This document contains a specification section for a motorized mobile storage shelving system and a presolicitation notice for a pharmacy renovation project.
The specification section describes the technical requirements for an electric, carriage-mounted high-density mobile storage unit including rails, carriages, drive systems, controls, safety features and finishes. Performance requirements specify a maximum height of 80 inches, length of 16 feet and subfloor deflection of L/480. Submittal requirements include product data, shop drawings, samples and warranty information.
The presolicitation notice is for project number 635-18-102 to renovate 12,155 square feet of inpatient and primary care pharmacy space at an Oklahoma City VA healthcare system to comply with pharmacy regulations. The $2-4 million project has a 100% set-aside for Service-Disabled Veteran Owned Small Businesses and responses are due on or shortly after March 8, 2021. Offerors must register in SAM and VetBiz databases and obtain any solicitation amendments from the provided website.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Oklahoma Renovate Pharmacy for Chapter 797/800
Contract No. VA259-16-D-0217
10 56 26.23 - 1
SECTION 105626.23
MOTORIZED MOBILE STORAGE SHELVING
PART 1 - GENERAL
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
SUMMARY
B. This Section includes the following:
1. Electric, carriage mounted high-density mobile storage units, support rails, fabrication, and installation including leveling of support rails.
C. Related Work, Not Furnished:
1. Structural floor system capable of supporting live and dead loads required by prevailing building codes, including loads of storage units to be installed. Provide a maximum allowable sub floor deflection of L/480 under specified mobile storage loads.
2. Finish floor covering and edging materials and installation on raised floors and ramps, or when on concrete with recessed rail installation.
3. Power wiring to units from adequate power supply. Final connections to units shall be provided by electrician.
4. Fire suppression system is by others.
D. Related Sections:
1. Division 26 Specification Sections power wiring devices, conductors and circuit protection.
REFERENCES
E. American Library Association (when applicable)
1. Cantilever Bracket Type Metal Library Bookstacks; Library
Technology Reports.
F. American National Standards Institute (ANSI) Standards:
1. Applicable standards for fasteners used for assembly.
G. American Society for Testing and Materials (ASTM) Standards:
1. Applicable standards for steel sheet materials used for fabrication.
H. American Institute of Steel Construction (AISC) Standards:
1. Applicable standards for steel materials used for fabrication.
I. Underwriters’ Laboratories (C-UL US):
10 56 26.23 - 2
1. Listings for electrical equipment and devices described in this specification.
SYSTEM DESCRIPTION
J. General: The system consists of four-post shelving units mounted on manufacturer’s track-guided carriages to form a compact storage system. System design permits access to any single aisle by moving units until the desired aisle is opened. The carriage/rail system provides uniform carriage movement along the total length of travel, even with unbalanced loads.
K. Carriage System Design and Features: The carriage system consists of a formed structural steel frame with hardened steel riding on steel rails recessed mounted to the floor. Rails shall be types selected by the manufacturer to ensure smooth operation and self-centering of mobile storage units during travel without end play or binding. Rail types, quantities and spacing shall be selected by the manufacturer to suit installation conditions and requirements. All bearings used in the drive mechanism shall be permanently shielded and lubricated.
L. Movement Controls: Provide a carriage control panel on the accessible
(open) end of each moveable carriage, located 44 inches (1118 MM) above the base, centered on the face panel. Minimum controls shall include directional control buttons/icons, STOP/RESET push-button/icon and a red reset light/icon.
1. System controls shall start motors on each movable carriage
“sequentially” to minimize power demands and shall provide dynamic braking to provide smooth operation. No additional hardware shall be required to change between “sequential” and
“block” movement. Maximum running speed shall be limited to 3.3 inches (84 mm) per second.
2. Provide solid state controls and indicator lights/icons for a visual indication of safety system operation. Provide each aisle with a programmable distance sensor to ensure proper timing for start/stop operation.
3. Pushing the directional control button/icon on any moveable carriage adjacent to the desired aisle location in the direction away from the desired aisle location opens the system at the desired aisle. The selected aisle shall open automatically regardless of the position of the carriages. Automatic Reset: The carriage control heads will display a constant green light, or green arrow icon, at all carriages indicating that the system is ready for the next aisle access. Provide for automatic reset if system is equipped with optional Zero Force Sensor (ZFS) system safety feature, or other redundant safeties.
4. Controls shall feature safety activated message and direction indicator designating which aisle safety was activated or back lit message indicating which aisle is in use (i.e. “Right Aisle in use” or “Left Aisle in use”).
5. Provide Bluetooth control via the TUSC Mobile Control App in replace of or in addition to the standard powered control or touch technology system controls.
10 56 26.23 - 3
M. Drive System: The system shall be designed with a positive type motorized drive which minimizes end play and that carriages will stop without drifting. All system components shall be selected to ensure a smooth, even movement along the entire carriage length.
1. Each electric carriage shall be provided with a current limited fractional horsepower gear motor, connected to drive wheel assembly with a roller chain.
2. System shall include a chain sprocket drive system to ensure that carriages move uniformly along the total length of travel, even with unbalanced loads.
3. A tensioning device shall be provided on each chain drive (when applicable).
4. All bearings used in the drive mechanism shall be permanently shielded and lubricated.
5. System shall operate on 115 V.A.C. 50/60 hertz, 20 amp dedicated circuit provided by others, one per module.
6. Overhead mounted power pantograph distribution system shall conceal all interconnecting wiring.
N. Safety Features:
1. Visual indicators shall provide verification that carriages are in the locked or unlocked mode.
2. Dual full-length infrared photoelectric safety sweeps shall be provided to stop carriage movement if the sweep contacts an obstruction while in motion. Sweep must be equipped with red/white stripped safety demarcation tape with text, “PLACE FOOT
HERE TO STOP”.
3. Entire system shall be C-UL US system listed.
4. An infrared photoelectric aisle entry sensor system shall be provided to stop carriage movement if the system detects persons entering a closing aisle.
5. A handheld rechargeable power pack shall be provided for emergency operations in case of primary power failure.
O. Finishes:
1. Fabricated Metal Components And Assemblies: Manufacturer’s standard powder coat paint finish.
2. End Panels, Accessible Ends: Plastic laminate, manufacturer’s standard available textures and patterns.
PERFORMANCE REQUIREMENTS
P. Design Requirements:
1. Limit overall height to 80 inches.
2. Limit overall length to 16 feet.
10 56 26.23 - 4
SUBMITTALS
Q. Product Data: Submit manufacturer's product literature and installation instructions for each type of shelving, track and installation accessory required. Include data substantiating that products to be furnished comply with requirements of the contract documents.
R. Shop Drawings: Show fabrication, assembly, and installation details including descriptions of procedures and diagrams. Show complete extent of installation layout including clearances, spacings, and relation to adjacent construction in plan, elevation, and sections.
Indicate clear exit and access aisle widths; access to concealed components; assemblies, connections, attachments, reinforcement, and anchorage; and deck details, edge conditions, and extent of finish flooring within area where units are to be installed.
1. Show installation details at non-standard conditions. Furnish floor layouts, technical and installation manuals for every unit shipment with necessary dimensions for rail layout and system configuration at the project site. Include installed weight, load criteria, furnished specialties, and accessories.
2. Provide layout, dimensions, and identification of each unit corresponding to sequence of installation and erection procedures. Specifically include the following:
a. Location, position and configuration of tracks on all floors.
b. Plan layouts of positions of carriages, including all required clearances.
c. Details of shelving, indicating method and configuration of installation in carriages.
3. Provide location and details of anchorage devices to be embedded in or fastened to other construction.
4. Provide installation schedule and complete erection procedures to ensure proper installation.
5. Show locations of wiring and disconnects required for operating movable carriage units.
S. Samples: Provide minimum 3 inch (76MM) square example of each color and texture on actual substrate for each component to remain exposed after installation.
T. Selection Samples: For initial selection of colors and textures, submit manufacturer's color charts consisting of actual product pieces, showing full range of colors and textures available.
U. Warranty: Submit draft copy of proposed warranty for review by the
Architect/Owner.
QUALITY ASSURANCE
A. Manufacturer Qualifications: Engage an experienced manufacturer who is
ISO 9001 certified for the design, production, installation and service of motorized, carriage mounted high-density mobile storage
10 56 26.23 - 5 units and support rails. Furnish manufacturer’s ISO 9001 quality system registration certificate.
B. Installer Qualifications: Engage an experienced installer who is a manufacturer's authorized representative for the specified products for installing carriages and anchoring shelving units to carriages.
1. Minimum Qualifications: 2-years experience installing systems of comparable size and complexity to specified project requirements.
2. Guaranteed 24-hour minimum response time to service call.
DELIVERY, STORAGE AND HANDLING
C. Follow manufacturer’s instructions and recommendations for delivery, storage and handling requirements.
PROJECT CONDITIONS
D. Field Measurements: Verify dimensions before fabrication. Indicate verified measurements on Shop Drawings. Coordinate fabrication and delivery to ensure no delay in progress of the Work.
E. Established Dimensions: Where field measurements cannot be made without delaying the Work, establish dimensions and proceed with fabricating mobile storage units without field measurements.
Coordinate construction to ensure actual dimensions correspond to established dimensions.
SEQUENCING AND SCHEDULING
F. Sequence storage shelving system installation with other work to minimize possibility of damage and soiling during remainder of construction period.
G. Schedule installation of specified products and accessories after finishing operations, including painting have been completed.
H. Provide components, which must be built in at a time which causes no delays general progress of the Work.
I. Pre-installation Conference: Schedule and conduct conference on project site to review methods and procedures for installing mobile storage units including, but not limited to, the following:
1. Review project conditions and levelness of flooring and other preparatory work performed under other contracts.
2. Review and verify structural loading limitations.
3. Recommended attendees include:
a. Owner's Representative.
b. Prime Contractor or representative.
c. The Architect.
d. Manufacturer's representative.
10 56 26.23 - 6
e. Subcontractors or installers whose work may affect, or be affected by, the work of this section.
WARRANTY
J. Provide a written warranty, executed by Contractor, Installer, and
Manufacturer, agreeing to repair or replace units which fail in materials or workmanship within the established warranty period. This warranty shall be in addition to, and not a limitation of, other rights the Owner may have under General Conditions provisions of the
Contract Documents.
K. Warrant the entire movable compact shelving installation against defects in materials and workmanship for a period of five years from date of acceptance by the Owner.
PART 2 - PRODUCTS
MANUFACTURERS
A. General: Model #ECSSG106759 Push Button electric Mobile by Southwest
Solutions Group 14320 N Lincoln BLVD, Unit 406 OKC OK 73013.
Telephone: 1-800-803-1083.
1. The materials, products and equipment described in the Bidding
Documents establish a standard of required function, dimension, appearance and quality to be met by any proposed substitution.
BASIC MATERIALS
B. General: Provide materials and quality of workmanship which meet or exceed established industry standards for products specified. Use furniture grade sheet metal for component fabrication unless indicated otherwise. Material thickness/gauges are manufacturer’s option unless indicated otherwise.
C. Plastic Laminates: NEMA LD-3, GP-28, Vertical Grade.
D. Electrical Devices and Controls: C-UL US System Listed for type of application and service.
GROUT
E. General: Provide non-shrink, non-staining hydraulic cement compound conforming to the following requirements, based on the performance of the test specimens at room temperature and in laboratory air, as stated by the grout manufacturer.
1. Linear Movement: No shrinkage while setting; maximum expansion limited to .002 inches per linear inch.
2. Compressive Strength: Based on two inch cubes made following
ASTM standards, tested on a Balding-Southward machine of 60,000 pounds capacity, meet or exceed the following:
a. Age: 1 hour ---- 4,500 psi
7 days ---- 8,000 psi
10 56 26.23 - 7
MANUFACTURED COMPONENTS
F. Rails:
1. General: Provide manufacturer's proprietary design units with the following properties:
2. Material: ASTM/AISI Type 1035 or 1045 steel, manufacturer’s selection.
3. Capacity: 1,000 pounds per lineal foot (1385kg/M) of carriage.
4. Minimum Contact Surface: 5/8 inch (16MM) wide.
5. Provide rail sections in minimum 6 foot (1.83M) lengths.
6. Rail configuration shall permit attachment to top of structural floor system with provision for leveling rails to compensate for variations in floor surface level.
7. Provide rail connections designed to provide horizontal and vertical continuity between rail sections, to gradually transfer the concentrated wheel point load to and from adjoining rail sections. Butt joints without connections are not permitted.
8. Once rails are leveled, they shall be supported the full length with the specified grout.
G. Floor / Ramp:
1. Floor/Ramp Sheathing: Minimum 3/4 inch (19MM), 7-ply underlayment grade plywood. Particleboard sheathing materials are not permitted. Provide low volatile organic compound (VOC)-emitting material for floor/ramp sheathing.
2. Provide fire retardant treated floor/ramp materials when required by code.
3. Finished flooring materials shall be provided by others.
H. Carriages:
1. Provide manufacturer's design movable carriages fabricated of welded wheel assembly with bolted steel and riveted construction.
Galvanized carriage components are unacceptable. The use of cross-bracing is unacceptable.
2. Design carriages to allow the shelving uprights to recess and interlock into the carriage wheel section a minimum of 2 inches
(50MM). Carriage design shall provide a minimum of two shelving retention rivets and two carriage bolts to securely retain each shelving post. Top mounting of shelving onto carriages is unacceptable.
3. Provide each carriage with two wheels per rail.
I. Drive / Guide System:
1. Design: Provide drive system which prevents carriage whipping, binding and excessive wheel/rail wear under normal operation.
a. Provide a full-length line drive shafts, whereby, all wheels on one side of carriage shall drive.
10 56 26.23 - 8
2. Shafts: 1-inch (25MM) steel connecting tube shafts.
3. Bearing Surfaces: Provide rotating load bearing members with ball or roller bearings. Provide shafts with pillow block or flanged self-aligning type bearings.
J. Wheels:
1. Low-Profile Wheel Section: Minimum 12 gauge. fixture-welded wheel sections to ensure that, once installed; bottom storage shelf is no higher than 4.25 inches (108mm) above top of rail. Locate wheel assemblies under each upright to distribute loads directly to wheels.
2. Wheel Size: Minimum 3 inches (76MM), outside diameter drive and load wheels.
3. Guide Wheels: All wheels and all locations.
K. Motors:
1. Type: 90VDC
L. Face Panels:
1. Materials: HPL Plastic laminate clad particleboard with plastic edging on vertical edges.
2. Finishes: Selected from manufacturer’s standard available colors and patterns.
3. End panels must cover the full height and width of shelving.
M. Shelving: Four Post
ACCESSORIES
A. Surface Mount Rail (steel or stainless steel material)
B. 4.3” Touchpad LCD Control: Provide a 4.3” LCD touch screen control with display to be located on all carriages and each controls its own carriage with an easy-to-read 4.3” LCD display. PC interface software installation and setup and touchpad setup shall not be required, and a default PIN-code shall be available to turn the system on and off or make that specific carriage a stationary unit.
C. Provide Bluetooth control via the TUSC Mobile Control App or
Diagnostic in replace of or in addition to the standard powered control or touch technology system controls. Option exists to not allow system movement from local controls while connected to the TUSC
Control App. One user at a time can be connected. Connection to system will timeout via set time configuration when the apps are no longer in use.
D. TUSC Control App: Available from iOS and Android smartphone or tablet. Universal remote control to open and close aisles, enter and search for items, and view safety notifications.
E. TUSC Diagnostic App: Available from Android smartphone or tablet.
Updates systems software/firmware, configurations, and reports
10 56 26.23 - 9 diagnostics wirelessly. Communicates system status, faults, and last stops real-time. Save and send diagnostic and configuration information file via email.
F. System controls shall start motors on each movable carriage
“sequentially” to minimize power demands. (No additional hardware shall be required to change between “sequential” and “block” movement.)
G. Power Pack Override: Provide one handheld rechargeable battery pack units to operate modules in case of main power failure.
H. Automatic Brake: Provide an automatic security brake on each motorized carriage.
I.
FABRICATION
A. General: Coordinate fabrication and delivery to ensure no delay in progress of the Work.
B. Wheels: Provide precision ground units with permanently shielded and lubricated bearings.
C. Carriage Wheel Sections: Fabricate Carriage wheel sections to provide two heavy-duty 7 ga. support plates to support the full weight of shelving posts.
D. Carriage Side Profiles: Fabricate 14 ga. die-formed carriage side profiles 2-3/4 inches (70mm) tall each with four (4) shelving retention rivets.
E. Rail Shims: Fabricate galvanized steel shims with interlocking tabs to prevent dislocation; interlocking tabs to interlock with rail and with other shims. For non-grouted systems only.
F. Shelving, Supports and Accessories: See individual descriptions in
“Shelving” paragraphs.
FINISHES
A. Colors: Selected from manufacturer’s standard available colors.
B. Paint Finish: Provide factory applied electrostatic powder coat paint.
Meet or exceed specifications of the American Library Association.
C. Laminate Finish: Provide factory applied laminate panels at locations indicated on approved shop drawings.
D. Edgings: Provide preformed edging, color-matched to unit colors selected.
10 56 26.23 - 10
PART 3 - EXECUTION
EXAMINATION
A. Examine floor surfaces with Installer present for compliance with requirements for installation tolerances and other conditions affecting performance of mobile storage units.
B. Verify that building structural system is adequate for installing mobile storage units at locations indicated on approved shop drawings.
1. For installations on existing floors, ensure that rail spacings indicated on shop drawings are in proper locations so existing load-bearing structural members are not over stressed.
C. Verify that intended installation locations of mobile storage units will not interfere with, nor block established required exit paths or similar means of egress once units are installed.
D. Verify that adequate capacity permanent power sources have been installed at locations indicated on approved shop drawings.
E. Prepare written report, endorsed by Installer, listing conditions detrimental to proper performance of mobile storage units, once installed.
F. Proceed with installation only after unsatisfactory conditions have been corrected.
INSTALLATION
G. Rails:
1. Lay out rails using full-length units to the maximum extent possible. Use cut lengths only at ends to attain total length required. Locate and position properly, following dimensions indicated on approved shop drawings. Verify thickness of finished floor materials to be installed (by others) and install level
1/16 inch (1.6MM) above finished floor surfaces.
2. Verify level, allowing for a minimum 1/4 inch (6MM) of grout under high points. Position and support rails so that no movement occurs during grouting.
3. Set rails in full grout bed, completely filling any voids entire length of all rails including rail connectors. Trim up sides flush with rails to ensure proper load transfer from rail to supporting floor. Using shims in lieu of full grouting is not permitted.
4. Installation Tolerances: Do not exceed levelness of installed rails listed below:
a. Maximum Variation From True Level Within Any Module: 3/32 inch (2.4MM).
b. Maximum Variation Between Adjacent (Parallel) Rails: 1/16 inch (1.6MM), perpendicular to rail direction.
10 56 26.23 - 11
c. Maximum Variation In Height: 1/32 inch (.8MM), measured along any 10 foot (3.05M) rail length.
5. Verify rail position and level; anchor to structural floor system with anchor type and spacings indicated on approved shop drawings.
H. Floors/Ramps:
1. General: Finished elevation shall be 1/16 inch (1.6MM) below top of rails.
2. Place floors and ramps to the extent indicated on approved shop drawings. Extend ramps under all movable and stationary ranges.
Do not extend ramps beyond the ends of carriages.
3. Construct floors and ramps to prevent warping or deformation of floor panels in a normal operating environment. Support panels on levelers at maximum 16 inches (406MM) on center.
4. Ramp Slope: Do not exceed the following:
a. ADA Accessible Ramps: Maximum 1:12 slope (4.76 degrees).
b. Other Ramps: Maximum 9 degree slope (1.9:12).
c. Vertical Transition, Ramp edge to floor: Maximum 1/8 inch
(3MM).
I. Shelving Units Installation:
1. General: Follow layout and details shown on approved shop drawings and manufacturer's printed installation instructions.
Position units level, plumb; at proper location relative to adjoining units and related work.
2. Carriages:
a. Place movable carriages on rails. Ensure that all wheels track properly and centering wheels are properly seated on centering rails. Fasten multiple carriage units together to form single movable base where required.
b. Position fixed carriage units to align with movable units;
make final leveling adjustments with leveling screws.
3. Shelving Units:
a. Stabilize shelving units following manufacturer's written instructions. Reinforce shelving units to withstand the stress of movement where required and specified.
b.
4. Wiring:
a. Make final control wiring connections between modules under single control.
b. Test wiring for continuity and proper connections with regulated field power supply before making final power connections.
c. Make final wiring connections to permanent power source.
Connection to power source by others.
10 56 26.23 - 12
d. Test system operation by cycling all units through complete operations sequences.
FIELD QUALITY CONTROL
A. Verify shelving unit alignment and plumb after installation. Correct if required following manufacturer’s instructions.
B. Remove components which are chipped, scratched, or otherwise damaged and which do not match adjoining work. Replace with new, undamaged, matching units.
ADJUSTING
A. Adjust components and accessories to provide smoothly operating, visually acceptable installation.
CLEANING
B. Immediately upon completion of mobile shelving installation, clear components and surfaces. Remove surplus materials, rubbish and debris resulting from mobile shelving installation upon completion of work and leave areas of installation in neat, clean condition.
DEMONSTRATION/TRAINING
A. Schedule and conduct demonstration of installed equipment and features with Owner's personnel.
B. Schedule and conduct maintenance training with Owner's maintenance personnel. Training session should include lecture and demonstration of all maintenance and repair procedures that end user personnel would normally perform.
PROTECTION
A. Advise Owner of additional protection needed to ensure that system will be without damage or deterioration at time of substantial completion.
END OF SECTION