RFIs May 24.docx
DOCX document 28 KB Posted
- Attached to
- Upgrade 480V Electrical System Federal contract opportunity
- Solicitation number
- 36C24921R0084
About this file
This document contains questions and answers regarding a solicitation to upgrade the 480V electrical system at a Department of Veterans Affairs facility. The solicitation seeks a contractor to install a new 1150 KVA transformer with pad and barrier walls, upgrade the 480V switchgear, correct wiring deficiencies for CAT Scan rooms, and move electrical feeds for several air handlers and associated equipment to emergency power circuits. Transformers must be new, and shutdowns for work in the manhole and changing over power to the new transformer will be limited to 4-8 hours on preferred Fridays after 5PM with two weeks notice required. EMT is acceptable in the basement crawl space. The work in rooms A-213 and A-222 and items 4-5 on drawing EP001B are not part of any deductive alternates. Panel 2AE in room A-236j rather than 2BE is the correct panel for keynote 3 on drawing EP201. Panel EEQD is currently powered from panel D-AC-B located between rooms B-003 and B-002a next to the main basement wallway.
View the file
Other files for this federal contract opportunity
Show all 50
Upgrade 480V Electrical System has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY
RFIs Solicitation 36C249-21-R-0084 Project 603-20-505 480V Upgrade at Louisville
Question: Ref: attached New Price Schedule - New price schedule includes a lot of new spec. sections for which there are no specs. Added are price breakouts for Divisions 6, 7, 9, 10, 14, 21, 23, 27, and 28. Also Division 1 includes all new items which are not included in the specs. Also several sections of the electrical have been deleted and new sections have been included. Can a new, new price schedule be provided?
Answer: The price schedule is a reference document and template only, please edit as you see fit to include other divisions or items. Only the total for each bid item will be evaluated for reasonableness. Those totals must also be entered on the second page of the solicitation in the appropriate block.
Question: Would a used/rebuilt transformer be acceptable? Also, will there be additional specifications posted for the transformer?
Answer: Transformer must be NEW. Specification is attached.
Question: Is rigid conduit required to be installed in the basement crawl space or is EMT acceptable?
Answer: EMT is acceptable in the basement crawl space.
Question: Are Keynotes 4 and 5 on Drawing EP001B part of a deduct alternate?
Answer: No, this work is not included in any deductive alternates.
Question: What are the requirements for shutdowns for the work needed to be performed in the manhole and the work for changing over the power to the new transformer? How long of a duration can a shut down last, preferred days, etc.?
Answer: Shutdowns will be limited to 4 hours (preference) to 8 hours (acceptable). Longer outaages will need to be discussed with COR after award. Preferred days: Fridays after 5 PM. A minimum of two weeks notice is required for these shutdowns.
Question: Is panel 2BE still the correct panel to use for keynote 3 on drawing EP201?
Answer: Panel 2BE is not the correct panel. The correct panel is panel is panel 2AE in room A-236j. The location of the panel is shown on drawing EP201.
Question: Is the work in Room A-213 & A-222 part of a deduct alternate?
Answer: This work is not included in any deduct alternate.
Question: Where is the existing panel EEQD currently fed from?
Answer: Panel EEQD is currently powered from Panel D-AC-B which located in the corridor between rooms B-003 and B-002a next to the main basement wallway.