Summary of SF 1442 Block #17 Price Sheet - Food & Nutrition Renovation

This is a pricing schedule for a federal construction contract to renovate the food and nutrition facility at the G.V. (Sonny) Montgomery VA Medical Center (GVSMVAMC) in Jackson, Mississippi. The contractor must furnish all supervision, labor, materials, tools, and equipment to complete the work in accordance with project plans and specifications.

The contract structure includes a mandatory base award on Line Item 1 (either 1A or 1B) combined with Line Item 2. Line Item 1 addresses the temporary kitchen requirement for 12 months (365 days) with two pricing options: 1A for a leased temporary kitchen (monthly cost) or 1B for a fabricated temporary kitchen (fixed 12-month price). Line Item 2 covers all renovation work except temporary kitchen costs, with a 540-calendar-day performance period, and requires offerors to provide a detailed price breakdown by specification divisions. Three alternates are available if funding constraints require modifications: Alternate 1 (Line Item 3) eliminates four work tables; Alternate 2 (Line Item 4) removes work tables and tray cart replacements; and Alternate 3 (Line Item 5) removes work tables and replaces the rack-type dish machine. Award hierarchy dictates Line Item 1(A or B) & 2 first, followed by Lines 1(A or B) & 3, then 1(A or B) & 4, and finally 1(A or B) & 5, based on available funding. Line Item 6 is an optional extension providing temporary kitchen services for an additional 6 months (180 days) with the same lease or fabricate pricing options and will not be awarded with the base contract.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION OF SF 1442 BLOCK # 17- PRICE SHEET

DESCRIPTION OF WORK: Contractor shall furnish all supervision, labor, material, tools, and equipment to renovate food and nutrition as specified herein at the G.V. (Sonny) Montgomery

VA Medical Center (GVSMVACM) located at 2002 Woodrow Wilson Avenue, Jackson, MS. All work shall be performed in accordance with the project plans and specifications.

BASIS OF AWARD: A single award will be made on Line Item 1(A or B) and 2, but in the event the offer exceeds the funds available, a single award will be made on Line-Item No. 1(A or B) & 3, Line-Item No. 1(A or B) & 4, or Line-Item No. 1(A or B) & 5, in that order, based on available funding. Offerors shall provide a total contract price on each line item listed. The project’s period of performance is reflected in each line item. Line Item No. 6 is an option and will not be awarded with the base contract.

LINE-ITEM NO. 1: Includes all work as indicated on the drawings and the specifications regarding the lease or fabricated temporary kitchen, including removal, for Renovate Food &

Nutrition at GVSMVAMC. The temporary kitchen period of performance is 12 months/365days.

TOTAL NO. 1A Lease Temporary Kitchen cost per month $_________________/month

TOTAL NO. 1B Fabricated Temporary Kitchen for 12 month duration $______________

LINE-ITEM NO. 2: Includes all work as indicated on the drawings and the specifications, except the lease or fabricated temporary kitchen cost, for Renovate Food & Nutrition at GVSMVAMC.

The project period of performance is 540 calendar days.

TOTAL NO. 2 $ _________________________________*

*Offeror shall complete a price breakdown by Specification Divisions as shown on page #5.

LINE-ITEM NO. 3: Alternate #1- Includes all work as indicated on the drawings and specifications for Line Item No. 2, except eliminate (4) work tables. Reference K101 and K201A in the drawings for details. The project period of performance is 540 calendar days.

TOTAL NO.3 (Line Item # 2- Alternate 1) $_________________________________

LINE-ITEM NO. 4: Alternate #2- Includes all work as indicated on the drawings and specifications for Line Item No. 2, except the items listed in line item #3 and eliminate replacing tray carts. Reference K101 and K200A drawings for details. The project period of performance is 540 calendar days.

TOTAL NO. 4 (Line Item # 2- (Alternate 1 + Alternate 2):$____________________________

LINE-ITEM NO. 5: Alternate #3- Includes all work as indicated on the drawings and specifications for Line Item No. 2, except the items listed in line items #3, and #4, and eliminate rack type dish machine. Reference K101, K200A, K300A, and K401A in the drawings for details

The project period of performance is 540 calendar days.

TOTAL NO. 5 (Line Item # 2- (Alternate 1 + Alternate 2 + Alternate 3):$________________

LINE-ITEM NO. 6 (Option): Includes all work as indicated on the drawings and the specifications regarding the lease or fabricated temporary kitchen, including removal, for Renovate Food & Nutrition at GVSMVAMC. The temporary kitchen option period of performance is 6 months/180 days. Note: Line item No. 6 is an option and will not be awarded in the base contract.

TOTAL NO. 6A Lease Temporary Kitchen cost per month $_________________/month**

TOTAL NO. 6B Fabricated Temporary Kitchen for 6 month duration $______________ **

**The option year pricing shall also be used if the options clause 52.217-8 is exercised to extend the agreement 6 months.