36C25226Q0359 0003.docx

DOCX document 41 KB Posted

Attached to
J059--Triennial Electical Panel Maintenance and Survey Federal contract opportunity
Solicitation number
36C25226Q0359
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

This is a Questions and Answers document (Amendment 0003) for Solicitation 36C25226Q0359, issued by the Department of Veterans Affairs Great Lakes Acquisition Center on June 24, 2026, extending the offer due date to July 7, 2026 at 6:00 p.m. CDT. The amendment provides clarifications on the scope of work for triennial electrical panel maintenance and survey services at Jesse Brown VAMC in Chicago.

The contract involves comprehensive electrical testing and maintenance across approximately 258 electrical panels at the facility over a three-year base period. Key services include visual inspection and oil sampling for MV transformers (6 per year for 3 years starting with the Bed Tower Building), testing of 301 LV circuit breakers and 39 MV circuit breakers with quantities varying by building per the Building Schedule, circuit tracing for all switches/outlets/receptacles served by panels, panel schedule updates in editable PDF and Excel format using NETA-formatted templates, infrared surveys, and NEC compliance verification using 2017 NEC standards with only major deficiencies reported. The contractor must provide before-and-after digital photos (photos only required for equipment with issues), draft reports within 30 days of completing work per building, and final reports within 15 days of receiving VA comments. All outage/shutdown work must be completed after-hours per Section 6.2 of the Statement of Work. The contract is structured as a firm fixed price award with work organized by building schedule across the base year and option years. Services excluded from scope include relay testing, ATS testing, MV cable testing, primary current injection testing for LV circuit breakers, and repairs (which are handled as separate corrective work items). Standard VA contractor requirements apply to all personnel regardless of work location, including TB testing and background screening.

View the file

Other files for this federal contract opportunity

Other files attached to J059--Triennial Electical Panel Maintenance and Survey, newest first.
File Type Posted
S02 - Substations and Switchgears.xlsx XLSX spreadsheet
36C25226Q0359 0004.docx DOCX document
S02 - Taylor bldg.pdf PDF
S02 - One Line Diagram - No Bedtower.pdf PDF
S02 - Damen bldg.pdf PDF
S02 - Atrium.pdf PDF
S02 - Ogden bldg.pdf PDF
S02 - Bed Tower One Line Diagram.pdf PDF
S02 - Bed Tower bldg.pdf PDF
36C25226Q0359 0002.docx DOCX document
36C25226Q0359 0001.docx DOCX document
S02 - WD 2015-5017 R 32 D 3.30.26.pdf PDF
S02 - Taylor Panel Breaker Survey.xlsx XLSX spreadsheet
S02 - Damen 1-A Panel Breaker Survey.xlsx XLSX spreadsheet
S02 - Building 21-26-27 Panel Breaker Survey.xlsx XLSX spreadsheet
S02 - Electrical Units 3Y Maintenance Total number of brakers.xlsx XLSX spreadsheet
S02 - Damen 1-C Panel Breaker Survey.xlsx XLSX spreadsheet
S02 - -Atrium Panel Breaker Survey.xlsx XLSX spreadsheet
S02 - -Bed Tower Panel Breaker Survey r1.xlsx XLSX spreadsheet
S02 - Building Schedule.docx DOCX document
S02 - Temp Building Panel Breaker Survey.xlsx XLSX spreadsheet
S02 - Building 42 Panel Breaker Survey.xlsx XLSX spreadsheet
36C25226Q0359.docx DOCX document
S02 - Ogden Panel Breaker Survey.xlsx XLSX spreadsheet
S02 - Damen 1-B Panel Breaker Survey.xlsx XLSX spreadsheet
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and answers in response to 36C25226Q0359

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority)

THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 06-24-2026 Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 Department of Veterans Affairs 36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders

36C25226Q0359 05-14-2026

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 07-0

-2026 6:00 CDT

See CONTINUATION Page X

ONE

Reference Solicitation 36C25226Q0359 for Panel Survey and Maintenance at Jesse Brown VAMC

The purpose of this amendment is to provide reponses to questions from interested vendors.

Additionally, to extend the Offers Due Date to the date and time listed in Box 11.

All other terms and conditions remain in effect.

Derrick Paquette Contracting Officer

A.1 Questions and Responses

1
Q:
Please provide the latest test report (I'm referring to the electrical test report, not the Arc Flash study report).
R:
The requested report is not available.
2
Q:
In the section “4. PERFORMANCE OBJECTIVES,” it was reported that there are 248 electrical panels to update the panel schedule, and a request was made to include up to 10 additional panels in buildings 1, 1A, 1B, 1C, 11A, 11B, 21, 26, 27, 30, 40, and the Temp Building. Should we consider the potential for up to 10 additional panels in each of the mentioned buildings? That is, 248 + 120 = 368 panels?
R:
The 10 additional panels is for the whole facility. The total including estimated panels is 258 panels.
3
Q:
It's clear that equipment that doesn't show any problems doesn't need a written report and infrared photo, but is it really necessary to provide a digital photo of equipment that isn't showing any problems? This would imply a longer reporting time and higher costs. Typically, equipment without problems is simply listed as: normal condition (without any photos being added to the report).
R:
Digital photos are only required on equipment with issues.
4
Q:
Will the transformers only undergo visual inspection and oil sampling, meaning no electrical tests such as Polarization Index, Excitation Current, Turns Ratio, Insulation, and Winding Resistance?
R:
Only visual inspection and oil sampling is required for transformers
5
Q:
What type of maintenance should be performed on dry-type transformers?
R:
Only Visual inspection and infrared on dry-type transformers
6
Q:
Do LV circuit breakers need to undergo electrical testing?
R:
No, LV circuit breakers do not need to undergo electrical testing.
7
Q:
The tables in the spreadsheet "S02 - Electrical Units 3Y Maintenance Total number of breakers" are a bit confusing. Can you confirm if the contractor will need to test (301) LV circuit breakers and (39) MV circuit breakers in total? Specify the numbers per contract year (i.e., the quantity for items 0002, 1001, and 2001).
R:
Yes, all LV and MV breakers need to be tested. The number of items being tested will vary by building. The schedule of buildings is found in the attachment titled “Building Schedule”
8
Q:
Will the contractor test a total of (18) MV Transformers? Specify the numbers per contract year (i.e., the quantity for items 0002, 1001, and 2001).
R:
Yes, Starting with Bed tower Building, 6MV Transformers, e.a per 3 Years life of the contract
9
Q:
Will the contractor test a total of (39) MV ATSs? Specify the numbers per contract year (i.e., the quantity for items 0002, 1001, and 2001).
R:
ATS, are not included
10
Q:
Do any relays need to be tested? How many?
R:
Relays, are not included
11
Q:
If the relays need testing, please specify whether they are single-phase or three-phase.
R:
Relays, are not included
12
Q:
In the Panel Survey we will consider (248) panels + 10 additional ones. In the Panel Maintenance (triennial) should we consider around (590) panels?
R:
The 10 additional panels is for the whole facility. The total including estimated panels is 258 panels.
13
Q:
Why is this not a SDVOSB set aside? There are several of us that compete for this work consistently.
R:
Market Research was conducted and a lack of responses from SDVOSBs in the area of being interested and capable lead to the determination to not set this aside for SDVOSBs
14
Q:
Some of the buildings only show the breakers and transformers, but the scope of work lists several other items like mcc, switchgear and switchboards, relays, and groundings? Can we get the info and counts for these items?
R:
All information requested has been provided in the Excel spreadsheets
15
Q:
In the scope of work, it lists buildings by numbers but in the excel sheet the buildings are listed by names. Can we confirm which building is what for Ogden, Taylor, Bedtower, and Damen?
R:
Information is shown in both ways. Ogden is 11B, Taylor A, Bed Tower 40, Damen is 1A, 1B, and 1C
16
Q:
Do you have any previous test results to share?
R:
The requested report is not available.
17
Q:
There are several ATS listed throughout the buildings, but the scope of work doesn't list ATS services. Is that accurate?
R:
References to ATS are for informational purposes only
18
Q:
Is there no MV cable testing?
R:
MV cable testing is not included
19
Q:
Can we confirm the relay counts by building?
R:
Relays are in the SOW for reference only
20
Q:
Any drawings would greatly help with the project.
R:
Available drawings have been provided but may have some undocumented variations
21
Q:
Please provide the existing panel schedules, floor plans, as-built drawings, and any available receptacle/switch layout drawings for the buildings included in the panel survey.
R:
Panel Schedules are not available. Floor plans are attached, as built drawings, receptacle/switch layout drawings for the buildings included in the panel survey are not available.
22
Q:
Please confirm whether circuit tracing is required for every switch, outlet, and receptacle served by all approximately 248 panels, or only for unlabeled/unknown circuits.
R:
Circuit tracing is required for every switch, outlet, and receptacle served by all approximately 248 panels
23
Q:
Please confirm whether the Contractor must physically access every room, ceiling space, and above-ceiling area to identify conduits and abandoned electrical infrastructure
R:
Contractor will need to access any room needed while performing tasks defined in the SOW.
24
Q:
Please provide the estimated quantity of switches, outlets, receptacles, hard-wired equipment, and abandoned conduits/pipes to be traced, labeled, or documented.
R:
This information is not available
25
Q:
Please clarify the requirement to “prove, test, and certify panels to be reliable and meet NEC compliance.” Does this require full electrical testing, visual inspection only, or a specific checklist/standard?
R:
Visual inspection to confirm NEC compliance
26
Q:
Please confirm whether removal of abandoned wiring/conduit is included in the base scope, or if it will be handled as a separate repair/corrective work item with separate approval.
R:
This will be handled as separate corrective work
27
Q:
Please provide the Building Schedule Attachment and/or equipment inventory referenced in the SOW, including exact equipment quantities by building (for scope section 4.2)
R:
Excel spread sheets with available information are attached
28
Q:
Please clarify the building list discrepancy. Buildings 5, 30, and 32 appear in the Building Schedule but are not listed in SOW Section 4.2.1, while Buildings 20 and 22 are listed in the SOW but do not appear in the year-by-year Building Schedule.
R:
BLDG 5, 30 and 32 shall be included in the SOW. There is no physical structure for BLDG 20, only transformers are standing on the ground exposed to the outside environment
29
Q:
Per VHA Directive 1028, low-voltage circuit breakers rated 225A and above typically require primary current injection testing. Please confirm whether primary current injection testing is required for this project, or if secondary injection testing is acceptable.
R:
Primary current injection testing is required for this project
30
Q:
Can testing for MV liquid-filled transformers be limited to oil sampling and visual inspection?
R:
Yes
31
Q:
The Period of Performance is listed as Monday–Friday, 0700–1630. Please confirm whether all outage work will be completed during normal business hours.
R:
As listed in Section 6.2 of the SOW, All outages/shutdowns be completed after-hours
32
Q:
Who was the incumbent contractor, and what was the previous contract value?
R:
This requirement has not previously been awarded
33
Q:
Can the Government provide the previous contract number(s) for the triennial electrical testing services?
R:
This requirement has not previously been awarded
34
Q:
I would like to ask what are the Option Years for? I am assuming that the entire triannual testing will not be completed in the base year, so the option years are there to assist?
R:
Correct, see the attached Building Schedule to determine what is due in each option year.
35
Q:
Is this statement instructing the contractor to account for 10 additional panels per building referenced? Or, as per verbal discussion at site visit, is it meant to instruct the contractor to account for 10 additional panels across all of the listed buildings, so account for 258 total panels to be surveyed?
R:
The 10 additional panels is for the whole facility. The total including estimated panels is 258 panels.
36
Q:
In order to accurately and efficiently determine equipment served by circuits, some energized work will likely be required to meet schedules. Is there current guidance from Jesse Brown VAMC regarding what is considered intrusive and what is not?
R:
There is no current guidance from Jesse Brown VAMC regarding what is considered intrusive and what is not. The contractor must coordinate activities very closely with the COR and the electrical department.
37
Q:
Are there any drawings available to aid in the performance of the panel survey?
R:
Available drawings have been provided but may have some undocumented variations
38
Q:
SOW §8.2 states the VA will furnish one-line drawings 'not certified as-built' and that the contractor will provide red-line updates. Please confirm: (a) format the red-line updates must be returned in (Visio, AutoCAD, Bluebeam), and (b) whether the VA will provide native CAD files or only PDF for markup
R:
The one-line drawings are not available yet. When they become available, they will be provided.
39
Q:
Section 4.1.1 states that in course of electrical panel survey, that each panel is to be proven to be reliable per the NEC. What revision year?

This contract is over a three year period. If ‘the current revision’ is the desired answer, that standard will fundamentally change in scope and applicability before this contract expires. E.g. Panels that met the 2026 NEC during an inspection performed in 2027 could fail by 2029 NEC standards, making the contractor delinquent in performing their scope if ‘the current NEC’ is the answer.

1.) If sufficiently older panels are inspected, it is possible that major changes would become contractually necessary to otherwise functioning and safe equipment if new code revisions are used to evaluate panels older than 10 years in age.

2.) Recommend using the 2017 NEC as that is the revision currently being used by Chicago.

R:
1) No, only report major deficiencies,

2) Use 2017 NEC standards

40
Q:
Per section 2, “From this RFQ, the Government intends to award a firm fixed price contract where the contractor provides a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract”

1. Attempting to deliver a FFP quote in tracing all branch circuits in panelboards in occupied, decades-old buildings, to the extent outlined in the SOW, is impractical to determine. Does the government then consider extra time spent delivering the performance objectives in accurately determining equipment served, retired circuits, etc. to be cost experienced by the contractor in performing the contract?

2. Would submitting a NTE T&M price be preferable? Or would meeting the objectives for the panel survey to the maximum extent practicable within a quoted FFP be preferable?

R:
This shall be a Firm Fixed Price Award.
41
Q:
SOW 9.1.6 requires updated panel schedules be provided in 'editable PDF and Excel.' Please confirm whether the VA has a preferred panel schedule template, or whether the contractor's standard NETA-formatted schedule with VA branding is acceptable.
R:
Contractor's standard NETA-formatted schedule with VA branding is acceptable
42
Q:
SOW 2.1.5 requires 'facility-approved adhesive labels.' Please confirm: (a) the approval authority (COR, Facility Engineer, Safety Office), (b) the lead time to approve a label spec, and (c) any color, material, or wording standards the labels must conform to.
R:
Labels shall be UL-approved and locally approved by the COR
43
Q:
SOW 7.0 references VA-provided escorts in restricted areas. Please confirm: (a) availability of escorts during nights and weekends when most shutdowns will occur, (b) any cost recovery for escort hours, and (c) the badging path and lead time for new contractor personnel (PIV / non-PIV).
R:
a) escorts will be provided as needed within 24 hrs written notice to the electrical supervisor, before accessing restricted areas.

b) No cost recovery

c) Estimated to be 3 days, Engineering – team can assist

44
Q:
SOW 3.0 places repair of identified defects outside the contract scope but requires the contractor to provide written cost estimates. Please confirm the expected turn-around time for the VA to authorize repairs (so we can plan whether the same crew will return for the repair, or whether a separate mobilization is required).
R:
For these repairs, they will be handled on a case-by-case basis
45
Q:
For the IR survey portion of the scope,

1. Are there any requirements on infrared camera specs?

2. Are all panelboards, switchboards, switchgear, transformers, etc. across all buildings to be surveyed each option year? Or are surveyed items per year to be determined by Attachment S02 – Building Schedule, Work by Period of performance?

R:
1. No, there not any requirements on infrared camera specs

2. Yes, The survey is during the base year, maintenance shall follow the attached schedule

46
Q:
SOW 9.0 requires draft reports within 30 days of completing work at each building and final reports within 15 days of receiving VA comments. Please confirm: (a) whether one report per building is required, or one consolidated annual report, and (b) the preferred electronic delivery method (SharePoint, email, share-drive path).
R:
a) One report will be needed per building

b) Electronic delivery – Share point

47
Q:
SOW 9.0 requires before-and-after digital photos of each component tested. Please confirm: (a) any minimum resolution standard, (b) the photo storage / delivery medium (USB, SharePoint, secure FTP), and (c) whether facility security has restrictions on cameras in patient care areas.
R:
There are restrictions on cameras in patient care areas; other than no pictures are allowed where patients are.
48
Q:
VHA Directive 1192 (influenza) and standard VA contractor requirements (TB testing, background screening) typically apply to clinical-area work. Please confirm: (a) which categories of testing/screening are required for contractor personnel performing this work, and (b) whether the requirements differ for personnel only in mechanical / electrical rooms versus those in patient-care areas.
R:
The same standard will apply to all. Work will be performed throughout the facility in a variety of locations on any given day.

A.2 Amendment Attachments

· Atrium.

· Bed Tower bldg.

· Bed Tower One Line Diagram.

· Damen bldg.

· Ogden bldg.

· One Line Diagram - No Bedtower.

· Taylor bldg.

File details come from the government source that posted it. Updated .