This document is a Pre-Construction Risk Assessment (PCRA) template for the Department of Veterans Affairs to assess safety risks associated with construction, renovation, and maintenance projects. The template provides instructions and tables to categorize the type of activity and determine appropriate control measures based on factors such as work duration and potential hazards. It also includes sections to identify adjacent areas that could be impacted and determine if an Infection Control Risk Assessment is required.
The specific project addressed in this PCRA is the repair of waterproofing deficiencies and damage in the North Campus steam tunnel between Buildings 7 and 43 at a VA medical center. It involves work exceeding six months to repair the steam tunnel. Control measures identified include excavation, dust, and pollution prevention plans, as well as requirements for crane lifts, fall protection, and confined space entry. An ICRA is also required for this project.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VHA Pre-Construction Risk Assessment (PCRA)
VHA-PCRA-2023-1.0 Page 1 of 10
PCRA Introductory Information and Instructions
Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.
Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.
Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.
Facilities may customize this template to incorporate site-specific information and requirements.
NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.
PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.
Activity Location:
Activity Name, Number, and/or Brief Description:
Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures
NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.
Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).
As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.
Activity Type determined from Table 1:
Large Scale
North Campus Steam Tunnel (Between Bldgs. 7 & 43)
695-21-110: Repair North Campus Steam Tunnel; Repair waterproofing deficiencies and damage done by past water infiltration events.
VHA-PCRA-2023-1.0 Page 2 of 10
Table 1: Every question must be answered with an “X” answering if part of project (yes or no).
If “Yes” is answered as part of project, the work is the type noted – inspect/upkeep, small scale or large scale. Always default to the highest category.
Activity Type and Description
Part of Project
(Yes or No) Actions Taken Inspect/ Upkeep
Small Scale
Const / Renov
Large Scale Const /Renov
Yes No
Work can be completed in a single shift, not to exceed 10 hours.
- Patients, employees and/or visitors may be in the area depending on the activity.
- Work that does not create dust or debris.
- Work that does not create vapors or fumes.
X
Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.
X
- Prolonged work that may take longer than a single shift but not exceeding six months.
- Patients and employees are not to be in the area until activity is completed.
X Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.
X
- Work exceeding six months.
- Patients and employees are not to be in the area until activity is completed.
Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.
X
Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited exposure time (not to exceed an hour for each tile) within the shift.
X
Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
X
Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.
X Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
X
Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.
X
Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the shop involved must work with Safety to ensure proper precautions are in place
X
Work will impact egress routes (corridors, stairwells, exit distances, etc.)
X An ILSM is required and staff training (VA Safety).
Exit signage changes (contractor).
X X
Work will impact traffic flow requiring alternate routes.
X Signage changes.
X X
Security (site security, access control, etc.)
Card readers for all construction areas, chain link fences around site, etc.
X X
VHA-PCRA-2023-1.0 Page 3 of 10
Activity Type and Description
Part of Project
(Yes or No) Actions Taken Inspect/ Upkeep
Small Scale
Const / Renov
Large Scale Const /Renov
Yes No
Work that creates some noise and vibration due to power tool use.
Excessive noise and vibration producing work is scheduled off normal working hours, weekends, Federal Holidays.
X X
VA phone available at work site (for emergency use)
X Install jobsite phone (contractor to run wire). VA IT will install phone.
X X
Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may
- create the potential for falling objects
Ensure area under and around work area is cordoned off.
X X
Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may
- create vibration and/or noise in excess of 80 dB(A) in surrounding areas.
X Excessive noise and vibration producting work is scheduled off normal working hours, weekends, Federal Holidays. X X
Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may
- cause penetrations in fire or smoke barrier
X Infection Control Plan in place, ICRA Permit in place.
X X
Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may
- disturb asbestos
X ACM abatement plan and monitoring per specification.
Infection control barriers and negative air HEPA units are installed (dust control plan).
ICRA Permit in place.
X X
Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural
- disturb lead
X Lead abatement plan and
Infection control barriers and negative air HEPA units are installed (dust control plan).
ICRA Permit in place.
X X
Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural
- disturb Silica
X Silica removal plan and
Infection control barriers and negative air HEPA units are installed (dust control plan).
ICRA Permit in place.
X X
VHA-PCRA-2023-1.0 Page 4 of 10
Activity Type and Description
Part of Project
(Yes or No) Actions Taken Inspect/ Upkeep
Small Scale
Const / Renov
Large Scale Const /Renov
Yes No
Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:
- LOTO
- The use of compressed gas cylinders
X Coordinate outages 3 weeks in advance, provide temporary utilities as required, LOTO procedures in place and staff trained on their use.
After piping/work is complete, run water lines affected for 10 minutes and complete flushing logs.
X
Plumbing work requiring LOTO and system shutdown and startup such as the installation of:
- new medical gas systems,
- steam/heating hot water, condensate systems,
- Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.
utilities as required, LOTO procedures in place and staff trained on their use.
Recertification procedures for medical gas systems.
After piping/work is complete, run water lines affected for 10 minutes and complete flushing logs.
X
Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc.
Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.
coordinate outages 3 weeks in utilities as required, LOTO procedures in place and staff trained on their use. X
Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc.
requiring LOTO and system isolation.
Coordinate outages 3 weeks in utilities as required, LOTO procedures in place and staff trained on their use.
X
Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:
- Work on ladders
- Rigging, hoisting or lifting of equipment or materials overhead utilities as required, LOTO procedures in place and staff trained on their use. X
Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.
X coordinate outages 3 weeks in utilities as required, LOTO procedures in place and staff trained on their use.
VHA-PCRA-2023-1.0 Page 5 of 10
Activity Type and Description
Part of Project
(Yes or No) Actions Taken Inspect/ Upkeep
Small Scale
Const / Renov
Large Scale Const /Renov
Yes No
Fire Alarm System - Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.
utilities as required, LOTO procedures in place and staff trained on their use.
X
Fire Alarm System - Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors
X coordinate outages 3 weeks in utilities as required, LOTO procedures in place and staff trained on their use.
X
Architectural, structural, or any other work that may cause vapors or fumes such as:
- Roofing work
- Flooring work
- Painting or other large-scale use of such substances.
The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators.
X Use of B-Bank Elevators not exceeding weight limit.
X X
Excavation or heavy equipment use taking place
- Dig safe required utility location
- Trench safety
- Dust control plan
- Equipment exhaust, Noise, Vibration
Excavation safety plan to be provided by contractor and approved by VA.
Dig safe paperwork in place.
X
Confined space entry required (permit required or not)
Confined entry plan in place and staff trained
X
Requires crane work
- General crane work
- Lift over buildings
X Crane lift plan in place
- Crane placement
- Crane swing
- Crane load evaluation
X
Includes elevated work
- Roof work, fall protection
- Window work, scaffolding and fall protection
- Odor control
X Fall protection plan in place and staff trained.
Comply with OSHA and VA standards.
X
Welding, cutting or use of torches requiring burn
Hot Work or burn permits in place and staff trained
X
Data / Telephone / Wireless (Staff or Guest WiFi) - are there modifications of installation of new systems that will impact operations.
Coordinate outages 3 weeks in utilities as required, LOTO procedures in place and staff trained on their use.
X X
Natural Gas Service - are there modifications to the existing system, interruptions to service or installation of new?
utilities as required, LOTO procedures in place and staff trained on their use.
VHA-PCRA-2023-1.0 Page 6 of 10
Activity Type and Description
Part of Project
(Yes or No) Actions Taken Inspect/ Upkeep
Small Scale
Const / Renov
Large Scale Const /Renov
Yes No
Pneumatic Tube System - are there modifications to the existing system, interruptions to service or installation of new?
utilities as required, general broadcast.
X
Are there moves to patients or staff involved? Coord with Arch Shop, Move Team & Planner. How will this affect start of project? How are patient services impacts being handled?
X Coordination and phasing identified in construction documents. X X
Activity Type and Description Control Measures
Inspection/upkeep generally defined as follows:
• Work can be completed in a single shift, not to exceed 10 hours.
• Patients, employees and/or visitors may be in the area depending on the activity.
• Work that does not create dust or debris.
• Work that does not create vapors or fumes.
• Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited exposure time (not to exceed an hour for each tile) within the shift.
• Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.
• Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.
1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
2. Site visits of construction area are required weekly by member of multi-disciplinary team.
Site visits will be documented on standard checklist.
3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the shop involved must work with Safety to ensure proper precautions are in place.
4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.
5. Communication and coordination plan for all affected areas
Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:
• Prolonged work that may take longer than a single shift but not exceeding six months.
• Patients and employees are not to be in the area until activity is completed.
• Work that creates some noise and vibration due to power tool use.
• Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.
o cause penetrations in fire or smoke barrier
• Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:
o LOTO
All control measures in the row above and the following:
1. Hazard communication chemical inventory required to be provided by the contractor and approved.
2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly
3. Hot Work or burn permits in place and staff trained
4. LOTO procedures in place and staff trained on their use
5. Site visits will be reviewed using the criteria in standardized guide.
VHA-PCRA-2023-1.0 Page 7 of 10 o The use of compressed gas cylinders
• Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.
• Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:
o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead
• Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.
• Architectural, structural, or any other work that may cause vapors or fumes such as:
o Roofing work o Flooring work o Painting or other large-scale use of such substances.
6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.
Large-scale construction, renovation, or maintenance generally defined as follows:
• Work exceeding 6 months in duration.
• Patients and employees are not to be in the area until activity is completed.
• Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration
• Confined space entry required (permit required or not)
• Requires crane work o General crane work o Lift over buildings
• Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control
• Welding, cutting or use of torches requiring burn permits
• Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.
o cause breaches to fire or smoke barrier
• The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators
• Plumbing work requiring LOTO and system shutdown and startup such as the installation of:
All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):
1. Excavation safety plan in place ☐
2. Dust control plan in place ☐
3. Pollution prevention plan in place ☐
4. Dig safe paper work in place ☐
5. Crane lift plan in place ☐
a. Crane placement
b. Crane swing
c. Crane load evaluation
6. Fall protection plan in place and staff trained ☐
7. Confined entry plan in place and staff trained ☐
VHA-PCRA-2023-1.0 Page 8 of 10 o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.
• Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.
• Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors
• Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.
Table 2. Affected Adjacent Area Assessment
In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:
• If adjacent area is vacant (e.g., work outside, construction of new building, etc.):
o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.
• If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):
o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).
• If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):
o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).
VHA-PCRA-2023-1.0 Page 9 of 10
Area Service(s)/Type(s) of Area(s)
(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*
Point of Contact
(POC)
POC Contact Information
Construction plan communicated to POC?
Activity Area**
Utility Tunnel Adam Kreger x44773 Yes
Area Above
NA
Area Below
Adjacent Area 1
Adjacent Area 2
Adjacent Area 3
Adjacent Area 4
* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.
** List the area(s) in which the construction/renovation/maintenance activity will occur.
Infection Control Risk Assessment (ICRA)
Consult with Infection Prevention and Control regarding the assessment of potential infection risks associated with the activity and the need for control measures. See VHA Directive 7715 and the VHA ICRA Template for more information.
Is an ICRA required for the Activity? Yes ☒ No ☐
VHA-PCRA-2023-1.0
Pre-Construction Risk Assessment (PCRA) Permit
This page must be posted at the entrance to the project area, or other designated area
Unique permit number: 695-21-110 PCRA 1
Location and brief description of construction/renovation/maintenance
North campus steam tunnel between Bldgs. 7 and 43 – Repair waterproofing deficiencies and damage done by past water infiltration events.
Project manager Sam W. Gudex Project start date TBD
Contact phone number 414-928-9505 Completion date TBD
Contractor or lead shop TBD Permit expiration date TBD
Activity Type Inspection/Upkeep, Small-scale, or Large-scale) Large Scale
Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)
Inspection/Upkeep
1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.
3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.
4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.
5. Communication and coordination plan for all affected areas
Small-scale
All control measures in the row above and the following:
1. Hazard communication chemical inventory required to be provided by the contractor and approved.
2. ILSMs in place and staff trained on situation
3. Hot Work or burn permits in place and staff trained
4. LOTO procedures in place and staff trained on their use
5. Site visits will be reviewed using the criteria in standardized guide.
6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.
Large-scale
All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):
1. Excavation safety plan in place ☒
2. Dust control plan in place ☒
3. Asbestos abatement plan in place ☐
4. Lead abatement plan in place ☐
5. Silicia removal plan in place ☐
6. Pollution prevention plan in place ☐
7. Dig safe paperwork in place ☒
8. Crane lift plan in place ☐
a. Crane placement
b. Crane swing
c. Crane load evaluation
9. Fall protection plan in place and staff trained ☐
10. Confined entry plan in place and staff trained ☒
*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.
Additional requirements:
Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☒ No ☐
Infection Prevention and Control signature: To be completed once construction is awarded and work is ready to start.
Date:
Project Manager signature Date
Safety Officer signature Date
Chair, Construction Safety Committee signature
Date