About this file

This document outlines a solicitation for a Multiple Award Task Order Contract (MATOC) for construction services at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The VA intends to award multiple Indefinite-Delivery Indefinite- Quantity contracts with a maximum value of $50 million over five years for maintenance, repair, alteration, and new construction projects ranging from $2,000 to $2 million. Eligible projects include general construction, carpentry, asphalt and concrete work, roofing, excavation, renovation, equipment installation, mechanical, electrical, plumbing, painting, demolition, masonry, fire protection, telecommunications, HVAC, and other construction services. The solicitation number is 36C25218R0104 and will be issued on or around February 5, 2018. This is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. Offerors must be verified as SDVOSBs under the assigned NAICS code of 236220 with a $36.5 million size standard.

36C25218R0104 00002 030760 FRP concrete 695-17-116.pdf

View the file

Other files

File Type Posted
36C25219D0028-000.docx DOCX document
36C25219D0027-000.docx DOCX document
36C25219D0026-001.docx DOCX document
36C25219D0025-005.docx DOCX document
36C25218R0104-00004001.pdf PDF
36C25218R0104-00004000.docx DOCX document
36C25218R0104-00003000.docx DOCX document
36C25218R0104-00002004.docx DOCX document
36C25218R0104-00002000.docx DOCX document
36C25218R0104-00002005.pdf PDF
36C25218R0104-00002003.pdf PDF
36C25218R0104-00002001.pdf PDF
36C25218R0104-00001000.docx DOCX document
36C25218R0104-00001001.pdf PDF
36C25218R0104-010.pdf PDF
36C25218R0104-015.pdf PDF
36C25218R0104-007.docx DOCX document
36C25218R0104-009.pdf PDF
36C25218R0104-006.docx DOCX document
36C25218R0104-016.pdf PDF
36C25218R0104-013.pdf PDF
36C25218R0104-011.pdf PDF
36C25218R0104-017.pdf PDF
36C25218R0104-003.docx DOCX document
36C25218R0104-002.docx DOCX document
36C25218R0104-014.pdf PDF
36C25218R0104-012.pdf PDF
36C25218R0104-001.docx DOCX document
36C25218R0104-004.docx DOCX document
36C25218R0104-005.docx DOCX document
36C25218R0104-008.pdf PDF
36C25218R0104-000.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLEMENT J. ZABLOCKI MEDICAL CENTER DEPARTMENT OF VETERAN AFFAIRS

MILWAUKEE, WI

Upgrade Elevators Buildings 5 and 6A

VA PROJECT: 695-17-116

Amendment 00002

03 07 60 - 1

SECTION 03 07 60

FIBER REINFORCED POLYMER CONCRETE

PART 1 - GENERAL

1.1 WORK INCLUDES

Externally bonded fiber reinforced polymer systems for strengthening concrete.

1.2 QUALITY ASSURANCE

A. Applicator: Company specializing in the installation of Carbon Fiber

Systems with minimum five years of experience, member of the

International Concrete Repair Institute (ICRI) and the American

Concrete Institute (ACI).

B. Reference Standards:

1. ACI 440.2R – Guide for the Design and Construction of Externally

Bonded FRP Systems for Strengthening Concrete Structures.

2. ASTM E 84 – Test for Surface burning Characteristics of Building

Materials.

3. ASTM E 119 – Fire Tests of Building Construction and Materials.

4. ASTM D 3039 – Test Methods for Tensile Properties of Fiber Resin

Composites.

C. Regulator Requirements: Conform to the following Code for flame/fuel/smoke ratings requirements and fire resistance ratings.

1. International Building Code (IBC), latest edition.

1.3 SUBMITTAL

A. Product Data: Provide manufacturer’s specifications showing compliance with specifications. Include data for fire retardant chemicals used to comply with fire rating:

B. Test Reports: Two certified copies of field test reports indicating tensile strength, strain and elastic modulus as per ISIS, ASTM D

3039, shell to concrete-adhesive shear, and shell to concrete-adhesive tension as per ISIS.

C. Shop Drawings: Submit documentation showing FRP system to be used, locations of FRP system relative to existing structure, dimensions and orientation of each ply, number of plies, sequence of installation and calculations prepared by a Professional Engineer registered in the

State of Wisconsin.

1.4 JOB CONDITIONS

A. Provide staging as required to install FRP system.

B. Protect finished surfaces from resin droppings.

1.5 PERFORMANCE

A. The selected FRP system shall be designed in accordance with ACI 440.2R by the FRP Contractor for the equivalent area of steel indicated on the

Upgrade Elevators Buildings 5 and 6A

03 07 60 - 2 construction documents, comply with specification requirements.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Products of the following manufacturers are acceptable. Submit products of other manufacturers for approval.

1. Master Builders.

2. Sika Chemical Corporation.

3. Stellar-Mark Inc.

2.2 MATERIALS

A. Epoxy Resin: Provide resin that has the following characteristics:

compatible with adhesion to concrete substrate, adhesion to FRP composite system, filling ability, workability, pot life and develop appropriate mechanical properties for the FRP composite.

B. Carbon Fiber Reinforced Polymer: Continuous, by-directional fibers selected and tested for the composite system.

C. Fire Retardant Chemicals: Chemicals that are used to retard the tendency of resin to burn. Retardant may be added to the resin or coated on the surface of the FRP.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that substrate surfaces are ready to receive work.

B. Confirm compatibility of surfaces to receive FRP materials.

C. Verify that epoxy injection repairs are complete prior to FRP application.

D. Verify ducts, piping, equipment, or other items which would interfere with application of the FRP system are suitably located.

E. Beginning of installation means acceptance of existing conditions and substrate.

3.2 PREPARATION

A. Clean surfaces as necessary for proper bonding of FRP system.

B. Fill voids and cracks in substrate; remove projections and level where FRP system is applied.

C. Protect adjacent surfaces and equipment from droppings.

D. Grind concrete surface to insure adequate bond between concrete and

FRP system. Prepare test surfaces for not less than three bond tests.

3.3 APPLICATION

A. Mix and apply FRP system in accordance with manufacturer’s instructions and to comply with ACI 440.2R.

3.4 FIELD QUALITY CONTROL

A. Contractor Tests: Contractor shall prepare and test not less than

Upgrade Elevators Buildings 5 and 6A

03 07 60 - 3 three samples to confirm that bond between concrete and FRP system is adequate to develop design loads used for the system. Notify

Engineer not less than three working days prior to testing of materials.

B. Preparation of concrete surfaces shall be conducted in accordance with approved test results.

C. Acceptance: Inspection, evaluation and acceptance of the work shall be performed by the Engineer in accordance with ACI 440.2R.

3.5 CLEANING

A. Remove excess material, droppings, and debris.

B. Remove FRP materials from surfaces not specifically required to be covered.

- - - E N D - - -