RFIs PART II FOOD AND NUTRITION.pdf

PDF 97 KB Posted

Attached to
Y1DZ | 586-22-104 | RENOVATE NUTRITION AND FOOD SERVICE KITCHEN | SOLICATION- AMEND 005
Solicitation number
36C25626R0011
Issued by

About this file

Summary of RFI #1 - Food & Nutrition Temporary Kitchen Project

This document is a Request for Information (RFI) and corresponding VA responses regarding a temporary kitchen facility project at a VA medical facility in Jackson. The RFI addresses critical clarifications on design details, site conditions, equipment specifications, operational logistics, utility provisions, and work scope definitions necessary for accurate contractor bidding on the temporary kitchen lease and installation.

Key issues addressed include: clarification that Detail 2/AE721 shows wall protection extent with approximately 40'-5" framed wall length at Corridor 109, and that cooler/freezer dimensions may vary by manufacturer; confirmation that site prep is part of the project and the existing VA grease trap service contract will continue quarterly pumping; establishment that all existing quarry tile should be assumed over a 1" mortar bed except for a 4" bed at noted locations; requirement that vendors propose equipment relocation plans minimizing downtime to less than one week; confirmation that utilities (power, HVAC, gas) are provided by the VA for the temporary kitchen; clarification that grease trap permits are the only City of Jackson interaction required; specification that Line Item 4 addresses Equipment Item #55 (meal tray delivery carts) and Line Item 5 addresses the flight-type dish machine with deduct alternates for rack-type substitution; requirement for onsite supervision during any extended six-month lease periods; direction that all prep work costs be included as lump sum pricing; payment methodology based on work percentages completed; and designation of temporary work for removal versus permanent work to be restored to previous conditions, with trenches maintained and covered throughout construction.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI #

Food & Nutr

Item

PAGE AE721

DETAIL 2 and DETAIL 6

AE101

Detail 6 is showing the freezer is 40 ft 5 in long. We notice an arrow on each side of the detail. We assume this indicates that the CT4 tile runs past the shown area. Please clarify exactly how long the wall is.

Detail 2 has the same arrows. Please clarify how long that wall will be also. Secondly, On Page AE101 we have looked and looked for this detail and we have not been able to locate it. Please clarify where this detail is on that page.

RFI 008

The question asked if the existing site is level within a 3" variance. The VA response did not address this question. Will the VA please confirm whether the existing site can be assumed to be level within a 3" variance?

RFI 080

The response places responsibility for emptying the temporary grease trap on the contractor. If this will be the contractor’s responsibility, the VA will need to provide information regarding the current service schedule for the grease trap so contractors can estimate the cost appropriately. Contractors are not typically involved in food service operations and do not have a basis to estimate the amount of grease generated from approximately 450 meals per day. Will the VA please provide the current service frequency or any available historical data regarding grease trap servicing?

RFI 087

The VA response states to assume all quarry tile is installed over a 1" mortar bed except where noted in Note 2.17. However, the General Notes on sheet AD101, Note B, states: “Remove existing ceramic floor throughout area of work, presume 3" grout bed unless noted otherwise.”

The difference between filling and sloping a 1" mortar bed and a 3" mortar bed is a significant cost difference. Will the VA please clarify which depth contractors should assume for bidding purposes?

RFI 110

The VA’s response states that kitchen functions must remain operational at all times. However, the existing kitchen equipment cannot remain operational in the current kitchen while also being disconnected, relocated, and reinstalled in the temporary kitchen simultaneously. At some point the contractor will need to disconnect and remove the existing equipment and relocate it to the temporary kitchen.

rition- RFIs Part II

This relocation work will likely require up to a week to complete, but definitely more than one or two nights. During this period, the kitchen equipment will be unavailable for meal preparation.

Please clarify what the VA’s plan is for maintaining meal service while the contractor disconnects, relocates, and reinstalls the existing kitchen equipment in the temporary kitchen?

I see temporary power is provided, but what about power to run HVAC and gas for heat? Are those to be metered as the specs state or are they free as well?

Will the City of Jackson be handling inspections since we are getting a building a permit? The women's clinic the question was asked in amendment #3 and the city would not be issuing a permit and handling inspections. Same building and same jurisdiction, why are they different?

Line Item No. 4 indicates the elimination of tray carts. Is this referring to Equipment Item #55 – Meal Tray Delivery Carts (Qty. 12)?

Line Item No. 5 states to eliminate the rack-type dish machine. The only dish machine listed in the new kitchen equipment is Equipment Item #60 – Flight Type Dish Machine. Please clarify whether Line Item No. 5 is eliminating the Flight Type Dish Machine or if the contractor should disregard Line Item No. 5.

Line Item No. 6 states to exercise FAR Clause 52.217-8 to extend the kitchen lease an additional six (6) months. If the kitchen is to remain onsite for an additional six months, should the contractor assume that supervision will also be required onsite for the same six-month period to oversee the rented temporary kitchen?

Pricing Location for Prep Work Should all of the above “prep work” costs be included within:

The prep work is largely front-loaded and not a monthly cost, so we want to confirm if the intent is to distribute this cost across the monthly pricing or include it within the lump sum durations.

oLine Item 1A (monthly lease cost),
oLine Item 1B (12-month fabricated cost),
oLine Item 6A (lease option), and
oLine Item 6B (fabricated option)?

Billing of Prep Work Since this work would be completed at the beginning of the project, is it acceptable for it to be billed based on progress (Schedule of Values) even if it is included within the temporary kitchen line items?

Temporary vs. Permanent Work For items such as sewer connections and trenching:

oAre these intended to be temporary and removed at the end of the project, or
oPermanent installations that remain in place after the temporary kitchen is removed?

Trench Protection / Final Condition For temporary sewer runs:

oShould trenches remain covered with steel plates for the duration, or
oShould they be backfilled and restored (concrete/asphalt) as permanent work?

Line item #5

Response

Detail 2/AE721 is a typical elevation noted at the Room Finish Schedule on sheet AE601 (see KT-1 and Note 1 below the schedule). The break marks at the edge of the detail indicate a continuation of this condition. Both details are to illustrate the extent of wall protection in relation to the finishes. The framed wall at Corridor 109 is approximately 40'- 5", as dimensioned, and is intended to align with the far side of the cooler (see details 10 and 11 on AE401), which may vary in lengths based on the selected cooler/freezer manufacturer and the clearances required by the manufacturer.

The bidders performed a site visit and site prep is part of this project.

The VA service contract pumps out the grease trap quarterly. The service contract will continue to empty the greas trap unless the temp kitchen has a vendor issue.

Bidders can assume all existing quarry tile is over a 1" mortar bed except where noted on AD101, not 2.17, which can be assumed to have a 4" mortar bed.

The vendor is to propose a move plan that minimizes down time. A week will not be acceptable from any vendor.

The utilities are provided by the VA for the temporary kitchen.

Permit for Grease trap will be the only interaction with the City of Jackson

Correct.

Flight type dish machine. M101:1. MODIFY: Note 7 to read “DISHWASHER HOOD. PROVDE MANUAL BACKDRAFT DAMPER. BASE BID CONNECTION TO FLIGHT DISHWASHER TO BE 16” DIA, REFER TO MANUFACTURERS SPECIFICATIONS. DEDUCT ALTERNATE CONNECTION TO DISHWASHER TO BE TEO 4”x16” DUCTS AT EACH END OF THE UNIT, REFER TO MANUFACTERERS SPECIFICATIONS. “ 2. MODIFY : Ductwork layout in dishwasher room. E201

1. MODIFY: Note 22 “DEDUCT ALTERNATE 3 : INCLUDES ALL WORK AS INDICATED ON THE DRAWINGS AND SPECIFICATIONS EXCEPT THE ITEMS LISTED IN DEDUCT ALTERNATE #2, AND #3 (REFER TO GI000 COVER SHEET) EXCEPT: INSTALL RACK-TYPE DISH MACHINE IN LIEU OF FLIGHT-TYPE DISH MACHINE. PROVIDE ONE 480V-3P-3W 90A CONNECTION TO RACK-TYPE DISH WASHER. PROVIDE ONE 100A NEMA 4 DISCONNECT SWITCH. OMIT FLIGHT- TYPE DISH MACHINE CONNECTION.” E204: 1. MODIFY: Note 17 “DEDUCT ALTERNATE 5 : INCLUDES ALL WORK AS INDICATED ON THE DRAWINGS AND SPECIFICATIONS EXCEPT THE ITEMS LISTED IN DEDUCT ALTERNATE #2, AND Page 4 of 4 10/31/2025 #3 (REFER TO GI000 COVER SHEET) EXCEPT: INSTALL RACK-TYPE DISH MACHINE IN LIEU OF FLIGHT-TYPE DISH MACHINE. PROVIDE ONE 480V-3P-3W 90A CONNECTION TO RACK-TYPE DISH WASHER.

PROVIDE 3- #3 CU, 1-#8 G IN 1.5"C. OMIT FLIGHT-TYPE DISH MACHINE CONNECTION.” E603: 1. MODIFY: note 23

If the kitchen is on site for an additional 6 months that indicated the construction is still going on and therefore supervision must be on site.

Prep work to be lump sum.

We will pay for work installed and completed based on percentages.

Follow the plans for temp VS construction. Temp will need to be removed at the end of construction

Trenches shall be maintained and covered for temp work . Permament areas will be returned to previous conditon at the end of consstruction.

PP101:

1. MODIFY: note

“WORK IN THIS AREA SHALL BE COORDINATED WITH DEDUCT ALTERNATE 5.

PIPE CONNECTIONS AND FLOOR DRAINS MAY SHIFT FOR NEW DISH MACHINE.

Sheet1