Install Animal Research Air Handler PN 589A4-17-181
Solicitation number
36C25518R0511
Issued by

About this file

36C25518R0511 SPECIFICATIONS- ANIMAL RESEARCH AHU -PAGES 827.pdf

View the file

Other files

File Type Posted
36C25518R0511-0001005.pdf PDF
36C25518R0511-0001002.pdf PDF
36C25518R0511-0001000.docx DOCX document
36C25518R0511-0001003.pdf PDF
36C25518R0511-0001001.docx DOCX document
36C25518R0511-0001004.pdf PDF
36C25518R0511-0001006.pdf PDF
36C25518R0511-001.docx DOCX document
36C25518R0511-003.pdf PDF
36C25518R0511-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Install Animal

Research Air Handler

Harry S. Truman

Memorial Veterans’

Hospital Columbia, Missouri

Specifications: Divisions 00 – 28 project manual no.:

VA project no.: 589A4-17-181 M+HFG project no.: H VA COLU 17101 issue date: June 22, 2018

M+HFG, LLC

142 North Mosley Street

Wichita, Kansas 67202 ggonzales Stamp

VA PROJECT NO. 589A4-17-181 02-01-16

TABLE OF CONTENTS – VOLUME 1

00 01 10.1-1

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 10 Table of Contents 02-16

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 10-17

01 00 10 Medical Center Requirements 03-16

01 33 23 Shop Drawings, Product Data, and Samples 05-17

01 35 26 Safety Requirements 02-17

01 42 19 Reference Standards 05-16

01 45 29 Testing Laboratory Services 06-15

01 57 19 Temporary Environmental Controls 01-11

01 74 19 Construction Waste Management 09-13

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 02-15

DIVISION 03 – CONCRETE – NOT USED

DIVISION 04 – MASONRY – NOT USED

DIVISION 05 – METALS - NOT USED

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES – NOT USED

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 02-16

DIVISION 08 – OPENINGS – NOT USED

08 11 13 Hollow Metal Doors and Frames 01-13

08 71 00 Door Hardware 01-16

DIVISION 09 – FINISHES

09 51 00 Acoustical Ceilings 12-16

09 91 00 Painting 01-16

00 01 10.1-2

DIVISION 10 – SPECIALTIES – NOT USED

DIVISION 11 – EQUIPMENT – NOT USED

DIVISION 12 – FURNISHINGS – NOT USED

DIVISION 13 - SPECIAL CONSTRUCTION – NOT USED

DIVISION 14– CONVEYING EQUIPEMENT – NOT USED

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16

22 05 12 General Motor Requirements for Plumbing Equipment 09-15

22 05 19 Meters and Gages for Plumbing Piping 09-15

22 05 23 General-Duty Valves for Plumbing Piping 09-15

22 07 11 Plumbing Insulation 09-15

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 09-15

22 13 00 Facility Sanitary and Vent Piping 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

08-17

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15

23 07 11 HVAC and Boiler Plant Insulation 02-15

23 08 00 Commissioning of HVAC Systems 11-16

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 08-17 23 22 13 Steam and Condensate Heating Piping 08-17

23 23 00 Refrigerant Piping 02-15

23 31 00 HVAC Ducts and Casings 03-13

23 36 00 Air Terminal Units 02-15

23 37 00 Air Outlets and Inlets 02-15

23 40 00 HVAC Air Cleaning Devices 02-12

23 73 00 Indoor Central-Station Air-Handling Units 04-11

23 82 16 Air Coils 04-11

00 01 10.1-3

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 05-14

26 05 73 Overcurrent Protective Device Coordination Study 12-15

26 08 00 Commissioning of Electrical Systems 11-16

26 27 26 Wiring Devices 01-16

26 29 11 Motor Controllers 08-14

26 29 21 Enclosed Switches and Circuit Breakers 01-17

26 51 00 Interior Lighting 08-14

DIVISION 27 - COMMUNICATIONS

27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 09-11

28 05 13 Conductors and Cables for Electronic Safety and

Security

09-11

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK – NOT USED

DIVISION 32 – EXTERIOR IMPROVEMENTS – NOT USED

DIVISION 33 – UTILITIES – NOT USED

DIVISION 34 – TRANSPORTATION – NOT USED

DIVISION 48 – Electrical Power Generation – NOT USED

VA PROJECT NO. 589A4-17-181

07-01-15

LIST OF DRAWING SHEET

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI-100 Title Sheet

GI-101 Life Safety Plan

GI-102 Phasing Plan

GI-103 Phasing Plan

GI-104 Phasing Plan

ARCHITECTURAL

AD-100 Demolition Plans

AS-100 Floor Plan

AS-101 Finish & Door Schedule

FIRE PROTECTION

FP101 Fire Protection Plan

PLUMBING

PP001 Plumbing Cover Sheet

PL101 Plumbing Floor Plans

HEATING, VENTILATING, AIR

CONDITIONING

MM001 Mechanical Cover Sheet

MM002 Mechanical Cover Sheet

MD101 Mechanical Demolition Plans

MD102 Mechanical Demolition Plans

MD103 Mechanical Demolition Plans

MD104 Hydronic Demolition Plans

MH101 HVAC Supply Plans

MH102 HVAC Supply Plans

MH103 HVAC Supply Plans

MH104 HVAC Exhaust Plans

07-01-15

LIST OF DRAWING SHEET

00 01 15 - 2

MH105 HVAC Exhaust Plans

MH106 HVAC Exhaust Plans

MH107 HVAC Supply Air Rebalance Plan

MH108 HVAC Exhaust Air Rebalance Plan

MP101 Hydronic Plans

MP102 Hydronic Plan – Pipe Basement

M-501 Mechanical Details

M-502 Mechanical Details

M-503 Mechanical Details

M-511 Mechanical Controls

M-512 Mechanical Controls

M-601 Mechanical Schedules

M-602 Mechanical Schedules

M-801 Airflow Diagram

ELECTRICAL

E-001 Electrical Symbols and Schedules

E-101 Partial Electrical Floor Plans

E-102 Partial Electrical Floor Plans

E-103 Partial Electrical Floor Plans

E-104 Partial Electrical Floor Plans

E-105 Partial Electrical Floor Plans

E-501 Electrical Details

- - - END - - -

VA Project No.589A4-17-181 10-01-17 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 PERIOD OF PERFORMANCE

1.5 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.6 CONSTRUCTION SECURITY REQUIREMENTS

1.7 OPERATIONS AND STORAGE AREAS

1.8 ALTERATIONS

1.9 DISPOSAL AND RETENTION

1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

1.11 RESTORATION

1.12 LAYOUT OF WORK

1.13 AS-BUILT DRAWINGS

1.14 USE OF ROADWAYS

1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.16 TEMPORARY TOILETS

1.17 AVAILABILITY AND USE OF UTILITY SERVICES

1.18 TESTS

1.19 INSTRUCTIONS

1.20 GOVERNMENT-FURNISHED PROPERTY

1.21 RELOCATED EQUIPMENT and other ITEMS

1.22 HISTORIC PRESERVATION

1.23 PROJECT MANAGEMENT SOFTWARE

VA Project No. 589A4-17-181 10-01-17

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of portions of existing structures, and furnish labor and materials and perform work for VA Project No.

589A4-17-181, Install Animal Research Air Handler as required by drawings and specifications.

B. Only one (1) site visit will be schedule prior to the bid date.

Attendance is highly recommended.

C. Offices of M+HFG, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by

Contracting Officer or his duly authorized representative. The A/E information is as follows:

M+HFG Architecture

142 N. Mosley, Suite 300

Wichita, KS 67204

316-262-2500

Contact Person: Mark Crane

D. Throughout the drawings and specifications, references to Contracting

Officer shall be represented by the abbreviation “CO”. References to

Resident Engineer, Contracting Officer’s Technical Representative or

Contracting Officer’s Representative shall be represented by the abbreviation “COR”. The COR for this project shall be Ryan Brown.

01 00 00 -2

E. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

F. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. BID ITEM 1: Includes all scope communicated in the drawings and specifications. A new air handling unit shall be installed within the

Animal Research area. The air handler with terminal units will serve the Animal Research rooms only to meet VA Guidelines and will include a heat recover heating water coil, steam heating coil, DX cooling coil, humidification and filtration. The rooms within the scope of work will reconnect to the existing exhaust fan to provide required room pressurization. The mechanical room will be enlarging to make these changes possible. There will be minimal other architectural changes.

B. BID ITEM 2 (Deduct 1): All work in bid item 1 with the following exceptions:

1. The heat recovery piping from the existing heat recovery coil in the pipe basement to the new air handler, AHU-30, shall be removed. The heat recovery heating coil will remain in the air handler for future connection.

1.4 PERIOD OF PERFORMANCE

A. The Period of Performance for this project shall be 180 calendar days for Bid Item 1 and Bid Item 2. The period of performance begins on the date of Notice to Proceed, and includes submittal review and product procurement, all construction services required, all punch list items reconciled, and ending once close-out services have been completed, and close-out documents have been distributed to the owner, including as-built drawings.

01 00 00 -3

B. The Period of Performance of specific phases, based on the time a designated portion of the building is released to the contractor until that portion is accepted by the owner, is as follows:

1. Phase 1A: 16 weeks

2. Phase 1B: 3 weeks

3. Phase 2A: 1 weeks

4. Phase 2B: 2 weeks

4. Phase 3: 3 weeks

1.5 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.6 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

01 00 00 -4

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

01 00 00 -5

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.7 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

C. Working space and space available for storing materials shall be located within the project limits as shown on the drawings.

D. Workmen are subject to rules of Medical Center applicable to their conduct.

01 00 00 -6

E. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Provide unobstructed access to Medical Center areas required to remain in operation.

F. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

To insure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to

Medical Center Director, COR and Contractor, as follows: Reference drawings for phasing plans.

G. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced

01 00 00 -7 at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by COR.

H. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

I. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. . It is the contractor’s responsibility to provide temporary utility hook ups in order to minimize any utility down times. Prior to any utility outages the contractor must provide a utility shut down request to the COR with a description of the proposed outage outlining the expected down time and actions that will be taken to minimize impact on the facility. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center

Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL

INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS

01 00 00 -8

INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC

SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours. Interruptions occurring at other than

Contractor's normal working hours shall be at no additional cost to the government.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR. Major utility outages may have to be done on off hours to minimize the impact on the facility.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

K. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

01 00 00 -9

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

M. Contractor shall have a supervisor on site at any/all time(s) that any contractor personnel or sub-contractor personnel are performing work of any kind. Submit this supervisor’s qualifications to COR in writing for approval before work begins. At the beginning of the job, supervisor shall meet with COR first thing first day in the COR’s office. Any time there is a lapse of one or more days (other than weekends/holidays) in contractor working on site, supervisor shall meet with COR in the

COTR’s office first thing first day back on the job.

N. Contractor’s on-site supervisor shall meet with COR early each day at a time mutually acceptable for the purpose of discussing the work to be performed that day. This meeting shall be held at the COR’s office or other mutually agreeable location. If contractor’s project manager is on-site daily then he/she shall attend these daily meetings. If contractor’s project manager is not on-site daily then he/she shall be available for a once-a-week meeting at the COR’s office.

O. The Contractor's on-site supervisor must be provided with a pager or cellular phone to ensure continuous contact by VA representatives while on the job site. This pager or cellular phone number must be provided to the COR at the Pre-Construction Meeting. This pager or cellular phone must use a Columbia, Missouri, local telephone number or a toll-free number (1-800-xxxx, 1-888-xxxx, etc.) and NOT require VA to initiate long distance telephone service in order to be reached.

P. The Contractor's employees, as well as his/her subcontractors' employees shall be provided with identification badges and/or parking pass hang tags by VA. All contractor and sub-contractor employees must wear an identification badge at all times that the employee is on VA premises. These badges and/or hangtags shall be returned to VA upon completion of the contract/project. A charge of $10.00 each shall be assessed for any and all badges and/or hangtags not returned. This charge shall be made in the form of a deduct change order to the contract or bill of collection, at the option of the CO.

01 00 00 -10

Q. The Contractor's Foreman shall, if/as necessary, be issued VA keys.

These keys shall be returned to VA upon completion of the contract/project. If the Contractor fails to return any issued keys, the actual costs of re-keying all doors which use that key and/or replacing/reissuing keys to all personnel that possess that key shall be charged to the Contractor. Depending upon the number of doors and keys involved this could range from $100 to several thousand dollars.

This charge shall be made in the form of a deduct change order to the contract or bill of collection, at the option of the CO.

R. The Contractor's normal working hours will be Monday through Friday from 7:30 am to 4:00 pm.

1. Regularly scheduled federal holidays are: New Years Day, Martin

Luther King's Birthday, Presidents Day, Memorial Day, Independence

Day, Labor Day, Columbus Day, Veterans' Day, Thanksgiving, and

Christmas. No work will be permitted on any regularly scheduled federal holiday. No work will be permitted on any non-regularly scheduled holiday, whether the holiday comes about by Presidential decree, by Congressional decree, or by any other manner.

2. For convenience of the Government, portions of the work must be accomplished after weekday business hours and/or on weekends.

Reference drawings for locations and times available to perform the work indicated.

3. In the event that it becomes necessary for the Contractor to work outside the normal business hours of the facility for reasons not determined to be for the convenience of the Government, said work will only be performed upon the approval of the CO. The Contractor will be assessed the overtime rate for all facility staff required to be present, who otherwise wouldn't be present, as deemed necessary by the CO. The contractor shall notify the COR 48 hours prior to performing the work.

4. The Contractor is required to discontinue his work in sufficient time to allow for his clean up of all work areas before he leaves the site each workday. The area shall be returned to "normal condition" for VA use at the end of each workday, including proper secure storage of all equipment, tools, and materials, and the removal of all construction debris.

01 00 00 -11

S. Contractor shall turn in completed and signed daily logs no later than

11:00AM on the following workday.

T. Location of parking is subject to VA approval and may be revoked at any time for any reason at no cost to the government. Job office trailers will not be allowed.

U. All metal cutting operations shall be performed in locations approved by COR. All metal shavings must be removed from VA premises completely.

1.8 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of the site in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list the following:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR

, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.

Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4 and VAAR 852.236-88).

01 00 00 -12

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings and site involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and any other items noted on the condition re-survey report as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such items, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.9 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

01 00 00 -13

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

01 00 00 -14

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.11 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2). ) of GENERAL CONDITIONS. These repairs shall be performed as soon as is practical.

1.12 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The

Contractor shall furnish, at Contractor's own expense, templates, platforms, equipment, tools, materials, and labor required to lay out

01 00 00 -15 any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

1.13 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.14 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

01 00 00 -16

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

01 00 00 -17

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.16 TEMPORARY TOILETS

A*. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.17 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. Electricity (for Construction and Testing):

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

C. Water (for Construction and Testing):

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

01 00 00 -18

1.18 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.

Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, automatic door operatior is one part of a system which includes controls, sensors and door mechanisms.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.19 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

01 00 00 -19

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned

Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.

This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual

01 00 00 -20 requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR , does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.20 GOVERNMENT-FURNISHED PROPERTY

A. Not used.

1.21 RELOCATED EQUIPMENT AND OTHER ITEMS

A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated by symbol "R" or otherwise shown to be relocated by the Contractor.

B. Perform relocation of such items at such times and in such a manner as directed by the COR.

C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".

D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated items; and leave such itemsin proper operating condition.

E. All service lines such as noted above for relocated items shall be in place at point of relocation ready for use before any existing item is disconnected. Make relocated existing items ready for operation or use immediately after reinstallation.

1.22 HISTORIC PRESERVATION

Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.

1.23 PROJECT MANAGEMENT SOFTWARE

Reference section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.- - -

01 00 00 -21

E N D - - -

03-02-16

MEDICAL CENTER REQUIREMENTS

01 00 10-1

SECTION 01 00 10

MEDICAL CENTER REQUIREMENTS

1.0 GENERAL INTENTION: This document pertains to station policy for construction projects performed at the Harry S Truman Memorial Veterans' Hospital (HSTMVH) in Columbia, MO. Safety and health concerns are taken seriously at this facility. Both our staff and yours are expected to strictly adhere to the regulations and requirements. This is exceedingly important, since we must be primarily concerned for the safety of our patients. In this regard, OSHA Standards may protect worker safety and health, but they have minimal benefit for protecting the safety and health of our patients, due primarily to their differing medical conditions.

Review this information as orientation with your personnel performing work on site. Where the requirements as outlined in this and Section 01 00 00 are differing, the more stringent shall apply.

2.0 REQUIREMENTS:

A. Security:

1. Secure all construction areas, especially mechanical and electrical rooms against entry of unauthorized individuals including patients.

2. Notify the CO’s Technical Representative (COTR) for permission to work after hours and weekends. Standard work hours for this project will be Monday through Friday from 7:30 am to 4:00 pm.

B. Key Security:

1. Only a limited number of keys will be issued to the contractor.

2. See section 01 00 00 for procedures in case the Contractor loses a key.

3. Ensure all doors leading to and from construction are either monitored or locked to prevent access to the area from unauthorized persons.

C. General Safety:

1. Follow all federal, state and local safety and health regulations.

2. Maintain safety in the construction site/area in accordance with the provisions of the contract that includes the Occupational Safety and Health Administration (OSHA) Regulations; National Electrical Codes;

National Fire Protection Association (NFPA) 70, National Electric Code; and NFPA 101, Life Safety Code. Work in a safe manner and take all proper precautions while performing your work. Extra precautions shall be taken when working around persons occupying the building during construction.

3. Provide Personal Protective Equipment (PPE) for your employees.

4. Post appropriate signs in specific hazardous areas.

5. Keep tools, ladders, etc., away from patients to prevent injuries.

D. Safety Inspections: The professional Occupational Safety and Health staff at this facility will perform safety inspections of all contract

MEDICAL CENTER REQUIREMENTS

01 00 10-2 operations. Written reports of unsafe practices or conditions will be reported to the COTR and CO for immediate attention and resolution.

E. Fire Alarms:

1. The fire alarm system connects all buildings at this facility, and is activated by various heat, duct, manual pull…