Attachment 9 - Official Geotechnical Subsurface Investigation.pdf
PDF 1 MB Posted
- Attached to
- Construct Campus Security Fence and Access Control - Construction Federal contract opportunity
- Solicitation number
- 36C26026R0042
About this file
This is a geotechnical subsurface investigation report prepared by TTL Associates, Inc. for Blue Trident, LLC regarding the proposed replacement of a campus security fence at Portland VA Medical Center–Vancouver Campus in Vancouver, Washington.
The investigation encompasses eight test borings (B-1 through B-8) conducted September 22-23, 2022, with samples analyzed for Standard Penetration Test (SPT) N-values, moisture content, pH, Atterberg Limits, and particle size distribution. Subsurface conditions consist predominantly of loose to medium dense granular soils including silty sand (SM), poorly graded sand (SP, SP-SM), and clayey sand with varying gravel content, with SPT N-values ranging from 5 to 18 blows per foot. Three borings encountered medium stiff to stiff sandy silt (ML) in the upper five feet. Groundwater was encountered only in Boring B-1 at 15 feet depth (Elevation 194±), suggesting normal groundwater levels exist below investigation depths. The site is characterized as IBC Site Class E "soft soil" based on weighted average N-value less than 15 blows per foot. Soil pH testing indicates neutral to slightly alkaline conditions (pH 6.8–7.4), presenting no significant corrosion risk.
Design recommendations include a net allowable bearing pressure of 2,000 psf for shallow spread foundations and precast concrete vehicle barrier supports, with minimum 12-inch embedment below finished grades. Post foundations are recommended with design (allowable) side resistance of 35 psf for vertical compression and 22 psf for uplift (without load tests; 55 psf and 32 psf respectively if load tests per ASTM D 1143 and D 3689 are performed). Lateral design parameters specify 120 pcf unit weight, 30-degree internal friction angle, and 25 pci soil modulus for granular soils. For pavement design, a subgrade CBR value of 7 percent is recommended for properly compacted subgrade, with flexible pavement minimum sections of 3 inches asphalt over 6 inches aggregate base for light duty and 4 inches asphalt over 8 inches base for heavy duty. Modulus of subgrade reaction (k) of 165 pci is recommended for rigid concrete pavement design. Construction recommendations emphasize detailed foundation excavation inspection by geotechnical engineer, proof rolling with vibratory equipment, removal of topsoil and unsuitable materials, and compaction of fill to not less than 100 percent of maximum dry density per ASTM D 698 (Standard Proctor).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 4 648-20-121 - 5-27-26.pdf | ||
| Attachment 8 - RFI - Project 648-20-121 - Const CampusSecurity Fence 1.pdf | ||
| Attachment 7 - REVISED PRICE COST SCHEDULE.pdf | ||
| Attachment 10 - 32 84 00 Planting Irrigation Specs - Project 648-20-121.pdf | ||
| Attachment 12 - Addendum 1 for Drawing 250122 - ELEC - Project 648-20-121.pdf | ||
| Attachment 13 - Revised SOW - Project 648-20-121.pdf | ||
| Attachment 11 - SUBMITTAL REGISTER -VA 01 33 23 - Project 648-20-121.pdf | ||
| Attachment 14 - Price Factor 3 - Evaluation change - Solicitation 36C26026R0042.pdf | ||
| Amendment 3 648-20-121.pdf | ||
| Amendment 2 648-20-121.pdf | ||
| Amendment 1 648-20-121.pdf | ||
| Attachment 6 - Geotech Report and Boring Logs - 648-20-121.pdf | ||
| Attachment 5- Wage Determination 1-2-26.pdf | ||
| Attachment 1- SOW 648-20-121 4-21-26.docx | DOCX document | |
| S02 36C26026R0042 SOL 648-20-121.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINAL REPORT (REV. 1)
GEOTECHNICAL SUBSURFACE INVESTIGATION
PROJECT 648-20-121 – PROPOSED CAMPUS SECURITY FENCE
PORTLAND VA MEDICAL CENTER – VANCOUVER CAMPUS
VANCOUVER, WASHINGTON
FOR
BLUE TRIDENT, LLC
900 WINSLOW WAY E, SUITE 130
BAINBRIDGE ISLAND, WASHINGTON 98110
SUBMITTED
MARCH 6, 2024
TTL PROJECT NO. 2213101
TTL ASSOCIATES, INC.
1915 NORTH 12TH STREET
TOLEDO, OHIO 43604
(419) 324-2222
(419) 321-6257 FAX
Blue Trident, LLC March 2024 TTL Project No. 2213101 Page i
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION
2.0 INVESTIGATIVE PROCEDURES
3.0 PROPOSED CONSTRUCTION
4.0 GENERAL SITE AND SUBSURFACE CONDITIONS
4.1 General Site Conditions
4.2 General Soil Conditions
4.3 Groundwater Conditions
5.0 DESIGN RECOMMENDATIONS
5.1 Shallow Spread Foundations
5.2 Post Foundations
5.2.1 Vertical Capacity
5.2.2 Lateral Capacity
5.3 Seismic Considerations
5.4 Corrosion Considerations
5.5 Subgrades
5.5.1 Existing Subgrade
5.5.2 Modified Subgrade
5.6 Flexible (Asphalt) Pavement
5.7 Rigid (Concrete) Pavement
5.8 Groundwater Control and Drainage
5.9 Excavations and Slopes
6.0 CONSTRUCTION RECOMMENDATIONS
6.1 Site and Subgrade Preparation
6.2 Fill
6.3 Foundation Excavations
7.0 QUALIFICATION OF RECOMMENDATIONS
PLATES
Plate 1.0 Site Location Map Plate 2.0 Test Boring Location Plan
FIGURES
Logs of Test Borings Legend Key Grain Size Distribution
TTL Project No. 2213101 Page 1
1.0 INTRODUCTION
This geotechnical subsurface investigation report has been prepared for the proposed replacement with a new campus security fence of the existing 6 feet high chain-link fence around the Portland VA Medical Center – Vancouver Campus, located at 1601 East 4th Plain Boulevard, in Vancouver, Washington. The general area of the project is shown on the attached Site Location Map (Plate 1.0).
This report summarizes our understanding of the proposed construction, describes the investigative and testing procedures, presents the findings, discusses our evaluations and conclusions, and provides our design and construction recommendations for fence support foundations. This report submittal also includes recommendations for subgrade modification and pavement design, as requested, should the fence construction require repair or replacement of sidewalks or pavements. Additionally, this revision of the final report incorporates recommendations for fence with vehicle barrier supports planned in the northwestern portion of the campus.
This study was performed in accordance with TTL Proposal No. 2213101, dated March 2, 2022 and was authorized with Blue Trident, LLC Addendum No. 001 to Subcontract No. 31- 18-0001, dated July 5, 2022. This revision has been prepared in accordance with TTL Change Order No. 1, dated August 21, 2023, and was authorized with Blue Trident Mod No. 001 to Addendum No. 001 to Subcontract No. 31-18-0001, dated February 18, 2024.
The purpose of this investigation was to evaluate the subsurface conditions and laboratory data relative to the design and construction of fence support foundations, as well as pavements and sidewalks, at the referenced location. This investigation included eight test borings, field and laboratory soil testing, and a geotechnical engineering evaluation of the test results.
This report includes:
• A description of the subsurface soil and groundwater conditions encountered in the borings.
• Design recommendations for fence post foundations, as well as pavements, related to the proposed development.
TTL Project No. 2213101 Page 2
• Recommendations concerning soil- and groundwater-related construction procedures such as site preparation (including subgrade modification for sidewalks and pavements), earthwork, foundation construction, and related field testing.
The scope of this investigation did not include an environmental evaluation of the site or subsurface conditions.
TTL Project No. 2213101 Page 3
2.0 INVESTIGATIVE PROCEDURES
This subsurface investigation included eight test borings, designated as B-1 through B-8, drilled on September 22 and 23, 2022. The borings were performed by Cascade under the direction of TTL. The borings were performed at approximate equal spacing adjacent to the existing chain link fence around the VA Medical Center campus. The test borings were located in the field by Cascade based on a proposed plan that was approved by Mr. Andrew S. Thornton of Portland VA Medical Center, Vancouver Campus on August 10, 2022. Ground surface elevations at the boring locations were estimated using Google Earth. The approximate locations of the borings are shown on the Test Boring Location Plan (Plate 2.0).
The test borings performed during this investigation were advanced with a GeoProbe® 3230DT utilizing 4-inch casing. All borings were terminated at depth 16½ feet below existing grade.
During borehole advancement, soil samples were collected at 2½-foot intervals to a depth of 10 feet and at 5-foot intervals thereafter. Split-spoon (SS) samples were obtained by the Standard Penetration Test (SPT) Method (ASTM D 1586), which consists of driving a 2-inch outside diameter split-barrel sampler into the soil with a 140-pound weight falling freely through a distance of 30 inches. The sampler was driven in three successive 6-inch increments with the number of blows per increment being recorded. The sum of the number of blows required to advance the sampler the second and third 6-inch increments is termed the Standard Penetration Resistance (N-value) and is presented on the Logs of Test Borings attached to this report. The samples were sealed in jars and shipped to our laboratory for further classification and testing.
All of the recovered samples of the subsoils were visually or manually classified in accordance with the Unified Soil Classification System (USCS) (ASTM D 2487 and D 2488). All of the recovered samples were also tested in our laboratory for moisture content (ASTM D 2216).
For corrosivity considerations, three selected samples were tested for pH (ASTM D 4972).
Atterberg Limits tests (ASTM D 4318) and particle size analyses (ASTM D 6913 and D 7928) were performed on samples from Borings B-1 (SS-1), B-3 (SS-1), and B-5 (SS-1).
Additionally, particle size analyses for granular soil samples were performed on samples from Borings B-6 (SS-4) and B-8 (SS-4) to determine soil classification properties. The results of these tests are presented on the Logs of Test Borings and Grain Size Distribution sheet attached to this report.
TTL Project No. 2213101 Page 4
Soil conditions encountered in the test borings are presented in the Logs of Test Borings, along with information related to sample data, SPT results, water conditions observed in the borings, and laboratory test data. It should be noted that these logs have been prepared on the basis of laboratory classification and testing as well as field logs of the encountered soils.
Experience indicates that the actual subsoil conditions at a site could vary from those generalized on the basis of test borings made at specific locations, especially at previously developed sites such as this site. Therefore, it is essential that a geotechnical engineer be retained to provide soil engineering services during the site preparation, excavation, and foundation phases of the proposed project. This is to observe compliance with the design concepts, specifications, and recommendations, and to allow design changes in the event subsurface conditions differ from those anticipated prior to the start of construction.
TTL Project No. 2213101 Page 5
3.0 PROPOSED CONSTRUCTION
The proposed construction consists of replacement with a new campus security fence of the existing 6 feet high chain-link fence around the Portland VA Medical Center – Vancouver Campus, located at 1601 East 4th Plain Boulevard, in Vancouver, Washington. The fence will be approximately 1.1 miles long (approximately 5,800 feet). A concrete mow strip along with two motorized vehicle gates and two personnel gates is included with the installation of this new security fence. Structural loads were not provided, but are assumed to be light in magnitude. If spread foundations are utilized for gate structures associated with the fence, maximum column loads are assumed to not exceed 40 kips. Smaller steel fence post type foundation loads are assumed to be on the order of 200 to 400 pounds, although uplift or lateral loads may govern embedment requirements.
In the northwestern portion of the campus, fence with concrete vehicle barrier supports is planned. Preliminary plans indicate the barrier will have an approximately 2½ feet wide base with minimum 6 inches embedment below surrounding final grades, supported on 4 inches minimum aggregate base. Depending on final design, additional embedment may be required to resist impact loads. The concrete barrier is indicated to extend 3 feet above grade. Maximum impact loads were indicated to be 6 kips.
It was requested that recommendations be provided for subgrade modification for sidewalks and pavements, as well as pavement design parameters, should fence construction necessitate repair or replacement of these “flatwork” items.
We have assumed that final grades will approximate existing grades present at the time of this investigation.
TTL Project No. 2213101 Page 6
4.0 GENERAL SITE AND SUBSURFACE CONDITIONS
4.1 General Site Conditions
The perimeter fence line of the VA Medical Center campus included grass areas and adjacent parking lots. Approximate ground surface elevations obtained from Google Earth for the borings locations varied from Elevs. 211± to 171±, with the higher elevations present in the north and the lowest elevations present in the southwest.
The borings were generally performed in grass areas and encountered surface materials consisting of topsoil, with thickness on the order of 3 inches. Borings B-3 and B-7 were performed in pavement areas and encountered approximately 6 inches of asphalt at each location. Distinct surface cover was not present at the location of Boring B-6.
4.2 General Soil Conditions
The subsoils encountered to the depth of termination of 16½ feet below existing grade consisted of predominantly loose to medium dense granular soils. The granular soils consisted of silty sand (SM), poorly graded sand with varying amounts of silt (SP and SP-SM), as well as clayey sand, each with varying amounts of gravel. SPT N-values generally ranged from 5 to 18 blows per foot (bpf). Moisture contents ranged from approximately 7 to 16 percent.
Within the upper 5 feet of Borings B-3, B-6, and B-7, predominantly medium stiff to stiff sandy silt (ML) with trace gravel was encountered. The tested sample from Boring B-3 contained 51 percent silt and clay fraction, just above the threshold of 50 percent between silty sand (SM) and sandy silt (ML) designation. As such, the sandy silt soils may be difficult to distinguish from the silty sand soils at the site. In any case, each soil type is generally suitable for support of the foundations associated with the proposed new campus security fence, as well as for subgrade support for sidewalks and pavements that may be repaired or replaced as part of the fence construction process. Within the sandy silt zones, SPT N-values of 5 bpf, 14 bpf, and 23 bpf were determined. An unconfined compressive strength of 2,000 pounds per square foot (psf) was determined for the lone intact sample, which was obtained from Boring B-3.
Moisture contents ranged from 10 to 17 percent.
Additional descriptions of the stratigraphy encountered in the borings are presented on the Logs of Test Borings.
TTL Project No. 2213101 Page 7
4.3 Groundwater Conditions
Groundwater was initially encountered during drilling in only Boring B-1 at a depth of 15 feet below existing grade (Elev. 194±). Groundwater was not encountered in the remaining borings and was not observed upon completion of drilling in any of the borings. It should be noted that each of the borings was performed and backfilled within the same day, and stabilized water levels may not have occurred over this limited period. Instrumentation was not installed to observe long-term groundwater levels.
Based on the limited data available, such as the soil characteristics and the groundwater conditions encountered in the borings, it is our opinion that the “normal” groundwater level may be encountered at depths below the extents of the borings performed for this investigation.
However, this investigation did not include research of possible hydrological influences at the project site. It should be noted that groundwater elevations can fluctuate with seasonal and climatic influences. Therefore, the groundwater conditions may vary at different times of the year from those encountered during this investigation.
TTL Project No. 2213101 Page 8
5.0 DESIGN RECOMMENDATIONS
The following conclusions and recommendations are based on our understanding of the proposed construction and on the data obtained during the field investigation. If the project information or location as outlined is incorrect or should change significantly, a review of these recommendations should be made by TTL. These recommendations are subject to the satisfactory completion of the recommended site and subgrade preparation and fill placement operations described in Section 6.0, “Construction Recommendations”.
5.1 Shallow Spread Foundations and Vehicle Barrier Supports
This section includes campus security fence foundation recommendations considering shallow spread foundations. We presume that spread foundations could be utilized particularly for gate structures as part of the fence installation. Additionally, vehicle barrier supports will be precast concrete “strip foundations.” For fence-post type foundations, recommendations are provided in the following section.
It is recommended that spread foundations bear at or below a minimum depth of 12 inches below finished grades. We understand that concrete vehicle barriers may be precast structures not intended to extend to a depth of 12 inches below grade. These structures may be subject to movement if frost action were to occur. On the other hand, local code or need for resistance to impact loads may require these structures extend to depths of 12 inches or greater below final grades.
Based on the results of the field and laboratory testing for the borings performed for this investigation, spread foundation excavations are anticipated to encounter predominantly loose to medium dense native granular soils, as well as zones of predominantly medium stiff to stiff native cohesive soils. These soils are considered generally suitable for the foundations, although in-place densification of loose granular soils will be required at the bottom of the footing excavation. Where loose granular soils are present at the bearing elevation, they should be re-compacted in-place using a backhoe-mounted vibratory compactor (hoe-pac) or similar equipment, or removed and replaced with new granular engineered fill.
Suitable compaction/bearing of native granular foundation soils can be verified as:
• Exhibiting a compacted (in-situ) dry density of at least 100 percent of the maximum dry density determined by Standard Proctor (ASTM D 698) laboratory compaction, TTL Project No. 2213101 Page 9
• A dynamic cone penetrometer (DCP) reading of at least 8 blows per increment (average over three increments), or
• Other methods to demonstrate an equivalent SPT N-value of 10 bpf or greater.
Following the satisfactory completion of the site preparation and footing excavation inspections outlined in this report, the proposed structure may be supported on a conventional shallow foundation system. For individual (square) foundations as well as vehicle barrier (strip) “foundations”, we recommend a net allowable bearing pressure of 2,000 pounds per square foot (psf), with a maximum bearing pressure at the toe of 2,665 psf due to overturning (where applicable, such as with wind load and vehicle impact considerations). In using a net allowable soil pressure, the weight of the footings or backfill over the footings need not be included in the structural loads for dimensioning footings. The bearing materials should be field-verified as being native granular soils meeting the compaction/ bearing criteria presented above, native cohesive soils with an unconfined compressive strength of at least 2,000 psf, or properly placed and compacted new engineered fill.
A friction factor of 0.35 may be utilized along the base of the footing to calculate sliding resistance. A passive earth pressure coefficient (kp) of 3.0 may be utilized for the portion of the footing that is below the minimum required embedment depth of 12 inches below final grades. If the design includes passive pressure above this elevation, the contribution of passive resistance to sliding or overturning stability should be evaluated in conjunction with the design factor of safety (FoS). These values are based on footings in intimate contact with at least medium dense granular soils. It should be noted that some wall/foundation movement or horizontal displacement is needed to mobilize the full passive pressure of the soil. Because of this consideration, some design methods incorporate a higher required factor of safety (e.g., FoS = 2.0) when using passive pressure contribution to stability, as compared to sliding resistance on the base only (typically, FoS = 1.5).
Due to the encountered very loose to loose granular soils as well as the existing site development, it is particularly important that a detailed foundation excavation inspection be completed by a geotechnical engineer or qualified representative. Inspection should be performed to verify that the exposed soil conditions at the bearing elevations are consistent with the subsurface conditions encountered in the test borings, loose granular soils have been suitably modified in-place, and that the conditions are suitable for foundation bearing.
Additionally, the presence of our engineer will help facilitate the timely remediation of unsuitable soil conditions. If the results of DCP, hand penetrometer, or other strength tests indicate the exposed soil conditions are not suitable for the design bearing pressure, it may be
TTL Project No. 2213101 Page 10 necessary to increase the footing size to accommodate the lower bearing strengths or to over-excavate and backfill with engineered fill or flowable fill.
If loose native granular soils are encountered that cannot be suitably re-compacted in-place, or if other deleterious materials are encountered, over-excavation should extend through these materials to suitable bearing soils. The base of the over-excavation should be widened one foot for every foot of depth below the planned bearing depth, centered along the footing. The over-excavated areas should be backfilled with dense-graded aggregate, placed in controlled lifts, and compacted to not less than 100 percent of the maximum dry density as determined by ASTM D 698 (Standard Proctor).
Alternatively, the over-excavated areas could be backfilled with lean concrete having a minimum compressive strength of 1,500 pounds per square inch (psi) or other flowable controlled-density fill having a minimum compressive strength of 300 psi. If foundations will be placed at the base of the over-excavation or the lean concrete fill option will be utilized, widening the footing over-excavation will not be required. If the controlled-density fill option is utilized, the footing over-excavation shall be widened as discussed above. If foundations are designed using sliding resistance, lean concrete or controlled density fill should not be used for backfill after over-excavation.
All exterior footings and footings in unheated areas should be constructed at a minimum depth of 12 inches below finished exterior grades. Column (square) footings should be at least 30 inches wide and strip footings should be at least 18 inches wide, regardless of sizing based on design loads and the recommended allowable bearing pressure. It should be noted that use of trench footings (i.e., placement of foundation concrete without forming) is not expected to be feasible due to the granular nature of the bearing soils, along with the need for in-place densification. Forming of footings and backfilling around CMU or poured foundation walls should be anticipated.
Utilizing the above allowable bearing pressure and proper foundation inspection techniques, the total settlement associated with the structure should not exceed 1 inch and differential settlement should not exceed ¾ inch.
5.2 Post Foundations
This section includes campus security fence foundation recommendations considering steel fence-post type foundations. If shallow spread foundations will be utilized for this project, recommendations are provided in the preceding section.
TTL Project No. 2213101 Page 11
5.2.1 Vertical Capacity
The steel fence post-type foundations are anticipated to bear in predominantly loose to medium dense native granular soils. Although zones of sandy silt were encountered in the upper 5 feet of three borings, vertical capacity design parameters based on the granular soils would dictate design. Additionally, a tested sample of the encountered sandy silt soils contained only 51 percent silt and clay fraction. As such, the vertical capacity provided by these soils is anticipated to be similar to the capacity provided by the silty sand soils at the site.
Vertical downward load and uplift load may be resisted by the side resistance on the embedded pipe. However, due to freeze-thaw effects and moisture content changes in the upper profile, effective side resistance may not be reliable in the upper 12 inches. Therefore, we recommend that side resistance be considered only for the embedment zone below a depth of 12 inches below final grade.
It should be noted that a minimum factor of safety (FoS) of 3 is recommended when calculating allowable capacity for pile-type foundations due to the variability of soil strength and installation methods, without performance of load tests. Based on this FoS, we recommend design (allowable) side resistance of 35 pounds per square foot (psf) for vertical compression and 22 psf for vertical uplift considerations.
A FoS of 2 may be utilized for design if load tests are performed. Load tests should be performed in accordance with ASTM D 1143, “Standard Test Method for Piles Under Static Axial Compressive Load” and ASTM D 3689, “Standard Test Method Individual Piles Under Static Axial Tensile Load.” Based on utilization of load tests, and a FoS of 2 applied to calculated ultimate values, we recommend design (allowable) side resistance of 55 psf for vertical compression and 32 psf for vertical uplift considerations.
5.2.2 Lateral Capacity
For lateral load-deflection evaluations using software, such as LPILE, recommended design parameters are summarized in the following table based on the conditions encountered in the borings.
TTL Project No. 2213101 Page 12
Table 5.2.2.A. Subsurface Conditions and Recommended Lateral Load-Deflection Parameters
General Condition
Average Depth (feet)
Generalized Layer Description
Approximate Total Unit
Weight (pcf)
Average Internal Angle of Friction, (degrees)
Soil-Modulus Parameter, k
(pci)
0 to 16½ Loose to Medium Dense Granular Soils 120 30 25
In addition to lateral load-deflection evaluation using the conditions presented in Table.
5.2.2.A, for steel post foundations in the areas of Borings B-3, B-6, and B-7, consideration should also be given to the upper profile sandy silt soils in these three borings using the design values in the following table. In these areas, design should be based on the more conservative result modeled by the conditions in Tables 5.2.2.A and 5.2.2.B.
Table 5.2.2.B. Subsurface Conditions and Recommended Lateral Load-Deflection Parameters Sandy Silt over Silty Sand Condition (B-3, B-6, and B-7)
Average Depth (feet)
Generalized Layer Description
Approximate Total Unit
Weight (pcf)
Average Undrained
Shear Strength, Su
(psf)
Strain at 50%
Maximum Stress, 50
Average Internal Angle of
Friction, (degrees)
Soil- Modulus
Parameter, k (pci)
0 to 5 Medium Stiff to Stiff Cohesive Soils 120 1,100 0.007 - -
5 to 16½ Loose to Medium Dense Granular Soils 120 - - 30 25
5.3 Seismic Considerations
We have reviewed seismic design parameters in accordance with International Building Code (IBC) criteria. It should be noted that the IBC seismic site characterization is based on the upper 100 feet of the geologic profile and the borings performed for this investigation extended only to a maximum depth of 16½ feet below existing grade. Therefore, our analysis is limited to characterization based on the encountered overburden soil profile only.
Based on IBC Section 1613.3.2, which references ASCE 7-10, using the N-method, the weighted average N-value for the profile was calculated to be less than 15 blows per foot (bpf).
Therefore, the site can be characterized as Site Class E “soft soil” in accordance with ASCE 7-10 Table 20.3-1.
If a Site Class E designation will be restrictive to structural design, it may be prudent to perform deeper SPT borings for seismic site class evaluations, to determine if a better site class designation is appropriate. However, there is no guarantee that such testing would yield a more favorable site class designation.
TTL Project No. 2213101 Page 13
An alternate method to evaluate seismic site class incorporates shear wave velocity.
Development of a shear wave velocity profile is typically performed in conjunction with down-hole or cross-hole seismic testing, which would require additional boreholes and specialized testing equipment, cone penetration testing (CPT) using a CPT rig, or Multi-channel Analysis of Surface Waves (MASW) testing. It should be noted that, like the deeper SPT borings, there is no guarantee that shear wave velocity testing would yield a more favorable site class designation.
5.4 Corrosion Considerations
Soil samples from Borings B-2, B-4, B-6, and B-8 were tested for pH. The pH results are summarized as follows:
Table 5.4. Corrosion Considerations Test Results Boring No. (Sample No.) Soil Type pH
B-2 (SS-4) Poorly Graded Sand (SP) 6.8 B-4 (SS-2) Silty Sand (SM) 7.2 B-6 (SS-1) Sandy Silt (ML) 7.4 B-8 (SS-1) Poorly Graded Sand w/Silt (SP-SM) 6.9
This range of pH is characterized as neutral to slightly alkaline soil reaction by the USDA Soil Conservation Service. Typically, soils with a pH range between 5 and 9 are not considered to represent a significant corrosion risk to buried structural concrete or underground utilities.
Therefore, we do not expect that these soils will represent a significant corrosion risk to underground construction, although this assessment is based on limited data.
5.5 Subgrades
Subgrade preparation recommendations are being provided should sidewalks or pavements require repair or replacement as part of the fence construction project.
5.5.1 Existing Subgrade
The subgrades that would result upon the satisfactory completion of the site preparation as described in Section 6.0 of this report are considered generally acceptable for support of the proposed sidewalks and pavements. Based on field and laboratory data developed during this investigation, the subgrade soils predominantly consist of granular soils with varying amounts of silt, as well as some zones of sandy silt soils. Laboratory analyses for selected subgrade soil samples, as well as visual descriptions of the upper profile, indicate that the subgrade soils may
TTL Project No. 2213101 Page 14 be generally classified in the Group A-1 or A-2 series, or as Group A-4 in accordance with the AASHTO system of soil classification. These soils are considered fair as subgrade materials.
At the time of this investigation, the moisture contents in the uppermost recovered sample from the borings generally ranged from 10 to 20 percent. These moisture contents are estimated to vary from slightly below to somewhat above the expected optimum moisture content for these soils. Therefore, remedial action should be expected to be required to adjust the moisture contents of the existing materials and achieve proper compaction of the subgrade. Remedial action should be anticipated due to the very loose to loose compactness of the near-surface granular subgrade soils.
5.5.2 Modified Subgrade
If soils are dry of optimum, water should be uniformly mixed into the subgrade. If soils wet of optimum are encountered, lowering the moisture content by scarification and aeration (discing and exposure to sun and wind) may be required. However, this may not be feasible if construction occurs during wet seasonal conditions. Very moist to wet soils will “pump” under the operation of heavy equipment, resulting in deep rutting and perhaps rendering the operation of grading and paving equipment difficult or impossible.
Therefore, other methods of subgrade modification may be required in areas of high moisture content. Modification may be achieved by undercutting and replacement with granular subbase (possibly in combination with a geotextile separation layer or geogrid reinforcement), mixing stone into the subgrade, or treating the subgrade with cement. The method of subgrade modification should be determined at the time of construction (See Section 6.1, “Construction Recommendations - Site and Subgrade Preparation”).
5.6 Flexible (Asphalt) Pavement
Based on the results of the gradation and plasticity analysis for the tested subgrade soil samples, as well as visual classification of the recovered subgrade soil samples, we recommend a subgrade CBR value of 7 percent for the Group A-4 or better subgrade soils. This CBR value is based on subgrade compacted to at least 100 percent of the maximum dry density as determined by ASTM D 698 (Standard Proctor) or verified as stable through proof rolling.
It should be noted that we are not privy to the design traffic loads or intended design life. The subgrade support recommendations indicated herein should be reviewed by the site engineer in conjunction with the design traffic criteria to determine the required pavement sections. In
TTL Project No. 2213101 Page 15 any case, we recommend the light-duty pavement cross-section consist of at least 3 inches of asphalt underlain by 6 inches of aggregate base for even the lightest-duty pavements based on our experience regarding environmental exposure and reasonable serviceability. For the same reason, we recommend the heavy-duty pavement cross-section consist of at least 4 inches of asphalt underlain by 8 inches of aggregate base.
It should be noted that two borings were performed in existing pavement areas. The encountered asphalt thickness in each of these two borings was approximately 6 inches.
However, no discernable aggregate base layer was encountered underlying the asphalt. Due to the silty condition of the subgrade soils, we recommend use of clean aggregate base be provided underlying asphalt pavements.
All paving operations should conform to the State of Washington Department of Transportation specifications. The pavement and subgrade preparation procedures outlined in this report should result in a reasonably workable and satisfactory pavement. It should be recognized, however, that all flexible pavements need repairs or overlays from time to time as a result of progressive yielding under repeated traffic loads for a prolonged period of time, as well as exposure to freeze-thaw conditions.
5.7 Rigid (Concrete) Pavement
For properly prepared subgrade soils, a modulus of subgrade reaction (k) of 165 pounds per cubic inch (pci) may be used for rigid pavement design. It is presumed that pavement type will be utilized to match existing pavements affected by the fence construction. However, consideration should be given to use of concrete pavement section in the loading-unloading areas, areas of repetitive turning, site exit and entrance aprons, and trash enclosure areas (including where the truck parks while servicing the container). This section should consist of a minimum of 6 inches of reinforced, air-entrained concrete with a minimum compressive strength of 3,500 pounds per square inch (psi) underlain by a minimum of 6 inches of a dense-graded aggregate base. The pavement section should be supported on a subgrade compacted to not less than 100 percent of the maximum dry density as determined by ASTM D 698 (Standard Proctor) or verified as stable through proof rolling. All paving operations should conform to the State of Washington Department of Transportation specifications.
5.8 Groundwater Control and Drainage
As stated previously, groundwater was initially encountered during drilling in only Boring B- 1 at a depth of 15 feet below existing grade (Elev. 194±). Groundwater was not encountered
TTL Project No. 2213101 Page 16 in the remaining borings and was not observed upon completion of drilling in any of the borings. Based on the limited data available, such as the soil characteristics and the groundwater conditions encountered in the borings, it is our opinion that the “normal” groundwater level may be encountered at depths below the extents of the borings performed for this investigation.
It is our experience that adequate control of groundwater seepage or surface water run-off into shallow excavations should be achievable by minor dewatering systems, such as pumping from prepared sumps. Although not anticipated to be required, if deeper excavations in granular soils were to extend below the groundwater table, installation of well points would likely be required in addition to pumping from prepared sumps. The type of dewatering system utilized will depend on construction practices, soil conditions encountered in the foundation excavations, seasonal conditions, and the depth of excavation. Additionally, the contractor will need to exercise diligence to control seepage and runoff to maintain a stable subgrade.
In the event excessive seepage is encountered during construction, TTL may be notified to evaluate whether other dewatering methods are required.
5.9 Excavations and Slopes
The sides of temporary excavations for foundations, utility installations, and other construction should be adequately sloped to provide stable sides and safe working conditions. Otherwise, the excavation must be properly braced against lateral movements. In any case, applicable Occupational Safety and Health Administration (OSHA) safety standards must be followed.
The soils encountered during this investigation, within the anticipated depths of excavation, consist of the following OSHA Type soils:
• OSHA Type A soils (cohesive soils with unconfined compressive strengths of 3,000 pounds per square foot (psf) or greater),
• OSHA Type B soils (cohesive soils with unconfined compressive strengths greater than 1,000 psf but less than 3,000 psf), and
• OSHA Type C soils (granular soils).
For temporary excavations in Type A, B, and C soils, side slopes must be no steeper than ¾ horizontal to 1 vertical (¾H:1V), 1H:1V, and 1½H:1V, respectively. For situations where a higher strength soil is underlain by a lower strength soil and the excavation extends into the lower strength soil, the slope of the entire excavation is governed by that required for the lower
TTL Project No. 2213101 Page 17 strength soil. In all cases, flatter slopes may be required if lower strength soils or adverse seepage conditions are encountered during construction.
For permanent excavation slopes, we recommend that grades be no steeper than 3H:1V without a more extensive geotechnical evaluation of the proposed construction plans and site conditions.
TTL Project No. 2213101 Page 18
6.0 CONSTRUCTION RECOMMENDATIONS
6.1 Site and Subgrade Preparation
Prior to proceeding with construction operations, all topsoil, root mat, vegetation, pavements, and other deleterious non-soil materials should be removed from the proposed construction areas. Suitable topsoil may be stockpiled for later use in landscaped areas. It is important to note that topsoil thicknesses referenced in the borings may vary across the site. Typically, soils with more than 5 percent organics are not recommended as subgrade soils in structure areas, but dark colored soils having the appearance of topsoil with only trace “root hairs” of 5 percent or less may not necessarily require stripping. For these “transitional” soils, the actual moisture content and subgrade stability under proof-rolling operations is more critical than the color in determination of the amount of stripping or subgrade undercut. The actual amount of required stripping should be determined in the field by a geotechnical engineer or qualified representative.
Upon completion of stripping and clearing, the areas intended to support new fill, foundations, and pavements should be carefully inspected by a geotechnical engineer. In general, proof rolling/compaction of the subgrade soils should be performed utilizing a vibratory smooth drum roller. However, for particularly silty granular soils and sandy silt soils, proof rolling verification may be performed utilizing a 20- to 30-ton loaded truck or other pneumatic-tired vehicle of similar size and weight. The truck or roller should make a minimum of two passes in each of two perpendicular directions covering the proposed development area, with additional passes as necessary to achieve required compaction and/or subgrade stabilization.
The purpose of proof rolling the silty/clayey granular soils and sandy silt soils is to locate any weak, soft, or excessively wet soils that may be present at the time of construction. The purpose of vibratory compaction for the less silty/clayey granular soils is to densify zones of loose materials that are encountered in the upper portion of the soil profile, thereby providing more uniform subgrade support. We recommend a roller with a minimum dead weight on the drums of 8 tons, vibrating at 30 Hz or greater, and traveling at speeds not exceeding approximately 4 feet per second (about 3 miles per hour). However, within 10 feet of existing structures, compaction by “static” methods or removal and replacement with new engineered fill would be required to avoid potentially compacting bearing materials and inducing settlement for those structures. These operational criteria should provide sufficient dynamic compaction energy to alleviate loose soil conditions within the zone of influence for subgrade support.
TTL Project No. 2213101 Page 19
Any unsuitable materials observed during the inspection and proof-rolling operations should be undercut and replaced with compacted fill or stabilized in place utilizing conventional remedial measures such as discing, aeration, and recompaction. Remedial action should be anticipated based on the encountered very loose to loose granular subgrade soils.
Once the site has been proof rolled, inspected, and stabilized, the proof-rolled or inspected subgrades should not be exposed to wet conditions. It should be recognized that during periods of wet weather, the silty/clayey soils that will be exposed at design subgrades will tend to pond water for short periods of time, with the potential to deteriorate the prepared subgrade.
The results of the inspection and proof-rolling operations will be partially dependent on construction operations, the moisture content of the soil, and the weather conditions prevalent at the time. If pumping or rutting is encountered and difficulty is experienced in the operation of construction equipment, TTL should be notified in order to determine which method of subgrade modification may be best suited for the conditions encountered. Should such conditions be experienced, we may recommend that a small test area be used to determine the necessary depth of undercutting and stone replacement or other remedial action necessary to achieve a stable subgrade condition.
6.2 Fill
Material for engineered fill or backfill required to achieve design grades may consist of any non-organic soils having a maximum dry density as determined by the Standard Proctor (ASTM D 698) of 90 pounds per cubic foot (pcf) or greater. To preserve the design CBR value and subgrade modulus (k-value) recommended in this report, new engineered fill placed within at least 12 inches of top of subgrade should consist of AASHTO A-4 or better soils. On-site soils may be re-used as engineered fill materials provided that they contain trace or less organic matter and debris, and are free of excessive moisture, and rock or stone fragments larger than 3 inches in diameter. Depending on seasonal conditions, the on-site soils may be wet of optimum and may require scarification and aeration to achieve satisfactory compaction. If the construction schedule does not allow for scarification and aeration activities, it may be more practical or economical to utilize imported granular fill.
Fill should be placed in uniform layers no more than 8 inches thick (loose measure) and adequately keyed into stripped and scarified soils. All fill within the structure areas should be compacted to not less than 100 percent of the maximum dry density as determined by ASTM D 698 (Standard Proctor).
TTL Project No. 2213101 Page 20
The upper soil profile at the site consists of native granular soils, as well as native sandy silt soils. The contractor should be prepared to use a sheepsfoot roller to provide effective compaction of the sandy silt soils, as well as particularly silty and clayey granular soils. The contractor should be prepared to use a vibratory, smooth-drum roller to provide effective compaction of the silty and clayey granular soils that do not compact well with a sheepsfoot roller, for granular soils containing less silt and clay fraction (SP or SP/SM), as well as for new granular engineered fill. In narrow utility or footing excavations, the on-site cohesive soils may be difficult to compact; therefore, a clean granular material may be required in these areas.
Scarified subgrade soils and all fill material should be within 3 percent of the optimum moisture content to facilitate compaction. Furthermore, fill material should not be frozen or placed on a frozen base. It is recommended that all earthwork and site preparation activities be conducted under adequate specifications and properly monitored in the field by a qualified geotechnical testing firm.
6.3 Foundation Excavations
As mentioned in Section 5.1, foundations used to support the structure should have a detailed footing inspection performed for each foundation. A geotechnical engineer or qualified representative should perform these inspections to verify that the exposed materials are similar to those encountered in the borings, loose granular soils have been suitably modified in-place, and that engineered fill has been properly placed and compacted such that it is capable of supporting the design bearing pressure.
We recommend that the foundation excavations be concreted as soon as practical after they are excavated and that water not be allowed to pond in any excavation. If it is necessary to leave the bearing surface open for any extended period of time, we recommend that a thin mat of lean concrete be placed over the bottom of the excavation to reduce damage to the surface from weather or construction. Foundation concrete should not be placed on frozen or saturated subgrade.
Additional foundation subgrade inspection and preparation recommendations are provided in Section 5.1.
TTL Project No. 2213101 Page 21
7.0 QUALIFICATION OF RECOMMENDATIONS
Our evaluation of foundation and pavement design and construction conditions has been based on our understanding of the site and project information and the data obtained during our field investigation. The general subsurface conditions were based on interpretation of the subsurface data at specific boring locations. Regardless of the thoroughness of a subsurface investigation, there is the possibility that conditions between borings will differ from those at the boring locations, that conditions are not as anticipated by the designers, or that the construction process has altered the soil conditions. The potential for differing conditions is increased at previously developed sites. Therefore, experienced geotechnical engineers should observe earthwork and foundation construction to confirm that the conditions anticipated in design are noted. Otherwise, TTL assumes no responsibility for construction compliance with the design concepts, specifications, or recommendations.
The design recommendations in this report have been developed on the basis of the previously described project characteristics and subsurface conditions. If project criteria or locations change, a qualified geotechnical engineer should be permitted to determine whether the recommendations must be modified. The findings of such a review will be presented in a supplemental report.
The nature and extent of variations between the borings may not become evident until the course of construction. If such variations are encountered, it will be necessary to reevaluate the recommendations of this report after on-site observations of the conditions.
Our professional services have been performed, our findings derived, and our recommendations prepared in accordance with generally accepted geotechnical engineering principles and practices. This warranty is in lieu of all other warranties either expressed or implied. TTL is not responsible for the conclusions, opinions, or recommendations of others based on this data.
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
REVISED
AutoCAD SHX Text
JOB NO.
AutoCAD SHX Text
DRAWING NUMBER
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
CHECKED
AutoCAD SHX Text
PREPARED FOR
AutoCAD SHX Text
AutoCAD SHX Text 2,000
AutoCAD SHX Text 4,000
AutoCAD SHX Text
APPROXIMATE SCALE - FEET
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
PROPOSED CAMPUS SECURITY FENCE
AutoCAD SHX Text
PORTLAND VA MEDICAL CENTER - VANCOUVER CAMPUS
AutoCAD SHX Text
VANCOUVER, WASHINGTON
AutoCAD SHX Text
BLUE TRIDENT, LLC
AutoCAD SHX Text
BAINBRIDGE ISLAND, WASHINGTON
AutoCAD SHX Text 2213101-01G
AutoCAD SHX Text
TRR/10-19-22
AutoCAD SHX Text 2213101
AutoCAD SHX Text
CPI/10-24-22
AutoCAD SHX Text
SITE LOCATION MAP
AutoCAD SHX Text
PLATE 1.0
AutoCAD SHX Text
APPROXIMATE SITE LOCATION
AutoCAD SHX Text
SITE LOCATION
COLUMBIA RIVER
DRAWN
AutoCAD SHX Text
REVISED
AutoCAD SHX Text
JOB NO.
AutoCAD SHX Text
DRAWING NUMBER
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
CHECKED
AutoCAD SHX Text
PREPARED FOR
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
APPROXIMATE SCALE - FEET
AutoCAD SHX Text
PROPOSED CAMPUS SECURITY FENCE
AutoCAD SHX Text
PORTLAND VA MEDICAL CENTER - VANCOUVER CAMPUS
AutoCAD SHX Text
VANCOUVER, WASHINGTON
AutoCAD SHX Text
BLUE TRIDENT, LLC
AutoCAD SHX Text
BAINBRIDGE ISLAND, WASHINGTON
AutoCAD SHX Text 2213101-02G
AutoCAD SHX Text
TRR/10-19-22
AutoCAD SHX Text 2213101
AutoCAD SHX Text
CPI/10-24-22
AutoCAD SHX Text
TEST BORING LOCATION PLAN
AutoCAD SHX Text
PLATE 2.0
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
APPROXIMATE TEST BORING LOCATION
AutoCAD SHX Text B-1
AutoCAD SHX Text
GOOGLE EARTH IMAGE DATED MAY 10, 2021.
AutoCAD SHX Text
FORT VANCOUVER WAY
AutoCAD SHX Text
VANCOUVER VA MEDICAL CENTER
AutoCAD SHX Text B-1
AutoCAD SHX Text B-2
AutoCAD SHX Text B-3
AutoCAD SHX Text B-4
AutoCAD SHX Text B-5
AutoCAD SHX Text B-6
AutoCAD SHX Text B-7
B-8
4-2-4 (6)
5-3-2 (5)
5-3-4 (7)
5-6-8 (14)
5-5-5 (10)
NP
NP
NP
NP
NP
SS
SS
SS
SS
SS
TOPSOIL - 3 Inches 0.3'
Moist Loose Brown SILTY SAND w/Gravel (SM)
5.0' Moist Loose Brown POORLY GRADED SAND w/Trace Gravel and Silt (SP)
10.0' Moist Medium Dense Brown POORLY GRADED SAND w/Trace Gravel and Silt (SP)
15.0' Moist Loose Brown POORLY GRADED SAND w/Gravel and Trace Silt (SP)
16.5' Bottom of hole at 16.5 feet.
NOTES
LOGGED BY KKC
AT TIME OF DRILLING 15.0 ft / Elev 194.0 ft
AT END OF DRILLING None
0hrs AFTER DRILLING Backfilled w/Cuttings and Bentonite Chips
GROUND WATER LEVELS:
CHECKED BY CPI
GROUND ELEVATION 209 ftRIG NO. 3230 DTDRILLING CONTRACTOR Cascade Drilling Caleb Michael
DRILLING METHOD 4-Inch Casing
DATE STARTED 9/22/22 COMPLETED 9/22/22
E
LE
V A
T
IO
N (f t)
D E
P T
H (f t)
G R
A P
H
IC
LO
G
R E
C O
V E
R Y
(R
Q D
B
LO
W C
O U
N T
S (N
V A
LU
E
U N
C O
N F
. C O
M P
S
T R ts f)
D R
Y U
N
IT
W T
(p cf
SPT N VALUE
20 40 60 80
S A
M P
LE
T
Y P
E N
U M
B E
R
20 40 60 80
PL LLMC
MATERIAL DESCRIPTION
BORING NUMBER B-1
CLIENT Blue Trident, LLC
PROJECT NUMBER 2213101
PROJECT NAME Proposed Campus Security Fence
PROJECT LOCATION Portland VAMC Vancouver Campus, Vancouver, WA
T T
L_ G
E O
T E
C H
_S T
A N
D A
R D
1.
G
P J
G
IN
T U
S L
A B
.G D
T
0/
4/
TTL Associates, Inc.
1915 N 12th Street Toledo, Ohio 43624 Telephone: 419-324-2222 Fax: 419-241-1808
9-4-4 (8)
8-8-9 (17)
10-7-7 (14)
10-6-5 (11)
8-7-7 (14)
NP
NP
NP
NP
NP
SS
SS
SS
SS
SS
TOPSOIL - 3 Inches 0.3'
Moist Loose Brown SILTY SAND w/Trace Gravel (SM)
5.0' Moist Medium Dense Brown POORLY GRADED SAND w/Trace Gravel and Silt (SP)
@10': pH = 6.8
16.5' Bottom of hole at 16.5 feet.
NOTES
LOGGED BY KKC
AT TIME OF DRILLING None
AT END OF DRILLING None
0hrs AFTER DRILLING Backfilled w/Cuttings and Bentonite Chips
GROUND WATER LEVELS:
CHECKED BY CPI
GROUND ELEVATION 211 ftRIG NO. 3230 DTDRILLING CONTRACTOR Cascade Drilling Caleb Michael
DRILLING METHOD 4-Inch Casing
DATE STARTED 9/23/22 COMPLETED 9/23/22
E
LE
V A
T
IO
N (f t)
D E
P T
H (f t)
G R
A P
H
IC
LO
G
R E
C O
V E
R Y
(R
Q D
B
LO
W C
O U
N T
S (N
V A
LU
E
U N
C O
N F
. C O
M P
S
T R ts f)
D R
Y U
N
IT
W T
(p cf
SPT N VALUE
20 40 60 80
S A
M P
LE
T
Y P
E N
U M
B E
R
20 40 60 80
PL LLMC
MATERIAL DESCRIPTION
BORING NUMBER B-2
CLIENT Blue Trident, LLC
PROJECT NUMBER 2213101
PROJECT NAME Proposed Campus Security Fence
PROJECT LOCATION Portland VAMC Vancouver Campus, Vancouver, WA
T T
L_ G
E O
T E
C H
_S T
A N
D A
R D
1.
G
P J
G
IN
T U
S L
A B
.G D
T
0/
4/
TTL Associates, Inc.
1915 N 12th Street Toledo, Ohio 43624 Telephone: 419-324-2222 Fax: 419-241-1808
2-2-3 (5)
3-2-5 (7)
8-6-7 (13)
8-7-7 (14)
9-7-8 (15)
2.00
NP
NP
NP
NP
SS
SS
SS
SS
SS
ASPHALT - 6 Inches 0.5'
Moist Medium Stiff to Stiff Brown SANDY SILT w/Trace Gravel (ML)
5.0' Moist Loose Brown SILTY SAND w/Trace Gravel (SM)
6.5' Moist Loose Brown CLAYEY SAND w/Trace Gravel (SC)
7.5' Moist Medium Dense Brown POORLY GRADED SAND w/Trace Gravel and Silt (SP)
16.5' Bottom of hole at 16.5 feet.
NOTES
LOGGED BY KKC
AT TIME OF DRILLING None
AT END…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .