S06 - Att 2 Pre-Bid RFIs Response 20240118.pdf
PDF 425 KB Posted
- Solicitation number
- 36C25224B0004
About this file
This document contains responses to pre-bid questions for a federal construction project to fix Legionella deficiencies at the Tomah Veterans Affairs Medical Center in Wisconsin. The project involves renovations to building corridors and patient rooms, including installation of one-hour fire-rated barriers when fire suppression or alarm systems are impacted. Overnight work will generally be required in corridors unless an alternative plan is approved. Shutdowns require seven days' notice. The superintendent cannot serve as quality control but may also be the safety officer. Bids must be submitted via mail rather than email to the attention of specified recipients by the closing date. Subcontracting limitations will follow guidance in the solicitation rather than a separate form.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
No. RFI From COMMENT Response
DAX Contracting Solutions, LLC
Can proposals be emailed? If so, whom should we email them too?
NO - Mail hard copy of proposal in to Attn of Lynn Vander Velde and Ryan McMillin
DAX Contracting Solutions, LLC
Is this project tax-exempt? not tax exempt
DAX Contracting Solutions, LLC
Can the Superintendent double hat as quality control or site safety? Super can be Saftey also but not Quality Control.
DAX Contracting Solutions, LLC
Can the Superintendent triple hat as quality control and site safety? NO Superintendent can not also be quality control
DAX Contracting Solutions, LLC
Are we required to complete one phase prior to moving onto another?
Phasing plan will need to be approved prior to work being started. Separate crews may work on different phases if it is not affecting patients and staff or creating a delay to the current phase.
DAX Contracting Solutions, LLC
Are overnights required for work in corridors? yes unless worked out with the COR on the phasing plan
DAX Contracting Solutions, LLC
Confirming shutdowns require 7 days notice. 7 Days is needed to notify VA staff
DAX Contracting Solutions, LLC
Are we required to work in 16 lineal foot sections throughout corridors and patient rooms? yes unless worked out with the COR
DAX Contracting Solutions, LLC
Are the ICRA barrier required to be 1-hour rated?
If the fire supression or the fire alarm is taken down then yes a 1 hour barrier will be needed if not no.
DAX Contracting Solutions, LLC
Are the ICRA barriers going to the structure above or to the bottom of ceiling? to the bottom of the ceiling.
11 RHI, LLC Can bids be submitted via email?
NO - Mail hard copy of proposal in to Attn of Lynn Vander Velde and Ryan McMillin
12 RHI, LLC
Will a ‘Limitations on Subcontracting’ form be provided or should the 852.219-75 section in the solicitation be used?
Provide the information in the 852.219-75 section of the solicitation.
Tomah VAMC Fix Legionella Deficiencies (C) 36C25224B0004 676-22-101
Pre-Bid RFIs
S06 - Att 2 Pre-Bid RFIs Response 20240118 1 of 1