This document outlines requirements for construction waste management on a federal contract for repair of a north campus steam tunnel. The contractor must submit a Construction Waste Management Plan within 60 days of the notice to proceed that details procedures for debris management, estimates waste types and quantities to be diverted from landfills through reuse and recycling versus disposal, and identifies designated staff responsible for plan implementation. The contractor is required to divert a minimum of 50% of construction and demolition waste from landfills by weight and maintain records documenting waste diversion and disposal. Hazardous and regulated wastes require special handling and disposal. Monthly summaries and a final report on waste diversion results must be submitted. The related federal contract opportunity is for repair of the north campus steam tunnel at the Milwaukee VA Medical Center under solicitation number 36C25223B0030.

View the file

Other files

File Type Posted
36C25223B0030 0006.docx DOCX document
S06 Basement Plan_Floor_Arch.pdf PDF
S06 SECTIONS _ DETAILS_Equipment_Arch.pdf PDF
36C25223B0030 0005.docx DOCX document
S06 North Elevation _ Cross Section Social Hall Bldg No. 4_Exterior_Arch.pdf PDF
S06 A0005 Follow Up questions to Amendment 003.docx DOCX document
S06 BUILDING NO 5 COMPANY 10_Exterior_Arch.pdf PDF
36C25223B0030 0004.docx DOCX document
P07 Wage Determination.pdf PDF
S02 695-21-110_BiddersQuestionsLog_FINAL-1.xlsx XLSX spreadsheet
S02 695-21-110_CvrSht_Amendment3-1.docx DOCX document
S02 695-21-110_DwgFrom695-97-101REFERENCE-1.pdf PDF
S02 695-21-110_030130_MaintCIPConcrete-1.pdf PDF
S02 695-21-110_CS101_Amendment3-1.pdf PDF
36C25223B0030 0003.docx DOCX document
S02 Wage Determination correction.pdf PDF
S02 695-21-110_GeotechReport_210512-1.pdf PDF
S02 695-21-110_PCRA_230901-2.pdf PDF
S04-PreBid2ndSignInSheet-1.pdf PDF
36C25223B0030 0002.docx DOCX document
S04 - Pre-Bid Sign-in Sheet.pdf PDF
36C25223B0030 0001.docx DOCX document
S02 695-21-110 Drawings Part 3.pdf PDF
36C25223B0030_1.docx DOCX document
S02 695-21-110 Drawings Part 1.pdf PDF
S02 Wage Determination.pdf PDF
S02 695-21-110 Drawings Part 2.pdf PDF
S02 695-21-110 Specficiations.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

695-21-110: Repair North Campus Steam Tunnel Amendment #3

Milwaukee VAMC

01 74 19-1

SECTION 01 74 19

CONSTRUCTION WASTE MANAGEMENT

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies the requirements for the management of non-hazardous building construction and demolition waste.

B. Waste disposal in landfills shall be minimized to the greatest extent possible. Of the inevitable waste that is generated, as much of the waste material as economically feasible shall be salvaged, recycled, or reused.

C. Contractor shall use all reasonable means to divert construction and demolition waste from landfills and incinerators, and facilitate their salvage and recycling to be not limited to the following:

1. Waste Management Plan development and implementation.

2. Techniques to minimize waste generation.

3. Sorting and separating of waste materials.

4. Salvage of existing materials and items for reuse or resale.

5. Recycling of materials that cannot be reused or sold.

D. At a minimum the following waste categories shall be diverted from landfills:

1. Clean/Uncontaminated Soil (Note: The Clement J. Zablocki VA Medical

Center (5000 W. National Ave. Milwaukee, WI 53295) is listed on the

Wisconsin Department of Natural Resources (DNR) Bureau for

Remediation and Redevelopment Tracking System (BRRTS) [BRRTS No. 02-

41-563846]. Soils excavated at the Medical Center are typically contaminated with low levels of lead, petroleum volatile organic compounds (PVOCs), polycyclic aromatic hydrocarbons (PAHs), and polychlorinated biphenyls (PCBs). All soil spoils are assumed to be contaminated unless an exemption is approved. If an exemption from the landfill requirement is desired, the contractor is responsible for all expenses related to sample collection, laboratory analysis, reporting, interpretation of the results, and coordination with the

DNR to obtain permission to dispose of soils at a non-licensed landfill or other site. For all soil management actions, the contractor is responsible for notifying and coordinating with DNR by using WI DNR Form 4400-315 and, if sending for disposal at a licensed landfill, obtaining approval from a licensed landfill prior to disposal. The contractor must consult with the Milwaukee VAMC

01 74 19-2

Green Environmental Management System (GEMS) Program Manager at least four weeks prior to shipment of soil spoils offsite so as not to cause any project delays.)

2. Inert Materials (concrete, masonry, and asphalt).

3. Clean dimensional wood and pallet wood.

4. Green waste (biodegradable landscaping materials).

5. Engineered wood products (plywood, particle board and I-joists, etc.).

6. Metal products (e.g., steel, wire, beverage containers, copper, etc.).

7. Sheathings

8. Cardboard, paper, and packaging.

9. Bitumen roofing materials.

10. Plastics (e.g., ABS, PVC).

11. Carpet and/or pad.

12. Gypsum board.

13. Insulation.

14. Paint.

E. The following regulated wastes require special handling, storage and disposal and must be segregated:

1. Hazardous Wastes (including oil-based paint, cleaning chemicals, other miscellaneous chemicals, etc.)

2. Used Oil and Antifreeze

3. Electronical Waste (E-waste)

4. Universal Wastes:

a. Aerosol Cans

b. Batteries

c. Lamps

d. Mercury-containing Equipment (thermometers, switches, etc.)

e. Pesticides

5. Polychlorinated biphenyl (PCB) ballasts and non-PCB ballasts

1.2 RELATED WORK

A. Section 02 41 00, DEMOLITION.

B. Section 01 00 00, GENERAL REQUIREMENTS.

1.3 QUALITY ASSURANCE

A. Contractor shall practice efficient waste management when sizing, cutting and installing building products. Processes shall be employed

01 74 19-3 to ensure the generation of as little waste as possible. Construction

/Demolition waste includes products of the following:

1. Excess or unusable construction materials.

2. Packaging used for construction products.

3. Poor planning and/or layout.

4. Construction error.

5. Over ordering.

6. Weather damage.

7. Contamination.

8. Mishandling.

9. Breakage.

B. Establish and maintain the management of non-hazardous building construction and demolition waste set forth herein. Conduct a site assessment to estimate the types of materials that will be generated by demolition and construction.

C. Contractor shall develop and implement procedures to recycle construction and demolition waste to a minimum of 50 percent.

D. Contractor shall be responsible for implementation of any special programs involving rebates or similar incentives related to recycling.

Any revenues or savings obtained from salvage or recycling shall accrue to the contractor.

E. Contractor shall provide all demolition, removal and legal disposal of materials. Contractor shall ensure that facilities used for recycling, reuse and disposal shall be permitted for the intended use to the extent required by local, state, federal regulations. The Wisconsin DNR

C&D website https://dnr.wi.gov/topic/Demo/Debris.html provides guidance and resources for diverting construction waste from the landfill.

F. Contractor shall assign a specific area to facilitate separation of materials for reuse, salvage, recycling, and return. Such areas are to be kept neat and clean and clearly marked in order to avoid contamination or mixing of materials.

G. Contractor shall provide on-site instructions and supervision of separation, handling, salvaging, recycling, reuse and return methods to be used by all parties during waste generating stages.

H. Record on daily reports any problems in complying with laws, regulations and ordinances with corrective action taken.

01 74 19-4

1.4 TERMINOLOGY

A. Class III Landfill: A landfill that accepts non-hazardous resources such as household, commercial and industrial waste resulting from construction, remodeling, repair and demolition operations.

B. Clean: Untreated and unpainted; uncontaminated with adhesives, oils, solvents, mastics and like products.

C. Construction and Demolition Waste: Includes all non-hazardous resources resulting from construction, remodeling, alterations, repair and demolition operations.

D. Dismantle: The process of parting out a building in such a way as to preserve the usefulness of its materials and components.

E. Disposal: Acceptance of solid wastes at a legally operating facility for the purpose of land filling (includes Class III landfills and inert fills).

F. EPA Subtitle C Landfill: A landfill which are authorized under the

Resource Conservation and Recovery Act (RCRA) to accept hazardous waste for disposal.

G. EPA Subtitle D Landfill: A landfill that accepts non-hazardous resources such as household, commercial and industrial waste resulting from construction, remodeling, repair and demolition operations.

H. Hazardous Waste: By-products of society that can pose a substantial or potential hazard to human health or the environment when improperly managed. It is a solid waste that possesses at least one of four characteristics (ignitability, corrosivity, reactivity, and toxicity), or appears on special DNR or EPA lists (P-, U-, K-, or F-lists). The regulatory definition of hazardous waste is found in s. NR 661, Wis.

Adm. Code. Examples of hazardous waste include, but are not limited to: xylene, toluene, acetone, kerosene, and petroleum distillates.

I. Inert Backfill Site: A location, other than inert fill or other disposal facility, to which inert materials are taken for the purpose of filling an excavation, shoring or other soil engineering operation.

J. Inert Fill: A facility that can legally accept inert waste, such as asphalt and concrete exclusively for the purpose of disposal.

K. Inert Solids/Inert Waste: Non-liquid solid resources including, but not limited to, soil and concrete that does not contain hazardous waste or soluble pollutants at concentrations in excess of water-quality objectives established by a regional water board, and does not contain significant quantities of decomposable solid resources.

01 74 19-5

L. Mixed Debris: Loads that include commingled recyclable and non-recyclable materials generated at the construction site.

M. Mixed Debris Recycling Facility: A solid resource processing facility that accepts loads of mixed construction and demolition debris for the purpose of recovering re-usable and recyclable materials and disposing non-recyclable materials.

N. Permitted Waste Hauler: A company that holds a valid permit to collect and transport solid wastes from individuals or businesses for the purpose of recycling or disposal.

O. Recycling: The process of sorting, cleansing, treating, and reconstituting materials for the purpose of using the altered form in the manufacture of a new product. Recycling does not include burning, incinerating or thermally destroying solid waste.

1. On-site Recycling – Materials that are sorted and processed on site for use in an altered state in the work, i.e. concrete crushed for use as a sub-base in paving.

2. Off-site Recycling – Materials hauled to a location and used in an altered form in the manufacture of new products.

P. Recycling Facility: An operation that can legally accept materials for the purpose of processing the materials into an altered form for the manufacture of new products. Depending on the types of materials accepted and operating procedures, a recycling facility may or may not be required to have a solid waste facilities permit or be regulated by the local enforcement agency.

Q. Reuse: Materials that are recovered for use in the same form, on-site or off-site.

R. Return: To give back reusable items or unused products to vendors for credit.

S. Salvage: To remove waste materials from the site for resale or re-use by a third party.

T. Solid Waste: Any garbage, refuse, sludge from a waste treatment plant, water supply treatment plant or air pollution control facility and other discarded or salvageable materials, including solid, liquid, semisolid, or contained gaseous materials resulting from industrial, commercial, mining and agricultural operations, and from community activities, but does not include solids or dissolved material in domestic sewage, or solid or dissolved materials in irrigation return flows or industrial discharges which are point sources subject to

01 74 19-6 permits under Wis. Stat. § 283, or source material, as defined in Wis.

Stat. § 254.31(10), special nuclear material, as defined in Wis. Stat.

§ 254.31(11), or byproduct material, as defined in Wis. Stat. §

254.31(1).

U. Source-Separated Materials: Materials that are sorted by type at the site for the purpose of reuse and recycling.

V. Transfer Station: A facility that can legally accept solid waste for the purpose of temporarily storing the materials for re-loading onto other trucks and transporting them to a landfill for disposal, or recovering some materials for re-use or recycling.

1.5 SUBMITTALS

A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and

SAMPLES, and within 60 days of the NTP, furnish to the COR a written

Construction Waste Management Plan (CWMP). A sample CWMP is available from the COR or Green Environmental Management System (GEMS) Program

Manager. The plan shall include, but not be limited to, the following information:

1. Procedures to be used for debris management.

2. Target Waste Diversion Rate (a minimum of 50% by weight)

3. Techniques to be used to minimize waste generation.

4. Analysis of the estimated job site waste to be generated:

a. List of each material and quantity to be salvaged, reused, recycled.

b. List of each material and quantity proposed to be taken to a

Subtitle D Landfill.

c. List of each regulated waste item and quantity proposed to be taken to a Subtitle C Landfill

5. Detailed description of the Means/Methods to be used for material handling.

a. On site: Material separation, storage, protection where applicable.

b. Off site: Transportation means and destination. Include list of materials.

1) Description of materials to be site-separated and self-hauled to designated facilities.

2) Description of mixed materials to be collected by designated waste haulers and removed from the site.

01 74 19-7

a) The names and locations of mixed debris reuse and recycling facilities or sites.

b) The names and locations of trash disposal landfill facilities or sites.

c) Documentation that the facilities or sites are approved to receive the materials.

6. Designated Manager responsible for instructing personnel, supervising, documenting and administer over meetings relevant to the CWMP.

B. Monthly summary of construction and demolition debris diversion and disposal, quantifying all materials generated at the work site and disposed of or diverted from disposal through recycling. Monthly summary must also include:

1. Target waste diversion rate by material and an overall diversion rate.

C. Final report documenting the results of implementation of the CWMP submitted to the COR and GEMS Program Manager.

1.6 APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced by the basic designation only. In the event that criteria requirements conflict, the most stringent requirements shall be met.

B. U.S. Green Building Council (USGBC): LEED Green Building Rating System for New Construction

1. Green Building Initiative (GBI): Green Globes for New Construction

1.7 RECORDS

A. Maintain records to document the quantity of waste generated; the quantity of waste diverted through sale, reuse, or recycling; and the quantity of waste disposed by landfill or incineration.

PART 2 - PRODUCTS

2.1 MATERIALS

A. List of each material and quantity to be salvaged, recycled, reused.

B. List of each material and quantity proposed to be taken to a landfill.

C. Material tracking data: Receiving parties, dates removed, transportation costs, weight tickets, tipping fees, manifests, invoices, net total costs or savings.

01 74 19-8

PART 3 - EXECUTION

3.1 COLLECTION

A. Provide all necessary containers, bins and storage areas to facilitate effective waste management. Contractor shall provide waste carts and dumpster for the project. Coordinate location of dumpster with the COR prior to mobilization and indicate location on CWMP. With permission from the COR, Contractor may be able to locate dumpster at the VA loading dock during demolition activities only, but shall be responsible for securing the dumpster so that it can only be used by the Contractor and their agents.

B. Clearly identify containers, bins and storage areas so that recyclable materials are separated from trash and can be transported to respective recycling facility for processing.

C. Hazardous wastes shall be separated, stored, disposed of according to local, state, federal regulations. These regulations include City of

Milwaukee Solid Waste Regulations Chapter 79, Wis. Admin Code § NR 660-

679, and 40 CFR 239-282.

3.2 DISPOSAL

A. Contractor shall be responsible for transporting and disposing of materials that cannot be delivered to a source-separated or mixed materials recycling facility to a transfer station or disposal facility that can accept the materials in accordance with state and federal regulations.

B. Construction or demolition materials with no practical reuse or that cannot be salvaged or recycled shall be disposed of at a landfill or incinerator.

3.3 REPORT

A. With each application for progress payment, submit a summary of construction and demolition debris diversion and disposal including beginning and ending dates of period covered (i.e. waste manifest).

B. Quantify all materials diverted from landfill disposal through salvage or recycling during the period with the receiving parties, dates removed, transportation costs, weight tickets, manifests, invoices.

Include the net total costs or savings for each salvaged or recycled material.

C. Quantify all materials disposed of during the period with the receiving parties, dates removed, transportation costs, weight tickets, tipping

01 74 19-9 fees, manifests, invoices. Include the net total costs for each disposal.

D. Submit a copy of all hazardous waste and special waste manifests to the

COR and GEMS Program Manager.

- - - E N D - - -