36C26118B0235-005.docx

DOCX document 33 KB Posted

Attached to
Emergency Department Safe Room| 662-18-1-6451-0005 | NRM Project #662-17-016
Solicitation number
36C26118B0235
Issued by

About this file

36C26118B0235 S02. 265100 Interior Lighting.docx

View the file

Other files

File Type Posted
36C26118C0065-000.docx DOCX document
36C26118B0235-00003000.docx DOCX document
36C26118B0235-00003001.docx DOCX document
36C26118B0235-00003002.pdf PDF
36C26118B0235-00002002.pdf PDF
36C26118B0235-00002004.pdf PDF
36C26118B0235-00002003.pdf PDF
36C26118B0235-00002001.pdf PDF
36C26118B0235-00002000.docx DOCX document
36C26118B0235-00001000.docx DOCX document
36C26118B0235-00001001.pdf PDF
36C26118B0235-00001002.pdf PDF
36C26118B0235-019.docx DOCX document
36C26118B0235-010.docx DOCX document
36C26118B0235-011.pdf PDF
36C26118B0235-017.pdf PDF
36C26118B0235-022.docx DOCX document
36C26118B0235-021.docx DOCX document
36C26118B0235-026.pdf PDF
36C26118B0235-025.docx DOCX document
36C26118B0235-004.doc DOC document
36C26118B0235-013.docx DOCX document
36C26118B0235-006.docx DOCX document
36C26118B0235-016.pdf PDF
36C26118B0235-012.pdf PDF
36C26118B0235-001.docx DOCX document
36C26118B0235-007.docx DOCX document
36C26118B0235-009.docx DOCX document
36C26118B0235-002.docx DOCX document
36C26118B0235-008.docx DOCX document
36C26118B0235-003.docx DOCX document
36C26118B0235-015.pdf PDF
36C26118B0235-023.docx DOCX document
36C26118B0235-020.docx DOCX document
36C26118B0235-014.pdf PDF
36C26118B0235-024.docx DOCX document
36C26118B0235-018.docx DOCX document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

08-01-14

SECTION 26 51 00

INTERIOR LIGHTING

PART 1 GENERAL

1.1 DESCRIPTION:

A. This section specifies the furnishing, installation, and connection of the interior lighting systems. The terms “lighting fixture,” “fixture,” and “luminaire” are used interchangeably.

1.2 RELATED WORK

A.Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: Requirements that apply to all sections of Division 26.
B.Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES: Low-voltage conductors.
C.Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS: Requirements for personnel safety and to provide a low impedance path to ground for possible ground fault currents.
D.Section 26 27 26, WIRING DEVICES: Wiring devices used for control of the lighting systems.

1.3 qualITY ASSURANCE A. Refer to Paragraph, QUALIFICATIONS (PRODUCTS AND SERVICES), in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.

1.4 SUBMITTALS

A.Submit three copies of the following in accordance with Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
1.Shop Drawings:
a.Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation.
b.Material and construction details, include information on housing and optics system.
c.Physical dimensions and description.
d.Wiring schematic and connection diagram.
e.Installation details.
f.Energy efficiency data.
g.Photometric data based on laboratory tests complying with IES Lighting Measurements testing and calculation guides.
h.Lamp data including lumen output (initial and mean), color rendition index (CRI), rated life (hours), and color temperature (degrees Kelvin).
i.Ballast data including ballast type, starting method, ambient temperature, ballast factor, sound rating, system watts, and total harmonic distortion (THD).
j.For LED lighting fixtures, submit US DOE LED Lighting Facts label, and IES L70 rated life.
2.Manuals:
a.Submit, simultaneously with the shop drawings, complete maintenance and operating manuals, including technical data sheets, wiring diagrams, and information for ordering replacement parts.
b.If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.
3.Certifications: Two weeks prior to final inspection, submit the following.
a.Certification by the Contractor that the interior lighting systems have been properly installed and tested.

1.5 APPLICABLE PUBLICATIONS

A.Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.
B.American National Standards Institute (ANSI)
C.American Society for Testing and Materials (ASTM)
D.Environmental Protection Agency (EPA):
40 CFR 261Identification and Listing of Hazardous Waste
E.Federal Communications Commission (FCC)
F.Illuminating Engineering Society (IES):
LM-79-08Electrical and Photometric Measurements of Solid-State Lighting Products
LM-80-08Measuring Lumen Maintenance of LED Light Sources
LM-82-12Characterization of LED Light Engines and LED Lamps for Electrical and Photometric Properties as a Function of Temperature
G.Institute of Electrical and Electronic Engineers (IEEE):
H.International Code Council (ICC):
I.National Fire Protection Association (NFPA):
70-11National Electrical Code (NEC)
101-12Life Safety Code
J.National Electrical Manufacturer's Association (NEMA):
C82.1-04Lamp Ballasts
SSL-1-10Electronic Drivers for LED Devices, Arrays, or Systems
K.Underwriters Laboratories, Inc. (UL):
496-08Lampholders
844-12Luminaires for Use in Hazardous (Classified) Locations
924-12Emergency Lighting and Power Equipment
1598-08Luminaires

8750-09.................Light Emitting Diode (LED) Light Sources for Use in Lighting Products

PART 2 PRODUCTS

2.1 LIGHTING FIXTURES

A.Shall be in accordance with NFPA, UL, as shown on drawings, and as specified.
B.Sheet Metal:
1.Shall be formed to prevent warping and sagging. Housing, trim and lens frame shall be true, straight (unless intentionally curved), and parallel to each other as designed.
2.Wireways and fittings shall be free of burrs and sharp edges, and shall accommodate internal and branch circuit wiring without damage to the wiring.
3.When installed, any exposed fixture housing surface, trim frame, door frame, and lens frame shall be free of light leaks.
4.Hinged door frames shall operate smoothly without binding. Latches shall function easily by finger action without the use of tools.
C.Ballasts and lamps shall be serviceable while the fixture is in its normally installed position. Ballasts shall not be mounted to removable reflectors or wireway covers unless so specified.
D.Recessed fixtures mounted in an insulated ceiling shall be listed for use in insulated ceilings.
E.Mechanical Safety: Lighting fixture closures (lens doors, trim frame, hinged housings, etc.) shall be retained in a secure manner by captive screws, chains, aircraft cable, captive hinges, or fasteners such that they cannot be accidentally dislodged during normal operation or routine maintenance.
E.Metal Finishes:
1.The manufacturer shall apply standard finish (unless otherwise specified) over a corrosion-resistant primer, after cleaning to free the metal surfaces of rust, grease, dirt and other deposits. Edges of pre-finished sheet metal exposed during forming, stamping or shearing processes shall be finished in a similar corrosion resistant manner to match the adjacent surface(s). Fixture finish shall be free of stains or evidence of rusting, blistering, or flaking, and shall be applied after fabrication.
2.Interior light reflecting finishes shall be white with not less than 85 percent reflectance’s, except where otherwise shown on the drawing.
F.Lighting fixtures shall have a specific means for grounding metallic wireways and housings to an equipment grounding conductor.

1. Integral Self-Test: Automatically initiates test of unit emergency operation at required intervals. Test failure is annunciated by an integral audible alarm and a flashing LED

2.4 EMERGENCY LIGHTING UNIT

A.Complete, self-contained unit with batteries, battery charger, one or more local or remote lamp heads with lamps, under-voltage relay, and test switch.
1.Integral Self-Test: Automatically initiates test of unit emergency operation at required intervals. Test failure is annunciated by an integral audible alarm and a flashing LED.
2.5led light fixtures
A.General:
1.LED light fixtures shall be in accordance with IES, NFPA, UL, as shown on the drawings, and as specified.
2.LED light fixtures shall be Reduction of Hazardous Substances (RoHS)-compliant.
3.LED drivers shall include the following features unless otherwise indicated:
a.Minimum efficiency: 85% at full load.
b.Minimum Operating Ambient Temperature: -20˚ C. (-4˚ F.)
c.Input Voltage: 120 - 277V (±10%) at 60 Hz.
d.Integral short circuit, open circuit, and overload protection.
e.Power Factor: ≥ 0.95.
f.Total Harmonic Distortion: ≤ 20%.
g.Comply with FCC 47 CFR Part 15.
4.LED modules shall include the following features unless otherwise indicated:
a.Comply with IES LM-79 and LM-80 requirements.
b.Minimum CRI 80 and color temperature 3000˚ K unless otherwise specified in LIGHTING FIXTURE SCHEDULE.
c.Minimum Rated Life: 50,000 hours per IES L70.
d.Light output lumens as indicated in the Keynote.

PART 3 EXECUTION

3.1 INSTALLATION

A.Installation shall be in accordance with the NEC, manufacturer's instructions, and as shown on the drawings or specified.
B.Align, mount, and level the lighting fixtures uniformly.
C.Lighting Fixture Supports:
1.Shall provide support for all of the fixtures. Supports may be anchored to channels of the ceiling construction, to the structural slab or to structural members within a partition, or above a suspended ceiling.
2.Shall support the lighting fixtures without causing the ceiling or partition to deflect.
D.Furnish and install the new lamps as specified for all lighting fixtures installed under this project, and for all existing lighting fixtures reused under this project.
E.The electrical and ceiling trades shall coordinate to ascertain that approved lighting fixtures are furnished in the proper sizes and installed with the proper devices (hangers, clips, trim frames, flanges, etc.), to match the ceiling system being installed.
F.Bond lighting fixtures to the grounding system as specified Per NEC Requirement.
H.At completion of project, replace all defective components of the lighting fixtures at no cost to the Government.

3.2 Acceptance Checks and Tests

A.Perform the following:
1.Visual Inspection:
a.Verify proper operation by operating the lighting controls.
b.Visually inspect for damage to fixtures, lenses, reflectors, diffusers, and louvers. Clean fixtures, lenses, reflectors, diffusers, and louvers that have accumulated dust, dirt, or fingerprints during construction.
2.Electrical tests:
a.Burn-in all lamps that require specific aging period to operate properly, prior to occupancy by Government. Burn-in period to be 40 hours minimum, unless specifically recommended otherwise by the lamp manufacturer. Burn-in dimmed fluorescent and compact fluorescent lamps for at least 100 hours at full voltage, unless specifically recommended otherwise by the lamp manufacturer. Replace any lamps and ballasts which fail during burn-in.

3.3 Follow-Up Verification

A. Upon completion of acceptance checks and tests, the Contractor shall show by demonstration in service that the lighting systems are in good operating condition and properly performing the intended function.

---END---