This document provides details for a federal contract solicitation to prepare site for nuclear medicine support space at the New Mexico VA Health Care System in Albuquerque. The solicitation will be issued by August 20, 2020 for a firm-fixed price contract valued between $100,000 to $250,000 under NAICS code 236220. The contractor shall demolish existing site elements, furnish labor and materials, and perform work including HVAC, plumbing, electrical, and architectural modifications within specified rooms in Building 41. The project must be completed within 272 calendar days of the notice to proceed. The solicitation is designated as a 100% service-disabled veteran-owned small business set-aside and responses are due by July 20, 2020. Interested parties must register in the System for Award Management and Vendor Information Pages to be eligible for award.

The second document provides responses to questions received related to the contract opportunity specifications and drawings. The responses clarify scope details such as the extent of mechanical and controls work, locations of lead shielding and access panels, and inspection requirements.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

501-20-2-675-0001 36C258-19-AP-1621

Project #501-CSI-108

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 08-18-2020

501-CSI-108

Department of Veterans Affairs NCO22-Gilbert Network Contracting 3601 S. 6th Avenue Tucson

AZ

85723 Department of Veterans Affairs NCO22-Gilbert Network Contracting 3601 S. 6th Avenue Tucson

AZ

85723 To all Offerors/Bidders

36C25820B0017 08-18-2020

X X X x The purpose of this amendment is to:

1) Attach a copy of the sign in sheet and agenda for the site visit.

2) Provide responses to all RFI's submitted via email.

3) Attach a copy of A101 Revison 3 Sheet Dated 08/10/2020

4) Attach a copy of A101 Revision 4 Sheed Dated 08/13/2020

5) Attach a copy of A610 Revision 3 Sheed Dated 08/10/2020

6) Attach a copy of MH100 Sheet Dated 08/10/2020

7) Attach a copy of original as builts

8) Attach a copy of the Specs for Access Doors and Frames

9) Attach a copy of SERIES 2 HOUR FIRE-RATED ACCESS PANEL DOUBLE DOOR John Kamerer Contracting Officer

NCO1815L2-0307

Request for Information (RFI) Log Site Preparation Nuclear Medicine Support Construction Project: 501-CSI-108 18 August 2020 New Mexico VA Health Care System (501)

RFI Number
Date
Question
Answer
001
8/08/2020
Because the cable trays are filled do we run 5 (five) new 1” conduits for power?

Cable tray and conduit maximum code allowable fill shall not be exceeded. Contractor shall provide new conduit for new devices where required.

002
8/8/2020
Where are the 2 access points for the Med gases?
Please see Sheet P-101, General Note J. Contractor shall submit coordination drawings showing all access points and clearances for approval by the VA/AE. These shall be field coordinated with existing conditions.
003
8/8/2020
The new doors that are lead lined should we plan on installing them with floor pivot hinges because of the weight?

Door 103 is not required to have lead shielding. Omit Lead lined Utility Hospital Lock. Provide Utility Hospital Lock, F9 x Paddles Pointing Down. Provide a Continuous Hinge for the weight of a 48” x 84” door leaf as required by the contract documents.

Please see the updated A-101 and A-610 sheets submitted with Revision 3 dated 08/10/2020.

004
8/8/2020
Is there asbestos in the floor glue and pipe insulation?

ACM estimated quantities are detailed in 01 00 00 Appendix B 2016 MECx assessment.

005
8/8/2020
Will this project require to use the new ceiling tile spec from the VA?

New ceiling tiles shall be provided per Specification 09 51 00 and Drawings AC101, A-531, IF101 and IF601.

006
8/8/2020
The requirement for Third Party testing, inspections, & written reports is costly to a small project. Is this required?

Yes, third-party inspections are required for all divisions.

007
8/8/2020
Will the VA be performing any of the inspections? In particular, if the GC is using 3rd party inspections, then if the 3rd party approves, then can the VA override the 3rd party approval?

The VA will not be performing third-party inspections. The VA shall provide final acceptance for all work.

008
8/8/2020
After third party inspection approval, if the VA requires reinspection or retesting, will this work be compensated as additional work to the contract?

All inspections shall be approved by the VA. Contractor shall ensure all work meets VA requirements. Any re-inspections, re-testing and work performed to correct deficiencies to the satisfaction of the VA shall be part of the Base Bid.

009
8/8/2020
Work in Room 1B-105 Plan Sheet A-100 Nuclear Medicine Note 4 says work in 1B-105 is by others. Sheet A-101 Note 9 indicates work in Room 1B-105. Please clarify if there is any work in Room 1B-105, and if so, what is the scope in this room
The Scope of Work in 1B-105 and the AHU on the first level roof on the east side of the building includes adding existing mechanical equipment to the campus Automated Logic Controls (ALC) BAS network. Per Sheet G-001, “Contractor shall provide new controls and commission existing mechanical equipment serving the Nuclear Medicine spaces, including fan coil units, terminal units, humidifier and air handling units. All devices shall be addressable and controllable via the existing ALC Bacnet control system. All existing HVAC systems impacted by the modifications shall be tested with a pre-construction TAB report and returned to original values at post-construction TAB.” Per MH101, see Key Notes 9, 10, 11 and 12 for specific equipment to added to the controls network. See 5/M-501 for existing AHU to be added to the ALC controls network.

For clarification on the extent of demolition and mechanical systems impacted, please also see the updated MH100 sheet submitted with Revision 3 dated 08/10/2020.

010
8/8/2020
Are we to include the New Mexico Gross Receipts tax within the cost of our proposal?

Bidders are to include all costs in their proposal. Refer to tax attorney.

011
8/8/2020
Sheet G-001 states, as signed by Matt Perkins “there is no lead or asbestos material designed into this project”. Please clarify this note. Is there no lead lined drywall incorporated/designed into this project?

Lead is present in the design where indicated on the plans to provide radiation shielding.

012
8/8/2020
Spec section 01 91 00 Part 3, 3.1 Are you requiring us to witness factory testing of the mechanical units?

Contractor shall submit verification of factory testing and acceptance. Witnessing factory testing is not required.

013
8/8/2020
Definition of "commissioning or recommissioning" in this sentence 01 00 00 – 1.3 (page 12 of 941) Please define what it meant with the sentence " Contractor to perform Commissioning of all new systems and existing systems impacted by the project according to requirements in sections". Are you expecting that every existing system (Div. 3-28) that is connected to these rooms be recommissioned? Who will be responsible for changes required to existing systems outside of the work clearly drawn on the construction documents?

For each division, all new construction shall be commissioned; new configuration/devices for all existing systems that are being modified shall be commissioned; and re-commissioning shall occur for existing mechanical equipment in 1B-105 and the AHU on the first level roof on the east side of the building.

For clarification on the extent of demolition and mechanical systems impacted, please also see the updated MH100 sheet submitted with Revision 3 dated 08/10/2020.

014
8/8/2020
Will Autodesk A360 Project Site be required for on site as-builts/plan revisions for this project, or can we keep red line drawings to be turned over at the end of the project?

Autodesk A360 shall be used for construction administration activities. In addition to A360, on-site redlines are acceptable, however they must be transferred to PDF and CAD formats and then uploaded to A360 for the development of record drawings.

015
8/8/2020
Concerning the ASHE statement in Spec section 01 00 00, Paragraph 1.2, C, we are confirming that we are to follow the guidelines of ASHE, and that we are not to have ASHE certified workers performing the work
ASHE guidelines shall be followed. Certification is not required for each employee.
016
8/8/2020
Plan Sheet A-101, Room 1C-103 indicate lead shielding for (L1- ½” Lead and L2 – 1/8” Lead) for the project. On Wall Types Sheet A-501 Wall type U and N receive lead shielding. The details for these wall sections include no indication in which layer of drywall where the lead is to be installed. Additionally, the plan set cover sheet G-000 certifies there is no lead designed into the project. Is there lead shielding required? if so, please indicate on the details which drywall layer will the lead shielding is to be placed.

Lead is present in the design where indicated on the plans to provide radiation shielding. Lead lining shall be installed in the locations shown on A-101 and detailed on A-501. Install lead lined Gypsum wallboard per Section 13 49 00 3.2. Detail C1/A-521 & on the Room side of 1C-103 Inpatient Pet.

Please see the updated A-101 and A-610 sheets submitted with Revision 3 dated 08/10/2020.

017
8/8/2020
Bid Form Template (pages 36 to 39 of 941) Are you expecting the GC's to provide the breakdown shown in the specifications in addition to the bid form included in the solicitation and Attachment 4 as part of our bid submission? As General Contractors typically receive their quotes within the last few minutes of the bid process, can this information be turned in after the announcement of the successful bidder?
A breakdown should be provided at time of the submission of bid however only the total bid price will be evaluated.
018
8/11/2020
Do the existing conduits have room for new wire going back to existing electrical room panels?

Cable tray and conduit maximum code allowable fill shall not be exceeded. Contractor shall provide new conduit for new devices where required.

019
8/11/2020
Please provide an as built drawing showing the location of the nurse call panel that new work will need to be tied into.

See attached as-builts from original construction. Note, actual existing conditions may have been modified since original construction and these are provided as a reference only. Contractor is responsible for field verifying all existing conditions and providing coordination drawings showing new work and existing conditions prior to commencing work.

020
08/11/2020
Will the operator for the existing double Door need to be relocated for installation of New lead lined door 103? Please refer to attached picture 8458

Yes, wall devices shall be relocated where demolition is required. Door 103 does not contain lead, please see Sheet A-610 Revision 3, 08/10/2020 for updated door schedule.

021
08/11/2020
Due to tight condition in interstitial space access panels will need to be cut into the interstitial decking please provide a structural detail and fire rating for new interstitial access.

Please see attached basis of design 1 1/2-hour rated access panel. Contractor shall install per manufacturer’s requirements to achieve the required fire rating.

022
08/11/2020
Dwg G000 Scope of work states All existing HVAC systems impacted by the modifications shall be tested with a pre-construction TAB report and returned to original values at post-construction TAB. Please provide the drawings showing the existing systems and design flows.

See attached as-builts from original construction. Note, actual existing conditions may have been modified since original construction and these are provided as a reference only. Contractor is responsible for field verifying all existing conditions and providing coordination drawings showing new work and existing conditions prior to commencing work.

023
08/11/2020
Please confirm that the contractor is to carry the cost for 3rd party Inspections.

Confirmed

024
08/11/2020
Please provides existing fire sprinkler drawings for the work area.

See attached as-builts from original construction. Note, actual existing conditions may have been modified since original construction and these are provided as a reference only. Contractor is responsible for field verifying all existing conditions and providing coordination drawings showing new work and existing conditions prior to commencing work.

025
08/11/2020
Please provide existing HVAC/Plumbing drawings for the interstitial space above area of work.

See attached as-builts from original construction. Note, actual existing conditions may have been modified since original construction and these are provided as a reference only. Contractor is responsible for field verifying all existing conditions and providing coordination drawings showing new work and existing conditions prior to commencing work.

026
08/14/2020
We had previously asked this question ( Concerning the ASHE statement in Spec section 01 00 00, Paragraph 1.2, C, we are confirming that we are to follow the guidelines of ASHE, and that we are not to have ASHE certified workers performing the work. ) but wanted to clarify that as this is a new requirement for the VA Albuquerque, will it be sufficient that there are a number of key site personnel to cover the ASHE certified worker (all labor on site) as has been presented in other projects? There is a real cost and time to get everyone tested and this would be a financial inconvenience to the project.

Work shall be performed in accordance with ASHE requirements and protocol. Certifications are not required for all employees. Key personnel are acceptable.

027
08/14/2020
When is the anticipated award of this project?

The anticipated award date of this project is between 8/31/2020 and 9/04/2020.

028
08/14/2020
Will any of the COVID19 issues have an impact on the award and subsequent NTP for this project?

There is no way of determining exactly what the restrictions will be on the go ahead for the project as we do not know what the conditions and COVID 19 requirements will be when the contract is awarded and the NTP is issued. At this time there is no anticipated impact on the award of the subject project and it is the intention of the VA to proceed with this project and schedule the NTP as appropriate.

See attached document: S04_IFB Site Visit Sign In Sheet.

See attached document: S04_Pre Proposal Tele-Conference Agenda.

See attached document: S06_08 31 13 Access Doors and Frames.

See attached document: S06_501-CSI-108_Selected Original As-Builts_reduced.

See attached document: S06_A101 R3 Sheet Updated 08102020.

See attached document: S06_A101 R4 Sheet Updated 08132020.

See attached document: S06_A610 R3 Sheet Updated 08102020.

See attached document: S06_MH100 Sheet Updated 08102020.

See attached document: S06_BA-FD2DWall.

image1.jpeg