This is a Statement of Work for Project Number 648-20-121, issued by the Department of Veterans Affairs for construction of a campus security fence and access control system at the Portland VA Medical Center Vancouver Campus in Vancouver, Washington.

The contractor shall furnish all materials, labor, equipment, training, transportation, and personnel to construct a new perimeter security fence replacing the existing 6-foot chain link fence. The work includes: a concrete mow strip, one motorized vehicle gate, three personnel gates, a concrete vehicle fortification (3 feet tall, sloped jersey barrier style) for approximately 1,100 linear feet along Fourth Plain Boulevard, and lighting and camera systems with designed raceways for the entire perimeter. The period of performance is 275 days from Notice to Proceed. Two optional line items are available: CLIN 2 (alternate option 1) for new entry doors, frames, hardware, and electronic locks at Buildings 3 and 4 priced as an additional lump sum; and CLIN 3 (alternate option 2) for eight additional trees with associated wheel stops priced on a per-unit basis with itemized material and labor costs.

Normal work hours are 7:00 AM to 9:00 PM (PST) Monday through Friday, excluding Federal Holidays and weekends, with contractor permission required for weekend or holiday work. Quiet hours apply after 6:00 PM PST near Building 1 and after 9:00 PM daily near Freedom's Path, the SRO, and Fisher House. The contractor must conduct weekly progress meetings with the Government, coordinate site scheduling with the Contracting Officer Representative, provide all traffic control and protective barriers at no additional cost, and schedule utility outages with at least 21 working days advance notice in writing. All work must be performed in a skillful and workmanlike manner with approval required for any proposed changes to the quality control plan and operations.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PROJECT NUMBER 648-20-121

Construct Campus Security Fence & Access Control

Portland VAMC, Vancouver Campus, Vancouver WA

Introduction/Background: This project will construct a campus security fence surrounding the Portland VA Medical Center Vancouver Campus. The contractor shall completely prepare site for building operations, including demolition and removal of existing structures, furnish labor and materials, and perform work for 648-20-121 Construct Campus Security Fence and Access Control (Vancouver) as required by drawings and specifications. For all requirements and further information see the attached specifications, drawings, and contract documents.

The new fence will replace the existing 6-foot chain link fence and be constructed with:

• A concrete mow strip

• One motorized vehicle gate

• Three personnel gates

• A vehicle fortification will be included for approximately 1100 linear feet of perimeter fence along Fourth Plain Blvd. starting approximately 100 feet East from the NW corner and following the perimeter eastward.

• This fortification is concrete, 3 feet tall, and sloped like a jersey barrier on the side facing Fourth Plain Blvd.

• Lighting and camera systems for the whole perimeter fence will use designed raceways.

CLIN 2- Alternate (Option 1) New entry doors, frames & hardware at Bldgs. 3 & 4 with electronic locks and card readers tied to the existing security system. CLIN 2 Pricing should be written as an additional lump sum.

CLIN 3 Alternate (Option 2) Eight additional trees and their associated wheel stops. The pricing for this line item should be itemized on a per unit basis with each unit comprising of one tree and 4 wheel stops inclusive of material and labor costs. CLIN 3 pricing should be written out for each tree and wheel stop.

Objectives

(a) The contractor shall furnish all materials, labor, equipment, training, transportation, and personnel to accomplish required tasks in accordance with VA provided drawings and specifications.

(b) The Government will provide specifications and drawings of all locations where the work is to be performed.

Normal Operating Hours

For this project, normal work hours are 7:00AM to 9:00PM (PST) Monday through Friday excluding Federal Holidays and weekends. Contractors must obtain permission from the COR prior to working on Saturdays, Sundays, and Federal Holidays. All medical center activities will remain unimpeded by construction activities. Also, work around Building 1 (CLC) will observe quiet hours after 6:00PM PST, meaning loud noises and vibrations will need to cease, but non disruptive work will be allowed until 9:00PM PDT. Quiet hour restrictions also apply near Freedom’s Path, the SRO, and Fisher House (Building 25) beginning at 9:00PM daily.

Site Superintendent

For contractor’s employees all work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require in writing the contractor to remove from the job site any employee the CO deems incompetent, careless, or otherwise objectionable.

Progress Meetings

Progress meetings shall be held weekly, between the contractor and the Government, to discuss work progress, problems, and potential modifications.

Period of Performance

Construction is 275 days from the issuance of the NTP.

Specifications

Project specifications are included with this solicitation under attachment 3 648-20-121 Specs R1.

Work Scheduling

1. Before commencement of work, the contractor shall confer with the Contracting Officer Representative and agree on a sequence of procedures, means of access to premises, space for storage of materials and equipment, delivery of materials and use of approaches, use of corridors, stairways, elevators, and similar means of communications; location of partitions, eating spaces, and restrooms for contractor employees, and the like.

2. Delivery of materials and equipment shall be made with a minimum of interference to Government operations and personnel.

3. The work shall so far as practicable be done in definite sections or divisions and confined to limited areas which shall be completed before work in other sections or divisions are begun.

4. The contractor shall be responsible for providing all work site protective barriers and site control devices. This includes protective fences, protective tapes, and protective signage. The contractor shall be responsible for providing all traffic control, such as street blockages, traffic cones, flagman, etc. As required for each task at no additional cost to the Government. Proposed traffic control methods shall be submitted to the COR for final approval. No street shall be completely closed to traffic without prior approval from the COR.

5. All temporary outages of any utility services required for the performance of work shall be scheduled with the COR no less than twenty-one working days in advance of such outages. Request for power outages must be in writing.

Contractor Quality Control

The Government reserves the right to require the contractor to make changes in the CQC Plan and operations to obtain the quality specified. These changes must be submitted to and approved by the CO.

Notification of changes: The contractor shall notify the CO in writing prior to any proposed changes. Proposed changes are subject to acceptance by the CO.