Attachment - VA Response to RFIs Solicitation No. 36C26125Q0949.pdf
PDF 99 KB Posted
- Solicitation number
- 36C26125Q0949
About this file
This document is a VA Response to Requests for Information (RFIs) for Solicitation No. 36C26125Q0949 for replacing safety valves on 3 boilers. Key details include the VA's allowance for the superintendent to simultaneously fulfill roles of Site Safety and Health Officer (SSHO) and Quality Assurance/Quality Control (QA/QC), confirmation that tax should be included in proposals, and clarification on boiler shutdown procedures. The facility has 3 boilers and requires N+1 redundancy, with only one boiler available for valve installation at a time during regular business hours.
Additional critical information reveals the project is intended for fall/winter 2025, involves mechanical safety relief valves (SRVs) without alarm or lockout capabilities, and does not require piping modifications. The Building Automation System uses JCI software and is maintained by either JCI or Bedard Controls. The VA confirmed no assumed asbestos on piping to be removed and instructed contractors to disregard paragraphs D and E of the original Statement of Work regarding valve alarming and shutdown capabilities, as the specified valves are mechanical in nature.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Response to RFIs for Solicitation No. 36C26125Q0949
Replace Safety Valves On 3 Boilers
RFI #1 – Will the sign-in sheet from site visit be available in addendum?
VA Response: Yes. The sign-in sheet(s) will be made available in a solicitation amendment with the VA Responses to RFIs.
RFI #2 – Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?
VA Response: For this project VA will allow the superintendent to also fulfill the duties of
SSHO.
RFI #3 – If no to the question above, will the SSHO need to be full-time for this project?
VA Response: See response to RFI#2.
RFI #4 – Please clarify if a superintendent can be a dual hat to cover the requirements of
QA/QC?
VA Response: For this project VA will allow the superintendent to also fulfill the duties of
QA/QC.
RFI #5 – If no to the question above, will the QA/QC need to be full time for this project?
VA Response: See response to RFI#4
RFI #6 – Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?
VA Response: For this project VA will allow the superintendent to also fulfill the duties of QA/QC and SSHO.
RFI #7 – Please confirm if tax should be included in our proposal?
VA Response: Yes.
RFI #8 – Will shutdowns be required to be done during off hours or weekends?
VA Response: The facility has 3 boilers, there must be N+1 redundancy at all times. Only one boiler will be available for contractor to install Steam Pressure Relief Valve at any time during this work. Shutdown of the boiler for contractor install may take place during regular business hours.
RFI #9 – Please confirm if there is assumed asbestos on any piping that is to be removed?
VA Response: There is no assumed asbestos on any piping that is to be removed.
RFI #10 – Is there a particular vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System?
VA Response: These systems are JCI software and are currently maintained by either JCI or Bedard Controls.
RFI #11 – The SRV's indicated to be provided do not contain an alarm feature or have the ability to lock out the unit. They are mechanical only. Referring to the specifications of the mechanical safety valves and paragraph D and E of the SOW, we cannot provide alarming and shutting down of the unit as the specified valve does not have that capability. Please advise how you would like to proceed.
VA Response: Disregard paragraph D and E of the SOW. The SRV’s are mechanical in nature and do not provide alarming and shutting down of the unit.
RFI #12 – Will work take place during fall/winter of 2025?
VA Response: Intention is for work to take place in fall/winter of 2025.
RFI #13– Will this work take place during spring/summer of 2026 when the boiler plant is at reduced load?
VA Response: See response to RFI#12
RFI #14 - In regards to the discharge piping. We understand that the installation of the new valves will require piping modifications. These are not included in the statement of work and we wanted to bring to your attention that they are essential for the replacement of each valve on the 3 boilers. Please advise on how you would like to proceed.
VA Response: No modification to piping is required for the scope of work. Intent is to replace SRV only.
-----------------------------------------------END OF RFIs----------------------------------------------------