Attachment 1 - PWS revision.docx

DOCX document 61 KB Posted

Attached to
J061--Miles City Generator Maintenance
Solicitation number
36C25925Q0534
Issued by

About this file

This Performance Work Statement (PWS) details generator maintenance and load testing services for the Department of Veterans Affairs' Miles City Community Living Center (CLC) in Montana. The contract requires comprehensive annual maintenance of a 375-kW Caterpillar 3412 emergency generator system, including full load testing, fuel system maintenance, lubrication system checks, cooling system inspections, and electrical system evaluations in accordance with NFPA 110 and Joint Commission standards. Contractors must demonstrate proven generator operations experience, electrical safety training, and capability to provide genuine CAT parts, with services to be performed annually in October and limited emergency repairs up to $2,500.

The solicitation (36C25925Q0534) is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses under NAICS code 811310, with a small business size standard of $12.5 million. The contract is structured as a firm-fixed price Indefinite Delivery Indefinite Quantity arrangement spanning five years from September 1, 2025, to September 1, 2030. Proposals were due by August 5, 2025, at 2:00 PM Mountain Standard Time, with evaluation criteria including price, technical capability, and past performance. Contractors must provide comprehensive documentation, wear company uniforms, display identification badges, and submit monthly electronic invoices through the VA's Electronic Invoice Payment System.

View the file

Other files

File Type Posted
36C25925Q0534_2.docx DOCX document
Attachment 2 - Price Schedule revision.xlsx XLSX spreadsheet
Attachment D - Equipment Plate.docx DOCX document
36C25925Q0534_1.docx DOCX document
Attachment C - Quality Assurance Surveillance Plan QASP.docx DOCX document
Attachment 1 - PWS Generator Maintenance and Testing.docx DOCX document
Attachment 3 - LOS 852.219-75 - SERVICES.docx DOCX document
36C25925Q0534.docx DOCX document
Attachment B - DOL 2015-5395 rv25 Custer County MT.pdf PDF
Attachment 2 - Price Schedule.xlsx XLSX spreadsheet
Attachment A - Diagram.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

1.0 INTRODUCTION

The Department of Veterans Affairs, Montana Veterans Health Administration (VHA) has a requirement for Generator Load Testing and Maintenance Services. Contractor shall provide maintenance, inspection, testing, and calibration of Emergency Backup Generator and all its components (e.g., batteries, Automatic Transfer Switches (ATS), fuel supply, radiators, etc.) located at the Miles City Community Living Center (CLC) located at 210 S Winchester Ave, Miles City, MT 59301. Contractor shall provide all labor, equipment and resources necessary to complete the services and return the unit to service detailed in the PWS.

The CLC has a 375-kW primary generator system that includes various secondary voltages and both normal and emergency power sources.

2.0 SCOPE OF WORK

The contractor shall provide all materials, labor, and equipment required to load test the generator at Miles City CLC. Load testing shall be in accordance with the most current National Fire Protection Association (NFPA) 110 Standard for Emergency and Standby Power Systems (EPS), current publication is 2025 Edition, Joint Commission requirements, American Society for Testing and Materials (ASTM) and manufacturer specifications.

The EPS is by NFPA definition a source of electric power of the required capacity and quality for an emergency power supply system (EPSS). Miles City CLC EPS consists of one (1) emergency generator listed below and shown in Attachment A-Diagram. The system shall be tested annually in October of each contract year.

The contractor shall provide all necessary labor, materials, tools and specialized equipment necessary for the full performance of this contract.

Testing, maintenance, and exercising of the generator, including all related components, must be executed to meet the requirements of NFPA 99 and NFPA 110, whichever is more stringent.

Annual fuel quality test meeting manufacturer’s recommendations and ASTM standards as specified in the current version of NFPA 110.

All testing should be performed using ASTM-approved test methods such as, but not limited to:

A. ASTM D4057, Standard Practice for Manual Sampling of Petroleum and Petroleum Products, for fuel quality;

B. ASTM D7464, Standard Practice for Manual Sampling of Liquid Fuels, Associated Materials and Fuel System Components for Microbiological Testing, for microbial contamination;

C. ASTM D2709, Standard Test Method for Water and Sediment in Middle Distillate Fuels by Centrifuge, for water and sediment;

D. ASTM D4176, Standard Test Method for Free Waler and Particulate Contamination in Distillate Fuels (Visual Inspection Procedures), for appearance-distillate;

E. ASTM D7220, Standard Test Method for Sulfur in Automotive, Heating, and Jet Fuels by Monochromatic Energy Dispersive X-ray Fluorescence Spectrometry, for sulfur (ppm), and meet engine manufacturer requirements. (NFPA 110-2025, A.8.3.7)

Caterpillar 3412 Generator Set

Model: SR4

Generator Part No. 5N 46 Generator Frame No. 588

RPM 1800 Hertz 60

Generator Serial no. 58BH746-B

3.0 CONTRACTOR RESPONSIBILITIES:

Contractor shall perform:

a. Load Tests (Annually):

i. Perform a full load test at a predetermined percentage of the generator's capacity for a specified duration.

ii. Monitor all critical parameters during the load test.

b. Maintenance Procedures (Annually):

i. Fuel System Maintenance:

1. Regularly check fuel levels and quality.

2. Clean fuel filters and lines as per manufacturer recommendations.

ii. Lubrication System:

1. Change engine oil and filters according to schedule. Contractor is responsible for the disposal of any used oil or fluids.

2. Inspect and lubricate all moving parts.

iii. Cooling System:

1. Check coolant levels and composition.

2. Clean cooling system components as needed.

3. Annual air filter replacement.

iv. Electrical System:

1. Inspect generator wiring and connections for damage or corrosion.

2. Test (3) automatic transfer switches as follows.

a. Check connections

b. Inspect for evidence of overheating or excessive contact erosion

c. Remove dust and dirt

d. Replace contacts if required

Maintenance shall include:

- Annual load bank test at minimum 50% nameplate kW rating for 30 minutes, followed by a minimum 75% nameplate kW for 60 minutes per NFPA 110 (8.4.2.4).

- Fluid analysis for oil, fuel and coolant.

- Fuel Quality testing for fuel tanks supplying the emergency generator

- All material & supplies shall be genuine CAT filters, fluids, gaskets, seals, etc.

4.0 CONTRACTOR QUALIFICATIONS:

a) The Contractor shall have track records of proven experience with generator operations and load banking.

b) The Contractor shall have safety training – either on-the-job or classroom type in electrical safety outlined in the OSHA Standard 29 Code of Federal Regulations (CFR) 1910 Subpart S – Electrical and NFPA 70E – Standard of Electrical Safety in the Workplace. Training certifications shall be submitted to the VA Facilities Management Service Contracting Officer Representative (COR) prior to work. If no training certificates are available, the Contractor’s employer shall certify that the service technician(s) meet this requirement.

5.0 SCHEDULING:

All inspection, evaluation and testing service must be scheduled one week in advance as and in agreement with the COR.

· The contractor must sign in each day that work is to be performed. Employees to perform the service must report to Miles City CLC Facility Manager.

· Contractor must notify the COR prior to testing any generator set or alarm devices unless the facility manager is witnessing the test and is physically present at the testing site.

6.0 REPAIRS:

Any necessary repair/replacement parts or services created by testing the equipment as part of this contract must be identified and reported to the COR for further action. The contractor shall communicate and coordinate with the COR for all repairs.

Repairs shall be designated and completed on an emergency basis under separate CLINs in the contract and not to exceed $2,500.

Contractor shall pause/standby annual testing for repairs. The contractor shall resume testing as soon as practical after the repairs have been made.

Minor repairs shall include but not be limited to such items as loose bolts, lose or broken lugs, wiring terminals, heaters, malfunctioning targets, dirty/high resistance connections, etc. and shall be communicated with the COR prior to making the repair during testing if possible.

Non-Emergency Repairs: The Contracting officer can authorize requests for repairs if they are submitted in writing and do not exceed $2,500. All requests for repairs shall be in writing with a detailed explanation of the cost of parts, labor and all associated costs to complete repair(s).

Any repair that exceeds $2,500 shall require approval. The contractor shall submit their request for repair with a detailed explanation and breakdown of costs to the COR who will work with contracting on the requirement.

All material & supplies shall be genuine CAT replacement parts: filters, fluids, gaskets, seals, etc.

7.0 EMERGENCY REPAIRS:

The contractor may be requested to perform emergency repair work if a circuit cannot be energized after inspection and maintenance have been accomplished. Any item found to be out of tolerance, or in any other way defective because of the required testing, shall be reported to the Contracting Officer’s Representative (COR) immediately.

The COR may authorize an emergency repair for an emergency that occurs outside of normal working hours 7:00 am -4:30 pm, Monday- Friday. The COR shall notify the CO and submit, in writing, the circumstances surrounding the emergency the next business day. The contractor shall submit a detailed breakdown of all costs to the COR and the CO within 24 hours, to include a detailed breakdown of labor, by category to include the number of estimated hours. All parts shall be listed and priced individually.

8.0 COORDINATION:

The contractor shall be responsible for coordinating any necessary utility system shutdowns and returning these systems to operational mode. In addition, the contractor must notify the COR before any systems are shut down and when these systems are put back into full service.

The contractor will not be permitted to leave any emergency generator system or component in a non-automatic connected mode or unattended mode during any portion of the testing.

Should such non-automatic circumstances exist the contractor must have the approval of the COR.

The contractor shall be responsible for damages to government equipment or property due to contractor negligence.

Contractor shall ensure that equivalent loads used for testing are connected such that they can be automatically replaced with emergency loads in case of failure of the primary power source.

9.0 DELIVERABLES:

At the completion of the service visit for all equipment, the contractor shall furnish a final written report, via e-mail or standard mail, within ten working days of completion of the testing, inspection and evaluation. Report shall list as a minimum:

i. Date of Service.

ii. Company’s name, addresses, telephone, & FAX numbers.

iii. Name and signature of contractors who perform the maintenance and testing.

iv. VA Work Contract Number, name and number of VA Contracting Officer.

v. Copies of contractors’ valid licenses, professional and training certificates.

vi. Location of system or devices

vii. Type of system or devices

viii. Type of service being performed.

ix. Recommended corrective actions, if any.

x. Tests completed.

xi. Fluid tests results

xii. Remarks on the conditions of electrical equipment. List all deficiencies, if any.

xiii. Reference materials such as equipment manufacturer’s specifications, coordination study, etc.

10.0 KEY PERSONNEL:

Key personnel will be identified in the proposal and shall be considered key personnel essential for the successful completion of the work performed under the contract. The contractor agrees that such personnel shall not be removed, diverted, or replaced from the work without prior written approval of the COR. The contractor shall submit written notice of proposed personnel changes to the COR for approval at least thirty (30) business days in advance.

11.0 CONTRACTOR EMPLOYEE IDENTIFICATION:

Contractor shall ensure that their personnel wear company uniforms and a visible identification badge which contains a photograph of the employee. All contractor vehicles and collection bins will be clearly identified with the company’s name.

Upon contract award, the Contractor shall specify an individual who shall serve as a single point of contact (POC) for all Contract related business. Contractor must provide to the COR the POC contact details, including cell phone and email. The POC must be easily accessible by phone.

12.0 HOLIDAYS AND WORK HOURS:

The services covered by this contract shall be furnished by the contractor as defined herein. The contractor shall not be required, except in cases of emergency, to furnish such services on Federal Holidays or during off duty hours as described below.

Normal working hours: Monday through Friday, 7:45 a.m. – 4:30 p.m. MOUNTAIN TIME, excluding federal holidays.

The 11 holidays observed by the Federal Government are:

New Year’s DayMartin Luther King, Jr. Day
President’s DayMemorial Day
Independence DayLabor Day
Columbus DayVeterans Day
JuneteenthThanksgiving Day

Christmas Day

Any other day specifically declared by the President of the United States to be a federal holiday. When one of the holidays falls on Sunday, the following Monday shall be observed as a Federal Holiday. When a holiday falls on a Saturday, the preceding Friday shall be observed as a Federal Holiday.

13.0 INVOICES:

The contractor shall submit payment requests in electronic form via VA’s Electronic Invoice Payment System. (See Web site at http://www.fsc.va.gov/einvoice.asp.)

Invoices shall be submitted monthly, in arrears. The following information must be included on all submitted invoices. Invoices submitted without the following information may be rejected for payment.

· Date of Invoice Contract Number

· Purchase Order Number for Correction Period of Performance

· Contractor Name Invoice Number

· CLIN i.e. Contract Line Item and Amount being billed per line item

· Date of Service

14.0 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

The contractor performance shall be evaluated in accordance with the QASP for Generator Maintenance Services and Load Testing as detailed in Section 16. and Attachment C.

15.0 PERFORMANCE STANDARDS

The table below defines the Performance Standards and Acceptable Levels of Performance associated with this effort.

Performance Objective
Performance Standard
Acceptable Levels of Performance
A. Technical / Quality of Service
· Demonstrates understanding of requirements.

· Efficient and effective in meeting requirements

· Meets technical needs and mission requirements.

· Provides quality services/products.

Satisfactory or higher

B. Project Milestones and Schedule
· Services completed, reviewed, delivered in accordance with the established schedule.

· Notifies customer in advance of potential problems

· Performs service needs and repairs timely.

Satisfactory or higher

C. Cost & Staffing
· Currency of expertise and staffing levels appropriate to perform tasks required.

· Personnel possess necessary knowledge, tools, skills, and abilities to perform tasks.

Satisfactory or higher

D. Management
· Integration and coordination of all activities to execute effort.
Satisfactory or higher

Acceptable Performance: The Government shall document positive or negative performance. Any report may become a part of the supporting documentation for any contractual action.

Unacceptable Performance: When unacceptable performance occurs, the COR shall work with the Contracting Officer (CO) inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case, the COR shall document the discussion and place it in the COR file.

To assure that the contractor receives impartial, fair, and equitable treatment under this contract, the COR will work with the contractor to increase performance to an acceptable level. When the COR and CO determines formal written communication is required, the COR and CO shall prepare a Notification (Letter or Concern (LOC), Cure Notice, Show Cause Notice) and present it to the Contractor.

1. The contractor shall acknowledge receipt of the LOC Notice in writing.

2. The LOC will specify if the contractor is required to prepare a corrective action plan (CAP) to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The Notice will also state how long after receipt the contractor shall present this corrective action plan to the CO.

3. The Government shall review the contractor's corrective action plan to determine acceptability.

Any Notice may become a part of the supporting documentation for any contractual action deemed necessary by the CO.

16.0 CONTRACT ADMINISTRATION:

Notwithstanding the Contractor's responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the COR, CO, and the Contractor.

The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements of this contract. The Contractor shall communicate with the Contracting Officer on all matters pertaining to contract administration. Only the Contracting Officer is authorized to make commitments or issue changes that shall affect price, quantity, or quality of performance of this contract.

The COR shall be responsible for the overall technical administration of this contract as outlined in the COR Delegation of Authority.

In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer without authority, no adjustment shall be made in the contract price to cover an increase in costs incurred as a result thereof.

POINTS OF CONTACT

Contracting Officer:

Department of Veterans Affairs Insert address

Contracting Officer’s Representative (COR):

Name Email Address