This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the Department of Veterans Affairs Network Contracting Office 10. The amendment changes the response due date from January 15, 2026, to December 5, 2025, at 10:00 EST, and provides clarification to the period of performance originally stated in the solicitation. The solicitation number is 36C25026Q0067, with an effective date of 11-19-2025.
The amendment also modifies the Statement of Work (SOW) paragraph VI, extending the ultimate completion date for work at both campuses to April 30, 2026. Contractors are still permitted to work simultaneously at both campuses. The accounting and appropriation data is listed as 610-366-0162-6091-854100-2580 010050100, and the contract is administered by the Department of Veterans Affairs in Indianapolis, Indiana. The contracting officer is Luke A. Turner, and the amendment is associated with project VA-VHA-RPOC-2024-0076.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Marion testing.pdf | ||
| Marion testing 2.pdf | ||
| FTW Testing.pdf | ||
| FTW Testing 2.pdf | ||
| 36C25026Q0067 0003.pdf | ||
| 36C25026Q0067 0002.pdf | ||
| Sign-in-Marion.pdf | ||
| 36C25026Q0067 0001.pdf | ||
| Sign-in-Ft.-Wayne.pdf | ||
| Attachment VII - marion dry type transformers.docx | DOCX document | |
| Attachment I - SOW Attachments.pdf | ||
| Attachment VIII - Marion MCC.docx | DOCX document | |
| 36C25026Q0067.docx | DOCX document | |
| Attachment III - Wage Determination - Allen Co.pdf | ||
| Attachment II - Wage Determination - Grant Co.pdf | ||
| Attachment IX - Important Information.docx | DOCX document | |
| Attachment VI - Marion panel boards.docx | DOCX document | |
| Attachment V - Fort Wayne Electrical test equipment list 08-05-25.xlsx | XLSX spreadsheet | |
| Attachment IV - Fort Wayne Electrical Panel 08-05-25.xlsx | XLSX spreadsheet |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 2
0004 11-19-2025
36C250
Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 325 Indianapolis IN 46240
36C50
Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 325 Indianapolis IN 46240
To all Offerors/Bidders
36C25026Q0067
10-23-2025
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 12-05-2025 10:00 EST
610-366-0162-6091-854100-2580 010050100
X 1
The purpose of this amendment is to changes the response due date from January 15, 2026, to December 5, 2025.
This amendment also provides clarification to the period of performance stated on page 13 of the original solicitation.
All other terms and conditions remain unchanged.
Luke A. Turner Contracting Officer
VA-VHA-RPOC-2024-0076
Previous SOW paragraph VI:
All work shall be completed at both campuses and written reports submitted within 60 days from work commencement. Contractors can work simultaneously at both campuses.
New SOW paragraph VI:
All work shall be completed at both campuses with an ultimate completion date of April 30, 2026. Contractors can work simultaneously at both campuses.