Attachment 14 - Price Factor 3 - Evaluation change - Solicitation 36C26026R0042.pdf
PDF 31 KB Posted
- Attached to
- Construct Campus Security Fence and Access Control - Construction Federal contract opportunity
- Solicitation number
- 36C26026R0042
About this file
This is an amendment to a solicitation that modifies the Price Evaluation Factor 3 criteria on page 49 of the original Request for Proposals (RFP). The amendment establishes that price will be evaluated based on reasonableness using methods identified in RFO subpart 36.2 and RFO part 15, with offerors required to ensure price completeness and accuracy before submission.
The pricing structure requires separate evaluation of three Contract Line Items (CLINs): CLIN 001 serves as the base bid; CLIN 002 (Alternate Option No. 1) shall be priced as an additional lump sum amount separate from the base bid; and CLIN 003 (Alternate Option No. 2) shall be priced on a per-unit basis for each tree and associated wheel stop, also separate from the base bid. The Government's total evaluated price will be calculated as the sum of all three CLINs (CLIN 1 + CLIN 2 + CLIN 3).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 8 - RFI - Project 648-20-121 - Const CampusSecurity Fence 1.pdf | ||
| Attachment 7 - REVISED PRICE COST SCHEDULE.pdf | ||
| Attachment 10 - 32 84 00 Planting Irrigation Specs - Project 648-20-121.pdf | ||
| Attachment 12 - Addendum 1 for Drawing 250122 - ELEC - Project 648-20-121.pdf | ||
| Attachment 13 - Revised SOW - Project 648-20-121.pdf | ||
| Amendment 4 648-20-121 - 5-27-26.pdf | ||
| Attachment 9 - Official Geotechnical Subsurface Investigation.pdf | ||
| Attachment 11 - SUBMITTAL REGISTER -VA 01 33 23 - Project 648-20-121.pdf | ||
| Amendment 3 648-20-121.pdf | ||
| Amendment 2 648-20-121.pdf | ||
| Amendment 1 648-20-121.pdf | ||
| Attachment 1- SOW 648-20-121 4-21-26.docx | DOCX document | |
| S02 36C26026R0042 SOL 648-20-121.pdf | ||
| Attachment 6 - Geotech Report and Boring Logs - 648-20-121.pdf | ||
| Attachment 5- Wage Determination 1-2-26.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Evaluation Factor 3 change
The current wording under 3 Factor 3 Price Evaluation on page 49 shall be removed and replaced with the following:
Price will be evaluated on a basis of reasonableness using any combination of methods identified in RFO subpart 36.2 and RFO part 15. Offerors are required to review and ensure their prices are complete and accurate prior to submitting to the Government.
CLIN 002 Alternate (Option) No. 1 shall be priced separately priced from the Base bid as an additional lump sum amount.
CLIN 003 Alternate (Option) No. 2 shall be separately pried from the Base bid on a per unit basis for each tree and associated wheel stop.
The Government will evaluated the total evaluated price, consisting of the base bid (CLIN 1) + CLIN 2 + CLIN 3= total evaluated price.
File details come from the government source that posted it. Updated .