S06 - Att 2 Pre-Bid RFIs Response 20240118.pdf

PDF 425 KB Posted

Attached to
Z1DA--Fix Legionella Deficiencies Construction Project 676-22-101
Solicitation number
36C25224B0004
Issued by

About this file

This document contains responses to pre-bid questions for a federal construction project to fix Legionella deficiencies at the Tomah Veterans Affairs Medical Center in Wisconsin. The project involves renovations to building corridors and patient rooms, including installation of one-hour fire-rated barriers when fire suppression or alarm systems are impacted. Overnight work will generally be required in corridors unless an alternative plan is approved. Shutdowns require seven days' notice. The superintendent cannot serve as quality control but may also be the safety officer. Bids must be submitted via mail rather than email to the attention of specified recipients by the closing date. Subcontracting limitations will follow guidance in the solicitation rather than a separate form.

View the file

Other files

File Type Posted
S06 - Att 3 Wage Determination Update WI20240011 20240621.pdf PDF
S06 - Att 1 Update VAH Directive 1061 2 Amended 20240304.pdf PDF
S06 - Att 2 Site visit sign in sheet 20240605.pdf PDF
36C25224B0004 0005.docx DOCX document
S06 - Att 4 Pre-Bid RFIs 20240521.pdf PDF
S06 - Att 2 Updated SOW rev-3 20240523.pdf PDF
S06 - Att 1 Updated Bid Schedule 20240523.pdf PDF
S06 - Att 5 Wage Determination Update WI20240011 20240517.pdf PDF
36C25224B0004 0004.docx DOCX document
S06 - Att 3 Updated Submittal Specs Rev-1 20240523.pdf PDF
36C25224B0004 0003.docx DOCX document
S06 - Att 1 Pre-Bid RFIs 20240319.pdf PDF
36C25224B0004 0002.docx DOCX document
S06 - Att 2 Wage Determination WI20240011 20240215.pdf PDF
S06 - Att 1 Safety Record.pdf PDF
S06 - Att 1 Sign-in sheet 20231227.pdf PDF
S06 - Att 3 Wage Determination WI20240011 20240105.pdf PDF
36C25224B0004 0001.docx DOCX document
S02 - Att 6 VHA Directive 1061 D 2021-02-16.pdf PDF
S02 - Att 9 Wage Determination WI20230011 20231215.pdf PDF
S02 - Att 5 Fix Legionella_BD Submittal Drawings Set 3 of 3.pdf PDF
S02 - Att 3 Fix Legionella_BD Submittal Drawings Set 1 of 3.pdf PDF
S02 - Att 7 Armstrong sole source.pdf PDF
S02 - Att 1 SOW rev-2 Fix Legionella Deficiency_s 676-22-101.pdf PDF
36C25224B0004_1.docx DOCX document
S02 - Att 2 Fix Legionella_BD Submittal Specs 20231129.pdf PDF
S02 - Att 8 SANIWARE SMS sole source.pdf PDF
S02 - Att 4 Fix Legionella_BD Submittal Drawings Set 2 of 3.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. RFI From COMMENT Response

DAX Contracting Solutions, LLC

Can proposals be emailed? If so, whom should we email them too?

NO - Mail hard copy of proposal in to Attn of Lynn Vander Velde and Ryan McMillin

DAX Contracting Solutions, LLC

Is this project tax-exempt? not tax exempt

DAX Contracting Solutions, LLC

Can the Superintendent double hat as quality control or site safety? Super can be Saftey also but not Quality Control.

DAX Contracting Solutions, LLC

Can the Superintendent triple hat as quality control and site safety? NO Superintendent can not also be quality control

DAX Contracting Solutions, LLC

Are we required to complete one phase prior to moving onto another?

Phasing plan will need to be approved prior to work being started. Separate crews may work on different phases if it is not affecting patients and staff or creating a delay to the current phase.

DAX Contracting Solutions, LLC

Are overnights required for work in corridors? yes unless worked out with the COR on the phasing plan

DAX Contracting Solutions, LLC

Confirming shutdowns require 7 days notice. 7 Days is needed to notify VA staff

DAX Contracting Solutions, LLC

Are we required to work in 16 lineal foot sections throughout corridors and patient rooms? yes unless worked out with the COR

DAX Contracting Solutions, LLC

Are the ICRA barrier required to be 1-hour rated?

If the fire supression or the fire alarm is taken down then yes a 1 hour barrier will be needed if not no.

DAX Contracting Solutions, LLC

Are the ICRA barriers going to the structure above or to the bottom of ceiling? to the bottom of the ceiling.

11 RHI, LLC Can bids be submitted via email?

NO - Mail hard copy of proposal in to Attn of Lynn Vander Velde and Ryan McMillin

12 RHI, LLC

Will a ‘Limitations on Subcontracting’ form be provided or should the 852.219-75 section in the solicitation be used?

Provide the information in the 852.219-75 section of the solicitation.

Tomah VAMC Fix Legionella Deficiencies (C) 36C25224B0004 676-22-101

Pre-Bid RFIs

S06 - Att 2 Pre-Bid RFIs Response 20240118 1 of 1