36C25726R0012 674-22-805 Upgrade Building Automation Systems Pre-Bid RFIs.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
Y1DA--36C25726R0012, 674-22-805 Upgrading Building Automation System Temple & Waco
Solicitation number
36C25726R0012
Issued by

About this file

This file is a Pre-Bid Request for Information (RFI) Q&A document for solicitation 36C25726R0012, addressing the upgrade of Building Automation Systems at Temple and Waco facilities. The document comprises 52 questions and answers that clarify technical specifications, equipment identification, project scope, and administrative requirements. Key technical clarifications include equipment type identifications across multiple buildings (fan coil units, packaged units, pressure reducing stations, expansion tanks, and various HVAC components), confirmation that BACnet MSTP is the preferred communication method, specification that globe valves are the preferred option, and requirements to replace existing end devices with new controllers and sensors. The RFI confirms that work will involve upgrading N2 Bus HVAC control devices and wiring to MSTP protocol across multiple buildings.

The document addresses critical project logistics and staffing requirements, including that work may occur outside regular business hours to minimize facility disruption, with VA-COR coordinating access and security clearance. Administrative clarifications specify that the superintendent can serve as Quality Control Manager but must be separate from the Site Safety and Health Officer; each site requires a separate full staff of on-site personnel. The RFI confirms the project will be issued as a single contract covering both McLennan and Bell County locations with applicable prevailing wage determinations for each county, that parking will be available at no cost, and that contractors should anticipate phasing constraints with VA approval required before moving between work areas. Additional specifications address earthwork and landscaping requirements to be provided by addendum, 180-day turf establishment/maintenance periods, 365-day exterior planting establishment/maintenance periods, and commissioning commissioning responsibilities per specification 23 05 93.

View the file

Other files

File Type Posted
36C25726R0012 0008.docx DOCX document
36C25726R0012 674-22-805 Upgrade Building Automation Systems RFI Responses .pdf PDF
36C25726R0012 0007.docx DOCX document
36C25726R0012 674-22-805 Upgrade Building Automation Systems 2090_07 Building Automation Systems Addendum 01 .pdf PDF
36C25726R0012 0006.docx DOCX document
36C257-26-AP-0208-FY26-1791 JOFOC NCO17 Upgrade BAS Temple - HCA Approved_Redacted.pdf PDF
36C25726R0012 0005.docx DOCX document
Temple VAMC Map Building 46E.pdf PDF
36C25726R0012 0004.docx DOCX document
2090.07 - Building Automation Systems_Addendum 01.pdf PDF
36C25726R0012 0003.docx DOCX document
36C25726R0012 0002.docx DOCX document
36C25726R0012 674-22-805 - Pre-Bid Upgrade Building Automation System Walkthrough Waco.pdf PDF
36C25726R0012 0001.docx DOCX document
36C25726R0012 674-22-805 - Pre-Bid Upgrade Building Automation System Walkthrough Temple.pdf PDF
Attachment 3 ICRA_674-22-805 Upgrade Building Automation System.pdf PDF
Attachment 4 PCRA_674-22-805 Upgrade Building Automation System.pdf PDF
Attachment 1 674-22-805 Drawings.pdf PDF
36C25726R0012_1.docx DOCX document
Attachment 6 Waco Site Visit Map.pdf PDF
Attachment 5 Price Breakout Worksheet.xlsx XLSX spreadsheet
Attachment 2 674-22-805 Specifications.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

36C25726R0012, 674-22-805 Upgrade Building Automation Systems, Pre-Bid RFIs
Q1Is it acceptable to have multiple VAV boxes be powered by a single 24V transformer or will each VAV boxes be required to have a dedicated transformer?
A1Provide power as recommended by equipment manufacturer for VAVs.
Q2Temple BLDG 171 - Page 1-M-102 references equipment tagged F-13 & F-14. What type of equipment is this? What are the control points and sequence of operation?
A2REPLACE N2 BUS HVAC CONTROL DEVICE AND WIRING WITH MSTP AS WELL AS ALL THERMOSTATS AND SENSORS.
Q3Temple BLDG 204 - Page 1-M-104 references equipment tagged 204-VF1JK, 204-UH1JK, 204-RF1K, 204-RF1J. What type of equipment is this? What are the control points and sequence of operation?
A3204-VF1JK is SIDE WALL FAN , 204-UH1JK is a UNIT HEATER, 204-RF1K and 204-RF1J are RETURN FANS.
Q4Temple BLDG 204 - Page 1-M-106 references equipment tagged 204-SA4GS. What type of equipment is this? What are the control points and sequence of operation?
A4204-SA4GS is a DUCT SILENCER.
Q5Temple BLDG 202 - Page 1-M-108 references equipment tagged B-CV-1, B1-1, A1-1 as examples.
A5B1-1, A1-1..etc are existing DUCTED FAN COIL UNITS and B-CV-1 ...etc are CONTROL VALVE BOXES
Q6Temple BLDG 202 - Page 1-M-108 references equipment tagged FC-1. What type of equipment is this? What are the control points and sequence of operation?
A6FC-1 are existing FANCOIL UNITS
Q7Temple BLDG 202 - Page 1-M-109 references equipment tagged E3-1. What type of equipment is this? What are the control points and sequence of operation?
A7These equipments are FANCOIL UNITS.
Q8Waco BLDG 6 - Page 2-M-107 references equipment tagged 6-GU-1. What type of equipment is this? What are the control points and sequence of operation?
A8GU-1 is a packaged unit.
Q9Waco BLDG 8 - Page 2-M-110 references equipment tagged 8-AC-1. What type of equipment is this? What are the control points and sequence of operation?
A9These are SINGLE PACKAGED WATER COOLED AIR CONDITIONERS
Q10Waco BLDG 15 - Page 2-M-116 references equipment tagged PRS, SCP-1, SG-1, AS-2, SMD, ET-2. What type of equipment is this? What are the control points and sequence of operation?
A10PRS - PRESSURE REDUCING STATION, SCP - STEAM CONDENSATE PUMP, SG - STEAM GENERATOR, AS - AIR SEPERATOR, ET- EXPANSION TANK
Q11Waco BLDG 92 - Page 2-M-121 references equipment tagged 92-FC3D and 92-RH1. What type of equipment is this? What are the control points and sequence of operation?
A11FC3D - VERTICAL FAN COIL UNIT and RH1 -
Q12Waco BLDG 227 - Page 2-M-127 references equipment tagged 227-GU-1 and HVU-1. What type of equipment is this? What are the control points and sequence of operation?
A12GU - 1 are packaged units for the Green house.
Q13Waco BLDG 202 has RTUs and a MAU on the roof. Do the existing units have a BACnet card for BACnet integration?
A13No they do not have.
Q14Waco BLDG 219 has RTUs on the roof. Do the existing units have a BACnet card for BACnet integration?
A14No they do not have BACnet cards for integration
Q15Waco BLDG 226 has RTUs on the roof. Are the existing units packaged units or is it the controls contractors responsibility to provide full controls? If they are packaged units, do the existing units have a BACnet card for BACnet integration?
A15Yes they are existing units and contractor to replace the BACnet N2 Bus controls and wiring with the BACnet MSTP.
Q16Will any of the areas involved with the upgrade require after-hours support during the duration of the project?

If yes, please specify:

• Which areas will require after-hours work?

• Estimated duration and frequency of after-hours activities.

• Any special considerations for staffing or scheduling.

A16Some areas may required work to be performed outside of regular hours to minimize impact to facility operations. Frequency and duration of after hours work is variable and dependant of the operational needs of a given area that time.
Q17Will after-hours work require special building access or security clearance?
A17If so, VA-COR will coordinate access with GC
Q18Who will be responsible for coordinating access (vendor or client)?
A18VA-COR
Q19Are there any restrictions on personnel entering the premises after hours?
A19VA-COR will coordinate access with GC for any after hours work
Q20How many buildings at each site are included in the upgrade scope?
A20Reference plan. Sheet index on sheet GI000 lists sites and building #s.
Q21Provide a list of building names or identifiers for each site.
A21See response to question 20.
Q22Will all buildings be upgraded concurrently, or will the work be phased? If phased, please provide the proposed sequence and timeline.
A22Phasing plan is not part of design. Apon award the GC will submit a phasing plan and project schedule for VA approval.
Q23Identify any buildings that will not be included in the upgrade scope.
A23See response to question 20.
Q24Will the historical status of the Waco site require vendors to comply with additional regulations or restrictions?

If yes, please specify:

• Applicable guidelines or governing authorities.

• Any limitations on modifications, equipment installation, or structural changes?

A24Scope of work is not expected to impact historic status of site or buildings on campus. No additional regulations or restrictions are anticipated.
Q25If end devices (controllers, sensors, etc.) are already installed and operational, should they remain in place or be replaced?
A25Replaced with new
Q26What valve body type is recommended for this project? Are globe valves the preferred option based on VA standards or specifications?
A26Yes, globe valves are the preferred option.
Q27Per specification section 23 09 23 – 24, BACnet MS/TP is the preferred communication method for the field communications.
A27Yes, BACnet MSTP is the preferred comm. method.
Q28For the Past Performance requirement, does the Department of Veterans Affairs require that submitted projects be 100% complete, or may projects that are substantially complete be considered acceptable for evaluation?
A28Per A.4. Proposal Preparation Instructions 2. Volume Specific Submittal Instructions Paragraph b., "Offerors are to submit information relating to up to three projects valued at least $10,000,000.00, it has completed within the last three years." This means "100%" complete.
Q29Will work be permitted to occur at both locations simultaneously?
A29Yes
Q30Will separate individuals be required to fill roles as on-site personnel staff at each project site?
A30Refer Q31 response below.
Q31Do the roles of SSHO, Superintendent, and QCM need to be filled by 3 separate individuals? Or can the same individual serve simultaneously as 2 or more of these positions?
A31Per 01 45 00, 3.4.B, the superintendent can also be QCM, but not SSHO. Per 01 35 26, 1.7.C, "...the SSHO has to be a separate qualified individual from the Prime Conttractor's Superintendent and/or Quality Control Manager with duties only as the SSHO."
Q32Will each site need a separate full staff of on-site personnel?
A32Yes
Q33Earthwork will be required for new duct bank installation but no specification section is included. Please provide a specification section for the earthwork.
A33Earthwork specification to be provided with Addendum 01
Q34Landscaping will be required for new duct bank installation but no specification section is included. Please provide a specification section for the landscape.
A34Arch.: 32 90 00 PLANTING section to be added by addendum 01.
Q35In areas disturbed by construction, is grass to be restored using seed or sod?
A35Arch. Requirements for both methods are indicated in 31 20 11 EARTHWORK (SHORT FORM) to be added by addenda.
Q36Is the contractor responsible for watering and maintenance of landscape work for an establishment period after approval? If so, what is the duration assumed for the establishment period?
A36Establishment/maintenance period for turf must continue for a minimum period of 180 calendar days after install, with weekly inspections and full maintenance (mowing, irrigation, fertilization, weed control) during that time.

Establishment/maintenance period for exterior planting must continue for a minimum period of 365 calendar days after install, with weekly inspections and full maintenance (mowing, irrigation, fertilization, weed control) during that time.

Q37Is the contractor to provide Max-cell innerduct in all new exterior UG fiber pathways?
A37Alternate products to be considered, post-bid and during the submittal process.
Q38Please confirm, will this entire contract be issued under a single contract?
A38Yes
Q39If issued as one contract, which prevailing wage/pay scale applies — McLennan County or Bell County?
A39Both wage determinations are applicable for the work conducted in the specific county. The wage determinations were inserted into solicitation and current wage determinations are provided with 36C25726R0012 Amendment 4.
Q40Please confirm, all work is to be done on regular hours between 8 am and 4:30 pm?
A40Some areas may required work to be performed outside of regular hours to minimize impact to facility operations
Q41Will parking be available for contractors free of charge?
A41Yes
Q42Will hard plastic barriers suffice as adequate infection control, or is the contractor required to construct temporary gypsum walls?
A42Safety Requirements specification indicates 1-hour temporary gypsum walls and doors as required for access; VA may amend these requirements on case-by-case basis.
Q43Are HEPA carts sufficient for any above-ceiling work in corridors?
A43Yes, asuming that all open ceiling is contain within the HEPA cart
Q44Please confirm, are all new power circuits to be removed and replaced?
A44Design intent is to demolish existing mechanical systems throughout areas of scope and reuse power circuits as possible. Where a greater quantity of circuits are required in the new work, new circuits shall be pulled from nearby electrical panels with spare capacity as indicated on the elctrical drawings.
Q45Please confirm, are all panelboards existing with spare capacity? Will the contractor be required to provide any new panels?
A45Refer to A44.
Q46Can one contractor perform both the controls work as well as integration, or must these be two separate contractors?
A46Spur does not see an issue with this - up to the bidding contractors how they want to write their scopes.
Q47Is it the responsibility of the contractor to hire the CxA for commissioning of the new upgrades?
A47Reference spec 23 05 93.
Q48Is the contractor required to provide an on-site SIOR to oversee inspections?
A48Contractor is not required to provide a third party SIOR for this project.
Q49Is the contractor responsible for hiring a 3rd party firestopping inspector as part of this project?
A49Reference spec 01 45 29 Third-party inspection responsibilities indicated in 07 84 00 FIRETOPPING, to be added by addenda.
Q50With the project work areas spanning throughout various buildings / areas at each facility, what should the contractor anticipate as far as phasing constraints when moving throughout the work areas?
A50Phasing plan not part of design.
Q51For bidding purposes, approximately how many rooms / work areas should the contractor anticipate having access to at a time?
A51Phasing plan not part of design.
Q52Will the contractor be required to complete all work in each work area and obtain VA approval prior to moving on to the next area?
A52Typically yes. However, exceptions may be approved by the VA on a case by case basis.