014529 Testing Laboratory Services.pdf

PDF 93 KB Posted

Attached to
Upgrade 480V Electrical System Federal contract opportunity
Solicitation number
36C24921R0084
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9

About this file

This document outlines testing laboratory services required for the Upgrade 480V Electrical System project at the Louisville KY Veterans Affairs Medical Center. The contractor shall furnish all material, equipment and labor to install a new 1150 KVA outdoor transformer to feed the 480V switchgear, correct wiring deficiencies for CAT scan rooms, and move electrical feeds for air handlers and pumps to emergency power circuits. The testing laboratory shall inspect materials and workmanship, perform required tests, submit written reports, and provide verbal notifications of any irregularities. Services include earthwork testing such as density tests during fill placement and compaction in building and pavement areas. Concrete batch plant inspection and materials testing is specified along with reinforcement testing.

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade 480V Electrical System, newest first.
File Type Posted
36C24921R0084 0003.pdf PDF
RFIs May 24.docx DOCX document
36C24921R0084 0002.pdf PDF
S02-Price Schedule (Project 603-20-505) FY2021.xlsx XLSX spreadsheet
265600 Ext Lighting.pdf PDF
312011 Earthwork.pdf PDF
260526 Grounding and Bonding.pdf PDF
260533 Raceway and Boxes.pdf PDF
262413 Distribution Switchboard.pdf PDF
260513 Med Voltage Cables.pdf PDF
018113 Sustainable Construction Requirements.pdf PDF
040516 Masonry Grouting2.pdf PDF
14.10_EP101 - FIRST FLOOR ELECTRICAL PLAN.pdf PDF
14.14_EP400 - OVERALL FOURTH FLOOR PLAN.pdf PDF
14.05_EP0001 - SUB-BASEMENT ELECTRICAL PLAN.pdf PDF
14.19_EP900 - OVERALL NINTH FLOOR PLAN.pdf PDF
14.12_EP201 - SECOND FLOOR ELECTRICAL PLAN.pdf PDF
14.01_E500 - SCHEDULES, DETAILS AND SINGLE-LINE DIAGRAM.pdf PDF
S15-PPQ-Template (Project 603-20-505) Upgrade 480V Electrical System.pdf PDF
323113 Chain Link Gates.pdf PDF
010000 Gen Requirments Rev 2.pdf PDF
000115 List Drawing.pdf PDF
040513 Masonry Mortaring.pdf PDF
042000 Unit Masonry.pdf PDF
017419 Const Waste Management.pdf PDF
000110 TOC.pdf PDF
00.00_GI000 - COVER SHEET AND SHEET INDEX.pdf PDF
14.07_EP001A - BASEMENT ELECTRICAL PLAN-A.pdf PDF
07.00_AE101 - SCREEN WALL DETAILS.pdf PDF
14.06_EP000 - OVERALL BASEMENT ELECTRICAL PLAN.pdf PDF
14.02_E501 - PARTIAL MEDIUM VOLTAGE SINGLE-LINE DIAGRAM.pdf PDF
S02-36C24921R0084_1.pdf PDF
263623 ATS.pdf PDF
264313 Surge Prot Dev.pdf PDF
260541 Underground Elec Const.pdf PDF
262416 Panelboards.pdf PDF
260573 Overcurrent Prot Device Study.pdf PDF
078400 Firestopping.pdf PDF
013526 Safety Req.pdf PDF
079200 Joint Sealants.pdf PDF
0000 cover Rev 1.pdf PDF
047200 CAST STONE MASONRY.pdf PDF
024100 Demolition.pdf PDF
Combined Drawings.pdf PDF
14.11_EP200 - OVERALL SECOND FLOOR PLAN.pdf PDF
14.16_EP600 - OVERALL SIXTH FLOOR PLAN.pdf PDF
14.13_EP300 - OVERALL THIRD FLOOR PLAN.pdf PDF
14.04_EP0000 - OVERALL SUB-BASEMENT PLAN.pdf PDF
14.03_E600 - PANEL SCHEDULES.pdf PDF
S03-Successful FBO Posting-36C24921R0084 (603-20-505).pdf PDF
Show all 50

Upgrade 480V Electrical System has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Louisville KY - Robley Rex VAMC – Upgrade 480V Electrical System

Project #: 603-20-505

11-01-18

01 45 29 - 1

SECTION 01 45 29

TESTING LABORATORY SERVICES

PART 1 - GENERAL

1.1 DESCRIPTION:

This section specifies materials testing activities and inspection services required during project construction to be provided by a

Testing Laboratory retained by the General Contractor.

1.2 APPLICABLE PUBLICATIONS:

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

B. American Association of State Highway and Transportation Officials

(AASHTO):

T27-11..................Standard Method of Test for Sieve Analysis of

Fine and Coarse Aggregates

T96-02 (R2006)..........Standard Method of Test for Resistance to

Degradation of Small-Size Coarse Aggregate by

Abrasion and Impact in the Los Angeles Machine

T99-10..................Standard Method of Test for Moisture-Density

Relations of Soils Using a 2.5 Kg (5.5 lb.)

Rammer and a 305 mm (12 in.) Drop

T104-99 (R2007).........Standard Method of Test for Soundness of

Aggregate by Use of Sodium Sulfate or Magnesium

Sulfate

T180-10.................Standard Method of Test for Moisture-Density

Relations of Soils using a 4.54 kg (10 lb.)

Rammer and a 457 mm (18 in.) Drop

T191-02(R2006)..........Standard Method of Test for Density of Soil In-

Place by the Sand-Cone Method

T310-13.................Standard Method of Test for In-place Density and Moisture Content of Soil and Soil-aggregate by Nuclear Methods (Shallow Depth)

C. American Concrete Institute (ACI):

506.4R-94 (R2004).......Guide for the Evaluation of Shotcrete

D. American Society for Testing and Materials (ASTM):

A370-12.................Standard Test Methods and Definitions for

Mechanical Testing of Steel Products

11-01-18

01 45 29 - 2

A416/A416M-10...........Standard Specification for Steel Strand, Uncoated Seven-Wire for Prestressed Concrete

C31/C31M-10.............Standard Practice for Making and Curing

Concrete Test Specimens in the Field

C33/C33M-11a............Standard Specification for Concrete Aggregates

C39/C39M-12.............Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

C109/C109M-11b..........Standard Test Method for Compressive Strength of Hydraulic Cement Mortars

C136-06.................Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

C138/C138M-10b..........Standard Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric) of

Concrete

C140-12.................Standard Test Methods for Sampling and Testing

Concrete Masonry Units and Related Units

C143/C143M-10a..........Standard Test Method for Slump of Hydraulic

Cement Concrete

C172/C172M-10...........Standard Practice for Sampling Freshly Mixed

Concrete

C173/C173M-10b..........Standard Test Method for Air Content of freshly

Mixed Concrete by the Volumetric Method

C330/C330M-09...........Standard Specification for Lightweight

Aggregates for Structural Concrete

C567/C567M-11...........Standard Test Method for Density Structural

Lightweight Concrete

C780-11.................Standard Test Method for Pre-construction and

Construction Evaluation of Mortars for Plain and Reinforced Unit Masonry

C1019-11................Standard Test Method for Sampling and Testing

Grout

C1064/C1064M-11.........Standard Test Method for Temperature of Freshly

Mixed Portland Cement Concrete

C1077-11c...............Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation

C1314-11a...............Standard Test Method for Compressive Strength of Masonry Prisms

11-01-18

01 45 29 - 3

D422-63(2007)...........Standard Test Method for Particle-Size Analysis of Soils

D698-07e1...............Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Standard Effort

D1140-00(2006)..........Standard Test Methods for Amount of Material in

Soils Finer than No. 200 Sieve

D1143/D1143M-07e1.......Standard Test Methods for Deep Foundations

Under Static Axial Compressive Load

D1188-07e1..............Standard Test Method for Bulk Specific Gravity and Density of Compacted Bituminous Mixtures

Using Coated Samples

D1556-07................Standard Test Method for Density and Unit

Weight of Soil in Place by the Sand-Cone Method

D1557-09................Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Modified Effort

(56,000ft lbf/ft3 (2,700 KNm/m3))

D2166-06................Standard Test Method for Unconfined Compressive

Strength of Cohesive Soil

D2167-08)...............Standard Test Method for Density and Unit

Weight of Soil in Place by the Rubber Balloon

Method

D2216-10................Standard Test Methods for Laboratory

Determination of Water (Moisture) Content of

Soil and Rock by Mass

D2974-07a...............Standard Test Methods for Moisture, Ash, and

Organic Matter of Peat and Other Organic Soils

D3666-11................Standard Specification for Minimum Requirements for Agencies Testing and Inspecting Road and

Paving Materials

D3740-11................Standard Practice for Minimum Requirements for

Agencies Engaged in Testing and/or Inspection of Soil and Rock as used in Engineering Design and Construction

D6938-10................Standard Test Method for In-Place Density and

Water Content of Soil and Soil-Aggregate by

Nuclear Methods (Shallow Depth)

E94-04(2010)............Standard Guide for Radiographic Examination

11-01-18

01 45 29 - 4

E164-08.................Standard Practice for Contact Ultrasonic

Testing of Weldments

E329-11c................Standard Specification for Agencies Engaged in

Construction Inspection, Testing, or Special

Inspection

E543-09.................Standard Specification for Agencies Performing

Non-Destructive Testing

E605-93(R2011)..........Standard Test Methods for Thickness and Density of Sprayed Fire Resistive Material (SFRM)

Applied to Structural Members

E709-08.................Standard Guide for Magnetic Particle

Examination

E1155-96(R2008).........Determining FF Floor Flatness and FL Floor

Levelness Numbers

F3125/F3125M-15.........Standard Specification for High Strength

Structural Bolts, Steel and Alloy Steel, Heat

Treated, 120 ksi (830 MPa) and 150 ksi (1040

MPa) Minimum Tensile Strength, Inch and Metric

Dimensions

E. American Welding Society (AWS):

D1.D1.1M-10.............Structural Welding Code-Steel

1.3 REQUIREMENTS:

A. Accreditation Requirements: Construction materials testing laboratories shall be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory’s scope of accreditation shall include the appropriate ASTM standards (i.e.; E329, C1077, D3666, D3740, A880, E543) listed in the technical sections of the specifications.

Laboratories engaged in Hazardous Materials Testing shall meet the requirements of OSHA and EPA. The policy applies to the specific laboratory performing the actual testing, not just the “Corporate

Office.”

B. Inspection and Testing: Testing laboratory shall inspect materials and workmanship and perform tests described herein and additional tests requested by COR. When it appears materials furnished, or work performed by Contractor fail to meet construction contract requirements, Testing Laboratory shall direct attention of COR to such failure.

11-01-18

01 45 29 - 5

C. Written Reports: Testing laboratory shall submit test reports to COR, Contractor, unless other arrangements are agreed to in writing by the

COR. Submit reports of tests that fail to meet construction contract requirements on colored paper.

D. Verbal Reports: Give verbal notification to COR immediately of any irregularity.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 EARTHWORK:

A. General: The Testing Laboratory shall provide qualified personnel, materials, equipment, and transportation as required to perform the services identified/required herein, within the agreed to schedule and/or time frame. The work to be performed shall be as identified herein and shall include but not be limited to the following:

1. Observe fill and subgrades during proof-rolling to evaluate suitability of surface material to receive fill or base course.

Provide recommendations to the COR regarding suitability or unsuitability of areas where proof-rolling was observed. Where unsuitable results are observed, witness excavation of unsuitable material and recommend to COR extent of removal and replacement of unsuitable materials and observe proof-rolling of replaced areas until satisfactory results are obtained.

2. Provide observation of fill placement and compaction and field density testing in building areas and provide observation of fill placement and compaction and field density testing in pavement areas to verify that earthwork compaction obtained is in accordance with contract documents.

3. Provide supervised geotechnical technician to inspect excavation, subsurface preparation, and backfill for structural fill.

B. Testing Compaction:

1. Determine maximum density and optimum moisture content for each type of fill, backfill and subgrade material used, in compliance with

D1557 Method A.

2. Make field density tests in accordance with the primary testing method following ASTM D6938 or AASHTO T310 shall be utilized on a case by case basis only if there are problems with the validity of the results from the primary method due to specific site field conditions. Should the testing laboratory propose these alternative

11-01-18

01 45 29 - 6 methods, they shall provide satisfactory explanation to the COR before the tests are conducted.

a. Foundation Wall Backfill: One test per 30 m (100 feet) of each layer of compacted fill but in no case fewer than two tests.

c. Trenches: One test at maximum 30 m (100 foot) intervals per 1200 mm (4 foot) of vertical lift and at changes in required density, but in no case fewer than two tests.

f. Footing Subgrade: At least one test for each layer of soil on which footings will be placed. Subsequent verification and approval of each footing subgrade may be based on a visual comparison of each subgrade with related tested subgrade when acceptable to COR. In each compacted fill layer below wall footings, perform one field density test for every 30 m (100 feet) of wall. Verify subgrade is level, all loose or disturbed soils have been removed, and correlate actual soil conditions observed with those indicated by test borings.

C. Fill and Backfill Material Gradation: One test per stockpiled or in-place source material. Gradation of fill and backfill material shall be determined in accordance with ASTM D1140.

D. Testing for Footing Bearing Capacity: Evaluate if suitable bearing capacity material is encountered in footing subgrade.

E. Testing Materials: Test suitability of on-site and off-site borrow as directed by COR.

3.2 CONCRETE:

A. Batch Plant Inspection and Materials Testing:

1. Perform continuous batch plant inspection until concrete quality is established to satisfaction of COR with concurrence of Contracting

Officer and perform periodic inspections thereafter as determined by

COR.

2. Periodically inspect and test batch proportioning equipment for accuracy and report deficiencies to COR.

3. Sample and test mix ingredients as necessary to insure compliance with specifications.

4. Sample and test aggregates daily and as necessary for moisture content. Test the dry rodded weight of the coarse aggregate whenever a sieve analysis is made, and when it appears there has been a change in the aggregate.

11-01-18

01 45 29 - 7

5. Certify, in duplicate, ingredients and proportions and amounts of ingredients in concrete conform to approved trial mixes. When concrete is batched or mixed off immediate building site, certify

(by signing, initialing or stamping thereon) on delivery slips

(duplicate) that ingredients in truck-load mixes conform to proportions of aggregate weight, cement factor, and water-cement ratio of approved trial mixes.

3.3 REINFORCEMENT:

A. Review mill test reports furnished by Contractor.

B. Make one tensile and one bend test in accordance with ASTM A370 from each pair of samples obtained.

C. Written report shall include, in addition to test results, heat number, manufacturer, type and grade of steel, and bar size.

D. Perform tension tests of mechanical and welded splices in accordance with ASTM A370.

- - - E N D - - -