This document is an Amendment (Modification Number 0005) to Solicitation 36C25525R0097 for the Department of Veterans Affairs, specifically a project to replace various Air Handling Units (AHUs) and Chillers in Buildings 1, 24, and 51 at a VA facility. The amendment addresses multiple Request for Information (RFI) clarifications, including detailed specifications for temporary cooling arrangements during construction, steam trap configurations, and electrical connection requirements for new AHUs.

Key technical details include replacing four specific AHUs: two in Building 1 (7,000 CFM Trane CSHX0035F3), one in Building 24 (10,000 CFM Trane CSH0050F4), and one in Building 51 (12,800 CFM Trane RSHX0080), all with electric heat and specific electrical requirements. The amendment provides guidance on temporary power connections from 208V panels, steam trap specifications using Spirax Sarco FT450-4.5 traps, and clarification on morgue operations during construction. The proposal response deadline is 8/12/2025 at 10:00 AM Central Time, with the project administered by the Department of Veterans Affairs Network Contracting Office in Leavenworth, Kansas.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 08-05-2025

657-23-101JB

36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048 To all Offerors/Bidders

36C25525R0097

X X X X The purpose of this amendment is to publish the answers to additional clarification.

The due date for proposals remains 8/12/2025 at 10:00 AM Central Time.

Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of the offer.

Jennifer Hill Contracting Officer NCO 15

CONTINUATION PAGE

1. RFI #65. Can the morgue be shut down during construction? Providing temp cooling for that area to the degree required will be between difficult and impossible. If the shutdown is not possible, can you please provide clarification on how temp cooling for that area is to be accomplished so we can properly price this scope? Including the size and placement of temp unit/units that will achieve the appropriate temperatures?

We don't use the JB morgue too often. Most patients that pass at JB go directly to the funeral home. The morgue is only used with the veteran does not have funeral home plans in place. The backup plan is the patient will be transported to JC morgue until funeral home arrangements are made.

1. RFI #70. Sizing the temp units based on a preconstruction TAB report will not enable us to provide the proper pricing for our scope of work. This information needs to be available for us to include the correct pricing at the time of our bid…not after we are awarded the project. Otherwise, it becomes and guess which usually drives the price up.

AHU-01-1 – Trane CSHX0035F3 (OR EQUIVALENT) (with electric heat), 7000 CFM Nominal, 5in Max ESP, 460V 3 Phase, MCA 179.8A, MOP 200A. Note: The contractor shall coordinate required electrical connection with the VA.

AHU-01-2 – Trane CSHX0035F3 (OR EQUIVALENT) (with electric heat), 7000 CFM Nominal, 5in Max ESP, 460V 3 Phase, MCA 179.8A, MOP 200A. Note: The contractor shall coordinate required electrical connection with the VA.

AHU-24-1 – Trane CSH0050F4 (OR EQUIVALENT) (with electric heat), 10000 CFM nominal, 5in Max ESP, 460V 3 Phase, MCA 232.2A, MOP 250A. Note: 460V unavailable at building 24. The contractor shall coordinate required electrical connection with the VA..

AHU-51-1 – Trane RSHX0080 (OR EQUIVALENT) (with electric heat), 12,800 CFM nominal, 4.8in Max ESP, 460V 3 Phase, MCA 329A, MOP 400A Note: 460V unavailable at building 24. The contractor shall coordinate required electrical connection with the VA. If alternate is used, unit must have adequate capacity for DOAS application.

The needs of the station and the temporary units are based on availability. The information provided is to ensure the contractor understands the situation and the need to ensure a maintenance team/ plan is made available by the subcontractor to avoid any issues with the temporary cooling during construction.

Power can be provided to the temporary units as follows:

0. Building 1: Feed the temporary AHU from 208V panel “EMDP”. Provide temporary transformer and connections as necessary.

0. Building 24: Feed the temporary AHU from 208V “External Wireway”. Provide temporary transformer and connections as necessary.

0. Building 51: Feed the temporary AHU from 208V switchboard “MSB-51A”. Provide temporary transformer and connections as necessary.

1. RFI #72, 73 & 108. We need the design team to provide the proper information on the steam trap sizing and placement. Including the traps at the units and any drip traps that might be required. This is a complicated issue that would need to be designed….by the design team….not the installing contractor. Drip traps are generally based on the pounds per hour capacity of the main. This information is not available to us.

Steam trap to be placed at the unit steam coil / humidifier.

Anticipated piping lengths do not require steam drip traps. Contractor to verify and report the piping lengths from steam mains.

STEAM TRAP SCHEDULE BASIS OF DESIGN

MANUFACTURER
TRAP NO.
TRAP SIZE
MAX PRESSURE (PSI)
STEAM CONDENSATE LOAD
CONSTRUCTION
AHU-1-01 HEATING COIL
SPIRAX SARCO
FT450-4.5
1"
15
217
STAINLESS STEEL
AHU-1-02 HEATING COIL
SPIRAX SARCO
FT450-4.5
1"
15
276
STAINLESS STEEL
AHU-24-01 HEATING COIL
SPIRAX SARCO
FT450-4.5
1-1/2"
15
466
STAINLESS STEEL
AHU-51-01 HUMIDIFER
SPIRAX SARCO
FT450-4.5
3/4"
15
23
STAINLESS STEEL

NOTE: STEAM TRAP CONNECTION SHALL BE RAISED FACE FLANGE.

Additional Information regarding RFIs 97 and 100:

3C06 As builts and site photos:

Condensate pumps in basement mechanical room GC18:

Location of the Steam supply and condensate return riser main connection to horizontal main.

No as-built of the steam condensate pump is available in Building 1, Room GC18. The steam riser main is 2-1/2” and the condensate return riser main is 2” based on as-built drawings available as noted above.