C26125Q0949 10-02-25.pdf PDF
Attachment - Service Contract Act WD No. 2015-5609 07-06-2025.pdf PDF
Attachment - Amended Combined Synopsis - Solicitation RFQ 36C26125Q0949 10-22-25.pdf PDF
Attachment - RFQ 36C26125Q0949_1 revised 10-22-25.pdf PDF
Attachment - Amended Combined Synopsis-Solicitation RFQ 36C26125Q0949 10-09-25.pdf PDF
36C26125Q0949_4.docx DOCX document
S06 VA Response to RFIs Solicitation No. 36C26125Q0949.pdf PDF
Attachment - RFQ 36C26125Q0949_1.pdf PDF
Attachment - VA Response to RFIs Solicitation No. 36C26125Q0949.pdf PDF
Attachment - REQUEST FOR INFORMATION RFI FORM.docx DOCX document
36C26125Q0949_3.docx DOCX document
Attachment - Diagrams - T6611-1-1.pdf PDF
S04 Pre-Proposal Site Visit Sign In Sheet 09-26-25.pdf PDF
Attachment - VAAR 852.219-75 VA Notice of Limitations on Subcontracting JAN 2023 DEVIATION.pdf PDF
Attachment - Data Report - T6611-1-1.pdf PDF
Attachment -VHA Boiler and Associated Plant Safety Device Testing Manual 8th Edition.pdf PDF
S04 Pre-Proposal Site Visit Sign In Sheet 09-30-25.pdf PDF
36C26125Q0949_2.docx DOCX document
S02 RFQ 36C26125Q0949_1 draft.docx DOCX document
P07 Service Contract Act WD No. 2015-5609 07-06-2025.pdf PDF
36C26125Q0949.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Response to RFIs for Solicitation No. 36C26125Q0949

Replace Safety Valves On 3 Boilers

RFI #15 – The project specifications call for safety valves with a 2.5” flanged connection.

However, the existing discharge piping that these valves will connect to is only 2” in diameter.

Per code requirement that discharge piping must be the same size or larger than the valve outlet.

Could the VA please provide clarification on how to proceed? Should the specifications be revised to specify valves with a 2” outlet to match the existing piping, or is the intent to replace the existing 2” discharge piping with new 2.5” piping to maintain compliance?

VA Response:

-Both safety valves are union fittings, if none can be made to be union fittings and if we must change to flanged fittings, then the overall height will have to be changed as well.

-135 pounder has a 2” inlet with a 2 ¼” outlet going to a 3 ½” discharge line.

-140 pounder has a 2” inlet with a 2 ¾” outlet going to a 3 ½” discharge line.

RFI #16 – The project scope requires that each safety valve be tested by being lifted with steam pressure. To ensure this testing is performed correctly and consistently, can the VA please provide the detailed testing procedure? Such as:

• The required test pressure.

• The required duration for the valve to remain in the lifted position.

• The pass/fail criteria (e.g., reseat pressure, visual/audible confirmation).

• Any specific data sheets or reports that need to be completed and submitted.

VA Response:

The valves must lift at no more than 3% over set pressure.

Valves must reseat at no more than 6% over set pressure.

The pass/fail criteria include the lift pressure and reseat pressure. This is a visual confirmation.

Reports that need to be submitted for testing is the location of the inspection facility and confirmation that the test was conducted with steam. Testing medium must be conducted with steam not water.

Our guideline comes from VHA Boiler and Associated Plant Safety Device Testing Manual (Eighth Edition) snip-it provided.

RFI #17 – The solicitation requires completion of the project within 30 calendar days after receipt of order (ARO). Based on current market availability, the specified Kunkle safety relief valves and associated components have lead times of 30 days from the manufacturer or distributor.

Please confirm whether the VA will allow a reasonable extension of the completion period to accommodate verified manufacturer lead times.

VA Response: The VA will allow reasonable extension of the completion period to accommodate the lead times of verified manufacturer lead times.

RFI #18 - The 1.5” x 2.0” valves originally selected by the VA will not meet the minimum capacity requirements for the system. The correct valves for this application are 2” FLG x 2.5” flanged connections. Since the existing discharge piping from the valves to the drip pan elbows is 2”, it does not comply with code, which requires that the discharge vent piping be equal to or larger than the safety valve discharge connection. Therefore, the discharge piping must be replaced to accommodate the properly sized valves and ensure full code compliance and safe operation. Please advise.

VA Response: See response to RFI#16.

-----------------------------------------------END OF RFIs----------------------------------------------------

File details come from the government source that posted it. Updated .