This document is a Bid Schedule for Project 655-20-202, Atrium Renovation Building 22 at the Aleda E. Lutz VA Medical Center in Saginaw, Michigan. The solicitation number is 36C25024B0058.
The Bid Schedule includes a Base Bid for the entire project, which covers general construction, alterations, roads, walks, grading, drainage, and other necessary items. The performance period for the Base Bid is 120 calendar days after receipt of the Notice to Proceed. There is also a Deductive Bid Item No. 1 that excludes work on the new interior hanging green wall in the atrium.
The key details of the federal contract opportunity include furnishing labor, tools, materials, equipment, and supervision to complete the atrium renovation project. The work will be performed in two phases, with the first phase focusing on exterior and selective interior demolition work, and the second phase covering the remaining interior work. The Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 10 is the procuring agency.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
36C25024B0058
Project 655-20-202 Atrium Renovation Bldg 22 at the Saginaw VA Medical Center
ALL ITEMS MUST BE PRICED IN ORDER TO BE RESPONSIVE TO THE SOLICITATION
Per Veterans Affairs Acquisition Regulation (VAAR) Provision 852.236-92 – NOTICE TO BIDDERS – ADDITIVE OR
DEDUCTIVE BID LINE ITEMS (APR 2019) The low bid shall be the Bidder that—
(i) Is otherwise eligible for award; and
(ii) Offers the lowest aggregate amount for the first or base line item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive line items that provide the most features within the funds determined available.
The included Deductive Bid Items are listed in descending order of priority in the event funds are not available to award Bid Item I, Base Bid, Entire Project. Deductive No. 1 is the highest priority, and Deductive No. 2 second highest priority.
BID ITEMS
Bid Item No. I, Base Bid, Entire Project: Work includes, but is not limited to, general construction, alterations, roads, walks, grading, drainage, and necessary removal of existing structures and construction and certain other items.
Performance Period for Bid Item I, Base Bid, Entire Project is One Hundred Twenty (120) Calendar Days after receipt of Notice to Proceed.
Total Bid Item No. I Base Bid, Entire Project: $________________________ (Lump Sum)
Bid Item No. II, Deductive No. 1: Provide all work in the base bid except for work pertaining to the new interior hanging green wall in the atrium of building #22.
Deduction for Bid Item No. II, Deductive No. 1: Subtract -$________________________
END OF BID SCHEDULE