These are architectural and engineering design documents for a 1.5T MRI (Magnetic Resonance Imaging) renovation project at the James A. Haley Veterans Hospital in Tampa, Florida. The comprehensive set of drawings covers multiple disciplines including architectural, structural, mechanical, electrical, plumbing, and fire protection, detailing a complete interior renovation of approximately 1,000 square feet to replace an administrative area on the ground floor of Building 1. The project involves creating a new MRI scanner suite with a control room, scanner room, system component room, and dressing room, with specific design considerations for RF shielding, medical equipment installation, and maintaining hospital operations during construction.
The design documents specify comprehensive technical requirements, including demolition of existing walls, ceilings, floors, and systems; reconfiguration of fire sprinkler and alarm systems; installation of computer and communication systems; coordination with the MRI equipment vendor; and adherence to multiple codes including NFPA 101, IBC 2021, and VA healthcare design standards. The project is part of VA solicitation 36C24826Q0128, set aside as a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) design-build contract, with the Request for Quote anticipated to be issued on January 10, 2026, and Phase I quotes due on January 6, 2026. The basis of design is a Siemens MAGNETOM SOLA 1.5T MRI system, with the total project focusing on creating a modern, compliant medical imaging environment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 673-CSI-132 SOW RFI update.docx | DOCX document | |
| first floor drawing.pdf | ||
| 673-CSI-132 RFI Responses.docx | DOCX document | |
| WD-FL20260208 01-02-26.pdf | ||
| 36C24826Q0128 0003.pdf | ||
| 673-CSI-132 - Hazardous Materials Report 60 PERCENTAGE.pdf | ||
| second floor drawing - ACM.pdf | ||
| sign in sheet.pdf | ||
| 36C24826Q0128 0002.pdf | ||
| VA James A Haley1 5T MRI -90 CD Progress Specifications 12-15.pdf | ||
| 2510179R0-DRAWINGS.pdf | ||
| 36C24826Q0128 0001.pdf | ||
| 36C24826Q0128_1.pdf | ||
| Experience information Sheet.pdf | ||
| EMR 1 page.pdf | ||
| Base Offer Price Breakdown - 1 page.xlsx | XLSX spreadsheet | |
| PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| WD FL20250208 05232025.pdf | ||
| 2510179R0-DRAWINGS.pdf | ||
| 36C24826Q0128.docx | DOCX document | |
| 673-CSI-132 SOW.docx | DOCX document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAWING SYMBOLS
1. THESE DRAWINGS SHALL BE USED ONLY FOR THIS SPECIFIC PROJECT/SITE
LOCATION. THEY ARE A COMPOSITE SET OF CONTRACT DOCUMENTS AND SHALL NOT
BE SEPARATED FOR DISTRIBUTION. THE GC SHALL REVIEW ALL DRAWINGS AND
PROVIDE/DISTRIBUTE THE ENTIRE SET TO EACH SUBCONTRACTOR.
2. THE CONTRACTOR SHALL COMPLY WITH ALL REQUIREMENTS OF THE DRAWINGS AND
THE SPECIFICATIONS. CONTRACTOR SHALL CAREFULLY STUDY AND COMPARE THESE
DRAWINGS, THE SPECIFICATIONS, AND IMMEDIATELY NOTIFY THE DESIGN
PROFESSIONAL OF ANY INCONSISTENCIES THAT ARE DISCOVERED.
3. DO NOT SCALE THE DRAWINGS. REQUEST ANY MISSING DIMENSIONS FROM THE A/E.
4. ALL WORK PERFORMED SHALL BE IN STRICT COMPLIANCE WITH GOVERNING
FEDERAL, STATE AND LOCAL BUILDING CODE REQUIREMENTS, SHALL BE EXECUTED
IN ACCORDANCE WITH ACCEPTED INDUSTRY STANDARDS, AND SHALL CONFORM TO
SPECIFIC REGULATIONS AS MANDATED BY THE OWNER, THE ARCHITECT/ENGINEER,
AND THE AUTHORITIES HAVING JURISDICTION. THE GENERAL CONTRACTOR IS
RESPONSIBLE FOR ANY FEES ASSOCIATED WITH PROCURING SUCH PERMITS AND
CERTIFICATES AND SHALL FURNISH COPIES OF PERMITS, INSPECTIONS, TESTING AND
CERTIFICATES TO THE OWNER.
5. THE GENERAL CONTRACTOR SHALL COORDINATE ALL WORK TO MINIMIZE
DISRUPTION OF ANY EXISTING TENANTS OR BUILDING OPERATIONS. THE GENERAL
CONTRACTOR SHALL TAKE ADEQUATE PRECAUTIONS TO PROTECT BUILDING
OCCUPANTS, MATERIALS, AND EXISTING CONSTRUCTION THROUGHOUT ALL PHASES
OF CONSTRUCTION. DAMAGE TO EXISTING-TO-REMAIN CONSTRUCTION OR
EQUIPMENT SHALL BE RESTORED TO ORIGINAL CONDITION AT THE CONTRACTOR'S
EXPENSE.
6. THE GENERAL CONTRACTOR SHALL REMOVE ALL TRASH AND DEBRIS FROM THE JOB
SITE ON A DAILY BASIS.
7. ANY REQUESTS FOR SUBSTITUTIONS OF ANY SPECIFIED ITEM ARE TO BE SUBMITTED
TO THE ARCHITECT IN WRITING AND WILL BE CONSIDERED ONLY IF THE ALTERNATE
PROPOSED IS PROVEN TO BE ADVANTAGEOUS TO THE OWNER WITH RESPECT TO
DELIVERY DATE, QUALITY, OR COST.
8. THE MEANS AND METHODS OF CONSTRUCTION, AND TEMPORARY STRUCTURES AND
FACILITIES, ARE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR. THE A/E DOES
NOT ASSUME ANY RESPONSIBILITY FOR THE CONTRACTOR'S MEANS AND METHODS
OR FOR TEMPORARY STRUCTURES.
9. DEMOLITION OF EXISTING STRUCTURES IS THE RESPONSIBILITY OF THE GENERAL
CONTRACTOR. THE CONTRACTOR SHALL EMPLOY ENGINEERING EXPERTISE AS
NEEDED TO ASSIST IN DEMOLITION.
10. JOB SITE SAFETY AND SECURITY ARE THE SOLE RESPONSIBILITY OF THE GENERAL
CONTRACTOR. THE GENERAL CONTRACTOR SHALL CONSULT WITH CAMPUS AND
LOCAL FIRE AUTHORITIES TO ASCERTAIN REQUIREMENTS FOR FIRE SUPPRESSION
AND SAFETY DURING CONSTRUCTION. THE GENERAL CONTRACTOR IS SOLELY
RESPONSIBLE FOR MEETING OSHA REGULATIONS DURING CONSTRUCTION.
11. THE GENERAL CONTRACTOR IS SOLELY RESPONSIBLE FOR STORAGE AND
PROTECTION OF BUILDING MATERIALS, AND INSTALLED CONSTRUCTION, FROM
INCLEMENT WEATHER, THEFT, AND OTHER HAZARDS. THE GC SHALL FOLLOW ALL
MANUFACTURER'S RECOMMENDATIONS FOR STORAGE OF MATERIALS. PARTIALLY
COMPLETED WALLS SHALL BE COVERED TO PROTECT FROM WATER INTRUSION.
DAMAGE, INCLUDING BUT NOT LIMITED TO MOLD, RESULTING FROM WATER
INTRUSION DURING CONSTRUCTION SHALL BE REPAIRED AT THE GENERAL
CONTRACTOR'S EXPENSE.
12. IN THE CASE OF CONFLICTS OR DISCREPANCIES WITHIN OR AMONG THE CONTRACT
DRAWINGS, THE BETTER QUALITY, MORE STRINGENT REQUIREMENTS OR GREATER
QUANTITY OF WORK, AS DETERMINED BY THE GOVERNMENT, SHALL BE PROVIDED.
13. THE GC SHALL BE RESPONSIBLE FOR COORDINATING THE INSTALLATION OF NEW
UTILITIES WITH EXISTING ADJACENT UTILITIES.
14. ANY WORK NOT SHOWN ON THE DRAWINGS, BUT CONSIDERED NECESSARY FOR THE
COMPLETION OF THE WORK IN A PROPER MANNER SHALL BE PROVIDED BY THE GC
WITHOUT ADDITIONAL CHARGE.
15. WHERE PRESENT WORK IS DAMAGED IN THE EXECUTION OF THE CONTRACT OR
WHERE OPENINGS ARE LEFT DUE TO THE REMOVAL OF PIPES, CONDUITS, CABLE
TRAYS, EQUIPMENT OR APPARATUS. REPAIR OR CLOSE UP CORRESPONDING
MATERIAL FINISH TO MATCH THE ADJOINING WORK. WHERE DAMAGE IS NOT
REPAIRABLE, NEW ITEMS OR EQUIPMENT SHALL BE PROVIDED.
16. CONTRACTOR TO COORDINATE WITH THE COR FOR QUESTIONS REGARDING SITE
ACCESS OF WORKERS, MATERIAL DISPOSAL AND HOURS OF OPERATION.
17. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING AND VERIFYING
DIRECTLY WITH THE COR REGARDING ANY OWNER DESIRED CHANGES TO THE
NUMBERING SYSTEM AND/OR NAMING CONVENTION, LABELING AND/OR
IDENTIFICATION FOR (OR ON) THE ELECTRICAL PANELS, MECHANICAL EQUIPMENT,
FIRE ALARM SYSTEMS/PANELS, SIGNAGE, ETC.
OWNER:
Department of Veterans Affairs - Network 23 Contracting Office 13000 Bruce B. Downs Boulevard Tampa, Florida 33612
CONTRACTING OFFICER REP. (COR):
James A. Haley VA Medical Center 13000 Bruce B Downs Boulevard Tampa, Florida 33612
Eric Richardson eric.richardson7@va.gov
PROJECT MANAGER:
Romanyk Consulting Corp.
3308 Preston Road, Suite 350-164 Plano, Texas 75093
Rebecca Olson rebecca.olson@romanykconsulting.com
855.424.3838x302
602.430.1265 cell
MECHANICAL ENGINEER:
Romanyk Consulting Corp.
3308 Preston Road, Suite 350-164 Plano, Texas 75093
JImmy Smith, PE jimmy.smith@romanykconsulting.com
855.424.3838 x329
404.483.1297 Cell
ELECTRICAL ENGINEER:
Romanyk Consulting Corp.
3308 Preston Road, Suite 350-164 Plano, Texas 75093
Ajay Bajracharya, PE ajay.bajracharya@romanykconsulting.com
855.424.3838 x350
301.633.7584 CELL
STRUCTURAL ENGINEER:
RS&H, INC.
10748 Deerwood Park Boulevard South Jacksonville, Florida 32256
Matthew McCaul mathew.mccaul@rsandh.com
904.256.2367
ARCHITECT:
Romanyk Consulting Corp.
3308 Preston Road, Suite 350-164 Plano, Texas 75093
Gary Friedman Gary.Friedman@RomanykConsulting.com
855.424.3838 x322
720.989.8588 cell
ELEVATION NUMBER
SECTION
INTERIOR ELEVATION
ENLARGEMENT,
DETAIL
PLATE NUMBER WHERE
SECTION/DETAIL IS DRAWN
PLATE NUMBER WHERE
SECTION/DETAIL IS DRAWN
PLATE NUMBER WHERE
SECTION/DETAIL IS DRAWN
A101
SIM
EXTERIOR ELEVATION
A-101
PLATE NUMBER WHERE
SECTION/DETAIL IS DRAWN
A101
A101
TRUE NORTH
PLAN NORTHNORTH
NORTH ARROW WITH TRUE
NORTH INDICATION
ROOM
ROOM OCCUPANCY
150 SF
ROOM OCCUPANCY & AREA
SPOT ELEVATION
Name Elevation
FLOOR LEVEL &
NAME
SHEET KEYNOTE#
1i
0 GRID / COLUMN LINE DESIGNATOR
EQUIPMENT NUMBER
DOOR NUMBER
Ga5xFB1
WALL TYPE
WINDOW TYPE
ROOM NAME
ROOM NAME / NUMBER
REVISION TAG
EGRESS ROUTE ID AND
SECTION LENGTH
EGRESS : EGRESS ID
Egress Length
GENERAL NOTES PROJECT TEAM VICINITY MAP
INDEX OF DRAWINGS
TRUE NORTH
PLAN NORTHNORTH
A ---------------------
A/E ARCHITECT/ENGINEER
ACT ACOUSTICAL CEILING TILE
AFF ABOVE FINISHED FLOOR
AHU AIR HANDLING UNIT
ALT ALTERNATE
ALUM ALUMINUM
ANOD ANODIZE
APPROX APPROXIMATE
B ---------------------
BLKG BLOCKING
BOS BOTTOM OF STEEL
BSMT BASEMENT
C ---------------------
CD CONSTRUCTION DOCUMENTS
CIP CAST-IN-PLACE
CJ CONTROL JOINT
CL CENTER LINE
CLG CEILING
CMU CONCRETE MASONRY UNIT
COL COLUMN
CONC CONCRETE
CONF CONFERENCE
CPT CARPET
CT CERAMIC TILE
CTB CERAMIC TILE BASE
CTF CERAMIC TILE FLOOR
D ---------------------
DEMO DEMOLITION
DET DETAIL
DOC DOCUMENT
E ---------------------
EJ EXPANSION JOINT
EL ELEVATION
ELEC ELECTRICAL
ELEV ELEVATOR
EXP EXPOSED
OFF OFFICE
OPR OPERABLE
ORD OVERFLOW ROOF DRAIN
P --------------------
PCC PRECAST CONCRETE
PLYWD PLYWOOD
Q --------------------
QTY QUANTITY
R --------------------
RCP REFLECTED CEILING PLAN
RD ROOF DRAIN
REC RECESSED
REQD REQUIRED
RM ROOM
RO ROUGH OPENING
S --------------------
SCHED SCHEDULE
SF SQUARE FOOT (FEET)
SIM SIMILAR
SPEC SPECIFICATION
ST STAIRS
STD STANDARD
STOR STORAGE
T --------------------
TEMP TEMPORARY
TFF TOP OF FINISH FLOOR
TN TRUE NORTH
TOF TOP OF FOOTING
TOP TOP OF PARAPET
TOS TOP OF SLAB
NOTES:
1. NOT ALL LISTED ABBREVIATIONS MAY BE USED.
2. SEE OTHER DISCIPLINES FOR ADDITIONAL ABBREVIATIONS.
F ---------------------
FD FLOOR DRAIN
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FIN FINISH
FRT FIRE RETARDANT TREATED
G ---------------------
GALV GALVANIZED
GYP BD GYPSUM BOARD
H ---------------------
HB HOSE BIBB
HM HOLLOW METAL
I ---------------------
IBC INTERNATIONAL BUILDING CODE
INSUL INSULATION
L ---------------------
LAV LAVATORY
LT LIGHT
M ---------------------
MACH RM MACHINE ROOM
MAX MAXIMUM
MECH RM MECHANICAL ROOM
MFR MANUFACTURER
MTL METAL
N ---------------------
N NORTH
NA NOT APPLICABLE
NFPA NATIONAL FIRE PROTECTION ASSOC.
NIC NOT IN CONTRACT
NRC NOISE REDUCTION COEFFICIENT
NTS NOT TO SCALE
O -------------------
OFD OVERFLOW DRAIN
ARCHITECTURAL ABBREVIATIONS
BUILDING LOCATION
DISCIPLINE DESIGNATOR
MAJOR:
GENERAL - G
ARCHITECTURE - A
PLUMBING - P
MECHANICAL - M
ELECTRICAL - E
BUILDING NUMBER
11 - AE101
SHEET TYPE
DESIGNATOR
DISCIPLINE DESIGNATOR
(MINOR):
SHEET NUMBER
WITHIN SERIES
FIRE PROTECTION:
RS&H, INC.
10748 Deerwood Park Boulevard South Jacksonville, Florida 32256
Scott Dubin scott.dubin@rsandh.com
904.256.2336
Romanyk Consulting Focusing on what matters
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
F
U.S. Department of Veterans Affairs
E
D
C
B
A
F
E
D
C
B
A
910 7 6 5 4 3 2 1
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
8910 7 6 5 4 3 2 1
Romanyk Consulting Corp. www.romanykconsulting.com 3308 Preston Road, Suite 350-164, Plano, Texas 75093
NOT FOR
PERMITTING OR
CONSTRUCTION
Consultant:
Sprinklered
U.S. Department of Veterans Affairs
Sprinklered
A/E
/5
/2
:1
:0
A M
A ut od es k D oc s:
//V
IS
N
T am pa A
E
.5 T
M R
I I C
C /V
A J am es
A H al ey
.5
T M
R I_
A _R
-A
R C
H N
E W
.r vt
COVER SHEET
AW/GF/LN SE
9/05/2025
James A. Haley VA Medical
Center, Tampa, Florida
673-CSI-132
PROJECT NUMBER - 673-CSI-132
1.5T MRI ICC
90% PROGRESS SET 1.5T MRI ICC
VA: _______________
90% PROGRESS SET
9/05/2025
01-GI101James A. Haley VA Medical Center, Tampa, Florida
13000 BRUCE B DOWNS BLVD.
TAMPA, FL 33612
NOTE: These documents were prepared using the Siemens MAGNETOM SOLA 1.5T MRI equipment as a "Basis of Design". If the MRI equipment selected for the project changes, the new equipment will need to be evaluated to verify compatibility with current design and documents
Revisions: Rev: Date:
WELL
x
GATE
GATE
GATE
GATE
GATE
GATE
GATES
GATE
GATE
GATE
GATE
GATE
(3.04 ACRES)
100-YEAR OVERFLOW DEVICE
RETENTION POND "A"
RETENTION POND "C"
CONCRETE
PAD
POLE
TRANS. PAD
EXIT
ENTER
LC OF R/W
18' ASPHALT PAVEMENT
30' R/W (P)
(F
)LC
O F A
SP
HALT
R
C P
S
L
SIGN
SIGN
SIGN
SKY WALK
ISLAND
ISLAND
POST
MC ONLY
F
IS
H E R H
O U S E P
A R K
IN
G A
R E A
E
P S
PLAN TER
PLANTERS
CONC. SL AB
TRASH
S-2
DO WN
' W
ID
E
C O
N C
RE
TE
SID
E
W
ALK
6' WIDE CONC. SIDEWALK
:1
S L
O P
E (T
Y P
IC
A
L
4:1 SLOPE
(TYP ICAL)
:1
S L
O P
E
(T Y
P
IC
A L)
P E
R
IM
E
TE
R
SID
EW
ALK
X X
X X
XXXX
X
X
X
X
X
X X
X
A/C
A/C A/C
A/C
A/C
6' High Brick Enclosure
C O
M P
A C
T
O N
L Y
O N
L Y
C O
M P
A C
T
C O
M P
AC
T
O N
LY
C O
M P
AC
T
O N
LY
O N
LY
C O
M P
AC
T
O N
LY
C O
M P
AC
T
MOTORCYCLE
PARKING
POST
S
S
BB
BB
S
S
S
S
POST
POST
S
S
S
S
SSSS
D
S
KEY NOTES
1. SITE ACCESS FOR CONTRACTOR
PERSONNEL AND MATERIAL
DELIVERY.
2. DESIGNATED PARKING FOR
CONTRACTOR.
3. SECURE, CONTRACTOR STAGING AND
LAYDOWN AREA.
4. CONTRACTOR EQUIPMENT
REPLACEMENT ACCESS AND PATH.
5. BUILDING 1 AREA OF RENOVATION.
6. CONTRACTOR BUILDING ACCESS.
7. CONTRACTOR BUILDING ACCESS TO
ELEVATOR.
8. CONTRACTOR TOILET.
BLDG
NO.
BLDG NAME
BLDG
NO.
BLDG NAME
T33
MAIN HOSPITAL
RESEARCH
GROUNDS
OXYGEN TANKS
VETERNAS BENEFITS
WATER TOWER
COOLING TOWER #2
FLAMMABLE STORAGE
ENG/EMS STORAGE
BOTTLE GAS STORAGE
RECREATION STORAGE
NURSING HOME CARE UNIT
RADIATION THERAPY UNIT
GENERATOR (BLDG #30)
STEAM CLEANING
EYE CLINIC
HAZARDOUS STORAGE
SPINAL CORD INJURY
CENTRAL ENERGY PLANT
ADMINISTRATIVE ANNEX #2
ADMINISTRATIVE ANNEX
BACKFLOW PREVENTOR
GAZEBO
TOTEM POLE
FISHER HOUSE
GENERATOR/ POWER PLANT
PET SCAN
BLDG 32 SUBSTATION
BLDG 30 SUBSTATION
POLYTRAUMA SUPPORT, TRANS HSNG
HAZARDOUS STORAGE #2
NURSING STATION
BLDG
NO.
BLDG NAME
T34 T43 T50 T51 T57 T58 T59 T60 T61 T62 T65 T66 T67 T70 T71 T74
STORAGE TRAILER
SMOKING SHELTER
EMS
BUSINESS OFFICE
COMP & PEN
AGENT ORANGE
DSS/EMPLOYEE TRAVEL
HAS
EEO/UNASSIGNED
CONFERENCE
TRAILER
TRAILER
TRAILER
TRAILER
TRAILER
GERIATRIC CLINIC
1. REGULAR MEDICAL CENTER BUSINESS HOURS ARE 0700 - 1530, SOME AREAS FUNCTION 24
HOURS A DAY, 7 DAYS A WEEK.
2. THE CONTRACTOR SHALL PROVIDE ALL REQUIRED CONSTRUCTION, SAFETY, AND ICRA
BARRIERS APPROVED BY COR BEFORE CONSTRUCTION COMMENCES WITH THE ICRA
PERMIT DISPLAYED DURING CONSTRUCTION FOR EACH PHASE.
3. ANY UTILITY SHUTDOWNS WILL REQUIRE THREE (3) WEEKS OR (21) CALENDAR DAYS NOTICE
AND ANY SHUTDOWNS THAT MAY DISRUPT NORMAL MEDICAL CENTER OPERATIONS MAY
NEED TO BE PERFORMED OUTSIDE REGULAR MEDICAL CENTER BUSINESS HOURS.
MAINTAIN UNINTERRUPTED OPERATION OF THE EXISTING FACILITIES, AND MINIMIZE
DISRUPTIONS TO THE MEDICAL CENTER FOR ALL SWITCH-OVER OF UTILITIES. COR
RESERVES THE RIGHT TO DETERMINE THE SEVERITY OF THE SHUTDOWN.
4. THE GC SHALL COORDINATE WITH THE COR TO DEVELOP A CRITICAL PATH METHOD (CPM)
SCHEDULE, SEQUENCING, COMPLETION DATES FOR RENOVATION AND NEW CONSTRUCTION
FOR THE PROJECT.
5. THE MEDICAL CENTER MUST REMAIN IN FULL OPERATION DURING CONSTRUCTION WITH
MINIMAL INTERRUPTION DUE TO ALL CONSTRUCTION ACTIVITES FOR THE PROJECT,
INCLUDING NOISE, DUST, VIBRATION, ETC., CREATED BY CONSTRUCTION ACTIVITIES
RELATED TO THIS PROJECT.
6. THE GC'S SCHEDULES SHOULD INCLUDE BUT IS NOT LIMITED TO THE FOLLOWING:
A. ALL CONSTRUCTION-ACTIVITIES-RELATED ISSUES WHICH MAY AFFECT THE CONTINUAL
OPERATIONS OF THE MEDICAL CENTER.
B. SCHEDULES FOR SHUTTING DOWN EXISTING SYSTEMS OR ACCESS FOR TIE-INS AND/OR
REPLACEMENT.
C. SCHEDULES FOR AFTER-HOURS OR WEEKEND CONSTRUCTION ACTIVITIES. BARRIERS
AND OTHER PROTECTIVE MEASURES SUCH AS ISOLATING THE HVAC SYSTEM IN AREAS
WHERE WORK IS BEING DONE TO PREVENT CONTAMINATION OF DUCTS, ETC.IBC (2021)
CHAPTER 33 SAFEGUARDS DURING CONSTRUCTION 3302.1 AND 1007.3.5 MAINTAIN
REQUIRED CORRIDOR EGRESS AT TEMPORARY BARRIERS AND PROVIDE SIGNAGE.
D. THE GC SHALL CONSULT WITH COR FOR SITE ACCESS INCLUDING ELEVATORS AND
DEBRIS/MATERIAL HAUL ROUTES.
7. IF MEDICAL CENTER ACCESS PATHWAYS AND ELEVATORS ARE REQUIRED TO BE BLOCKED
OR USED TEMPORARILY TO ACCOMMODATE CONSTRUCTION, COORDINATE ALTERNATE
PATHWAYS WITH THE COR AND PROVIDE TEMPORARY SIGNAGE AND TEMPORARY
PROTECTIVE BARRIERS TO CREATE ALTERNATE PATHWAYS AS REQUIRED. COORDINATE
AND SCHEDULE ANY DOWNTIME FOR THESE ROUTES WITH THE COR.
8. MAINTAIN ACCESS TO ALL EXISTING BUILDINGS, UTILITIES AND FACILITIES WITHIN THE
CONSTRUCTION LIMITS TO ACCESS EQUIPMENT AND TO PROVIDE SERVICE OR
MAINTENANCE OF EXISTING FACILITIES AND EQUIPMENT SERVING THE MEDICAL CENTER.
9. SOME NON STATIONARY EQUIPMENT (EQUIPMENT SITTING ON A COUNTERTOP OR MOBILE
UNITS) MAY BE MOVED. CONTRACTOR TO IDENTIFY AND REQUEST THE MOVEMENT OF THE
EQUIPMENT WITHIN THEIR CONSTRUCTION SCHEDULE. ONLY MEDICAL CENTER PERSONNEL
WILL BE ALLOWED TO MOVE MOBILE EQUIPMENT.
10. CONTRACTOR SHALL BE RESPONSIBLE FOR TEMPORARILY COVERING, PROTECTION,
MOVING AND/OR STORAGE OF ALL FURNITURE AND EQUIPMENT RELATED TO THE PROJECT.
11. ALL LARGE CONSTRUCTION MATERIAL OR EQUIPMENT DELIVERIES, DEBRIS REMOVAL TO
BE COORDINATED WITH THE COR.
12. THE VA HAS DETERMINED THE RENOVATION AREA IS 100% ASBESTOS FREE.
13. PERSONNEL IN THE PHASED RENOVATION UP-GRADE AREA WILL BE TEMPORARILY
RELOCATED DURING CONSTRUCTION.
PROJECT NOTES CODE ANALYSIS
DEPARTMENT OF VETERANS AFFAIRS
JAMES A. HALEY VETERANS' HOSPITAL
13000 BRUCE B. DOWNS BOULEVARD
TAMPA, FLORIDA 33612
PROJECT CODE DATA
THIS PROJECT WILL PROVIDE AN INTERIOR RENOVATION OF APPROXIMATELY 1000 SF FOR A NEW 1.5T MRI SCANNER SUITE TO REPLACE AN ADMINSTRATIVE AREA ON THE GROUND FLOOR OF BUILDING 1. THE PROGRAM SCOPE INCLUDES THE ADDITION OF A CONTROL ROOM, SCANNER
ROOM, SYSTEM COMPONENT ROOM AND DRESSING ROOM.
THE FOLLOWING IS A SUMMARY OF THE PROJECT SCOPE:
1. THE COMPLETE DEMOLITION OF WALLS, CEILINGS, FLOORS, ELECTRICAL, AND MECHANICAL SYSTEMS.
2. RECONFIGURATION OF THE FIRE SPRINKLER AND ALARM SYSTEMS.
3. THE INSTALLATION OF COMPUTER AND COMMUNICATION SYSTEMS SUCH AS A NURSE CALL.
4. COORDINATION WITH THE MRI EQUIPMENT VENDOR.
5. THE DESIGN OF NEW WALLS, FLOORS, CEILINGS, CASEWORK, ELECTRICAL AND MECHANICAL SYSTEMS.
6. THE AE RADIOLOGY PHYSICIST WILL PROVIDE TEMPLATES FOR THE MRI AND REPORT SPECIFYING THE SHIELDING REQUIREMENTS, ETC. AND
DURING CONSTRUCTION CERTIFY THAT THE SHIELDING HAS BEEN INSTALLED PER THE DOCUMENTS.
7. EQUIPMENT ROUTE AND STRUCTURAL SLAB REVIEW AND ANCHORAGE BY THE AE TEAM.'
8. DESIGN DOCUMENTATION CONSIDERATIONS/ SCHEDULE FOR LIFE SAFETY, PHASING, ICRA BARRIERS, SECURITY AND TIME MANAGEMENT
WHERE PRIMARY WORK IMPACTS PATIENTS AND STAFF WITH MINIMUM DOWNTIME.
9. ADDRESS FIRE AND SMOKE PENETRATIONS THROUGH WALLS AND FLOORS.
10. SITE PLAN AND BUILDING DOCUMENTATION SHOWING PROPOSED CONTRACTOR ACCESS, PARKING, LAYDOWN AREAS, TRAILER, ETC.
11. VA HAS DETERMINED WORK SCOPE DOES NOT CONTAIN ANY HAZARDOUS MATERIALS AND/OR ASBESTOS.
SCOPE OF WORK
APPLICABLE CODES AND DESIGN CRITERIA
2024 NFPA 101 NATIONAL FIRE PROTECTION ASSOCIATION LIFE SAFETY CODE
NATIONAL FIRE CODES, EXCEPT FOR NFPA 5000 AND NFPA 900
2021 IBC INTERNATIONAL BUILDING CODES
7/1/23 OSHA OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION
2023 NEC NATIONAL ELECTRIC CODE
2021 IPC INTERNATIONAL PLUMBING CODE
11/1/22 ABAAS ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS INCLUDING VA SUPPLEMENT, BARRIER FREE DESIGN
(PG-18-13)
PG 18-2 IMAGING SERVICE DESIGN GUIDE TABLE 2.3.1: IMAGING ROOM CLASSIFICATION (CLASS 2 INTERVENTIONAL
MODERATE SEDATION/GENERAL ANESTHESIA
PG 18-2 IMAGING SERVICE DESIGN GUIDE CI121:
A. NURSE CALL/CODE BLUE
B. CAMERA AND CEILING MOUNTED MIRROR BEHIDN THE MRI.
C. SOUND SYSTEM
CODES AND LIFE SAFETY STANDARDS
VA MASTER CONSTRUCTION SPECIFICATIONS. (http://www.cfm.va.gov/til/spec.asp) VA DESIGN MANUALS. (https://www.cfm.va.gov/til/dManual.asp) VA DESIGN CRITERIA. (https://www.cfm.va.gov/til/criteria.asp) LEADERSHIP IN ENERGY AND ENVIRONMENTAL DESIGN (LEED) CERTIFICATION. CURRENT REVISION.
IMAGING SERVICES DESIGN GUIDE SEPTEMBER 1, 2020, REV. 8/1/23
VHA DIRECTIVE 1105.05 ON MAGNETIC RESONANCE (MR) SAFETY
CLASS 2 MRI SCANNING ROOM, IMAGING SERVICES (CI121)
VA SEISMIC DESIGN REQUIREMENTS, H-18-8
APPLICABLE VA STANDARDS
IBC OCCUPANCY GROUP INSTITUTIONAL I-2 HOSPITAL SECTION 308.3
NFPA 101 OCCUPANCY GROUP EXISTING HEALTHCARE OCCUPANCIES CHAPTER 19 AMBULATORY HEALTHCARE AND 43 REHABILITIATION
IBC OCCUPANCY LOAD FACTOR TABLE 1004.5 INSTITUTIONAL 1-2 HOSPITAL 100 GSF
NFPA 101 TABLE 7.3.1.2 OCCUPANT LOAD FACTOR EXISTING HEALTHCARE USE AMBULATORY HEALTH CARE 150 GSF
OCCUPANCY LOAD 1020 GSF/100=10
OCCUPANCY GROUP
BASEMENT 1,070 SF
GROUND FLOOR 1,070 SF
BUILDING 1 AREA OF RENOVATION
IBC I-B TABLE 601; FULLY SPRINKLERED
NFPA 101 TYPE I (322) CHAPTER 19 EXISTING HEALTHCARE OCCUPANCY AMBULATORY HEALTHCARE OCCUPANCIES TABLE 19.1.6.1
BUILDING CONSTRUCTION CLASSIFICATION
I-B
3 HR PRIMARY STRUCTURAL FRAME
2 HR BEARING WALLS -- EXTERIOR
2 HR BEARING WALLS -- INTERIOR
NON-BEARING WALLS AND PARTITIONS TABLE 602
O HR NON-BEARING WALLS AND PARTITIONS TABLE 602
2 HR FLOOR CONSTRUCTION AND SECONDARY MEMBERS SECTION 202
1 1/2 HR ROOF CONSTRUCTION AND ASSOCIATE SECONDARY MEMBERS SECTION 202
FIRE RESISTANCE RATING REQUIREMENTS FOR BUILDING ELEMENTS PER IBC TABLE 601
OCCUPANCY SEPARATION NFPA 101 TABLE 6.1.14.4.1(A)
100 FT COMMON PATH OF TRAVEL LIMIT EXISTING HEALTH CARE
20 FT DEAD END LIMIT EXISTING HEALTH CARE
200 FT TRAVEL DISTANCE LIMIT EXISTING HEALTH CARE
NFPA 101 TABLE A.7.6 COMMON PATH, DEAD-END AND TRAVEL DISTANCE LIMITS (BY OCCUPANCY)
CLASS B INTERIOR EXIT STAIRWAYS AND RAMPS (SPRINKLERED)
CLASS B CORRIDORS AND ENCLOSURE FOR EXIT ACCESS STAIRWAYS AND RAMPS (SPRINKLERED)
CLASS B ROOMS AND ENCLOSED SPACES (SPRINKLERED)
INTERIOR FINISHES PER IBC TABLE 803.13
AN INFECTION CONTROL ASSESSMENT 2.0, TABLE 1 (ACTIVITY TYPE D), TABLE 2 (PATIENT RISK GROUP HIGH), TABLE 3 PATIENT RISK GROUP D V)
INFECTION CONTROL -- ICRA
SHEET INDEX
RF SHIELDED GENERAL NOTES /
REQUIREMENTS
1. THE RF SHIELDING WALL ASSEMBLY TO PROVIDE A MINIMUM OF 40 STC.
2. THE VENDOR WILL BE RESPONSIBLE FOR THE DESIGN AND INSTALLATION OF WALLS,
CEILINGS, WALLS, FLOORS, EQUIPMENT, EXHAUST, WINDOWS AND DOORS, ETC.
3. RF SHIELDING VENDOR TO COORDINATE WITH GC FOR HE STRUCTURE, WEIGHT . WALL
TYPES, PLUMBING, MECHANICAL AND ELECTRICAL DISCIPLINES.
4. VERIFY THAT THE SUB FLOOR AND CEILING OF EXISTING STRUCTURE MEET THE RF SHIELD
REQUIREMENTS AND APPLICATION FINISHES
5. COORDINATE ABOVE CEILING CONCEALED MOUNTING FOR SCAN ROOM EQUIPMENT, ETC.
6. PROVIDE SHOP DRAWINGS AND VERIFY BUILDING AREA AND PATH OF MAGNET IS
SUFFICIENT.
7. THE DRAWINGS AND DETAILS SHOW DESIGN INTENT ONLY. VENDOR TO PROVIDE
DELEGATED DESIGN ENGINEERING.
ELEMENTS REQUIRING ITEMS FLORIDA
PRODUCT APPROVALS, NOA
ALL COMPONENTS OF THE PRIMARY ENVELOPE INCLUDING BUT NOT LIMITED TO THE
FOLLOWING REQUIRED FLORIDA PRODUCT APPROVALS (TESTING)
1. LOUVERS
2. MECHANICAL SYSTEMS
3. ROOF SYSTEMS
4. RAILINGS
5. EXTERIOR DOORS AND WINDOWS
DELEGATED DESIGN SUBMITTALS
1. RF SHIELDING
2. FLOOR SHORING (SUBMITTALS SHALL BE SIGNED AND SEALED B A PROFFESSIONAL
ENGINEER REGISTERED IN THE STATE OF FLORIDA.
132ND AVENUE
POND
POND
DO0CTORS
WALK-IN CLINIC
131ST AVENUE
131ST AVENUE
L
IV
IN
G
S T
O N
A V
E N
U E
T
H S
T R
E E
T
T
H S
T R
E E
T
T
H R
O W
T
H S
T R
E E
T
HARTLINE BUS
UNIVERSITY
NORTH
TRANSFER
STATION
WAL-MART BANK
T
H S
T R
E E
T B
R U
C E
B . D
O W
N S
B O
U L
E V
A R
D
T H
S T
R E
E T
WOODED AREA
42A 42B42
35 21
T74
T33T50T51
T34
19T43
T57
T58
T59
T67
T66
T70
T71 T65 T62
T61
T60
TRUE NORTH
PLAN NORTHNORTH
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/3 2"
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/2
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
0"
Romanyk Consulting Focusing on what matters
VA FORM 08 - 6231
F
U.S. Department of Veterans Affairs
E
D
C
B
A
910 7 6 5 4 3 2 1
8910 7 6 5 4 3 2 1
NOT FOR
PERMITTING OR
CONSTRUCTION
E
D
C
B
A
F
Sprinklered
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
Romanyk Consulting Corp. www.romanykconsulting.com 3308 Preston Road, Suite 350-164, Plano, Texas 75093
Consultant:
Sprinklered
A/E
A ut od es k D oc s:
//V
IS
N
T am pa A
E
.5 T
M R
I I C
C /V
A J am es
A H al ey
.5
T M
R I_
A _R
-A
R C
H N
E W
.r vt
9/ 5/
:1
2:
A M
SHEET INDEX, OVERALL SITE PLAN, PROJECT
NOTES, AND CODE SUMMARY
AW/GF/LN SE
90% PROGRESS SET 673-CSI-132
1.5T MRI ICC
James A. Haley VA Medical Center, Tampa, Florida
9/05/2025
James A. Haley VA
Medical Center, Tampa, Florida
VA: _______
01-GI102
SCALE: N.T.S.1
OVERALL SITE PLAN
SHEET NUMBER SHEET NAME
01-GI101 COVER SHEET
GI102 SHEET INDEX, OVERALL SITE PLAN, PROJECT NOTES, AND CODE SUMMARY
GI103 ACCESSIBILITY DETAILS
GI104 ICRA NOTES & DETAILS
GI105 GROUND FLOOR OVERALL PLAN
GI106 BASEMENT FLOOR OVERALL PLAN
GI107 ENLARGED GROUND LEVEL & BASMENT LIFE SAFETY TRANSPORT AND DELIVERY ICRA PLAN
GI109 PHASING PLAN
GI110 PARTITION TYPES
GI111 PARTITION DETAILS
AD101 GROUND FLOOR AND REFLECTED CEILING DEMOLITION PLANS
AE101 GROUND FLOOR MRI CONSTRUCTION PLAN AND REFLECTED CEILING PLAN
AE104 ROOF 1 PLANS
AE105 ROOF 2 PLAN
AE106 ROOF 3 PLAN
AE107 ROOF DETAILS
QH101 NEW EQUIPMENT PLAN
AE522 SHIELDING DETAILS
AE523 SHIELDING DETAILS
AE524 SHIELDING DETAILS
AE601 DOOR & WINDOW SCHEDULE, TYPES AND DETAILS
AI701 FINISH PLAN & SCHEDULE
AI702 INTERIOR ELEVATIONS
AI703 MILLWORK DETAILS
AI705 INTERIOR DETAILS
FA101 GROUND FLOOR MRI FIRE ALARM
FX101 GROUND FLOOR MRI FIRE PROTECTION PLAN
P-001 PLUMBING SYMBOLS, NOTES, AND ABBREVIATIONS
PD401 GROUND LEVEL - PLUMBING DEMOLITION - ENLARGED PLAN
PD402 GROUND LEVEL MED GAS DEMOLITION ENLARGED PLAN
PP401 GROUND LEVEL PLUMBING PRESSURE ENLARGED PLAN
PW401 GROUND LEVEL DWV PARTIAL PLAN
PX401 GROUND LEVEL MED GAS ENLARGED PLAN
M-001 MECHANICAL SYMBOLS, NOTES, AND ABBREVIATIONS
MD111 ROOF HVAC DEMOLITION PARTIAL PLAN
MD112 ROOF PIPING DEMOLITION PARTIAL PLAN
MD401 GROUND LEVEL HVAC DEMOLITION ENLARGED PLAN
MD402 GROUND LEVEL PIPING DEMOLITION ENLARGED PLAN
MP101 BASEMENT LEVEL PIPING PARTIAL PLAN
MP102 GROUND LEVEL PIPING PARTIAL PLAN
MP111 ROOF PIPING PARTIAL PLAN
MH111 ROOF HVAC PARTIAL PLAN
MP401 GROUND LEVEL PIPING ENLARGED PLAN
MP402 MECHANICAL PIPING ENLARGED PLANS
M-704 MECHANICAL CONTROLS
MH401 GROUND LEVEL HVAC ENLARGED PLAN
M-501 MECHANICAL DETAILS
M-502 MECHANICAL DETAILS
M-503 MECHANICAL DETAILS
M-504 MECHANICAL DETAILS
M-505 MECHANICAL DETAILS
M-506 MECHANICAL DETAILS
M-601 MECHANICAL SCHEDULES
M-602 MECHANICAL SCHEDULES
M-701 MECHANICAL CONTROLS
M-702 MECHANICAL CONTROLS
M-703 MECHANICAL CONTROLS
GENERAL NOTES
1. SEE SPECIFICATIONS FOR MANUFACTURERS INFORMATION ON ALL TOILET ACCESSORIES
SPECIFICATION SECTION 10 28 00 TOILET, BATH AND LAUNDRY ACCESSORIES.
2. FOR ALL TOILET ROOM ACCESSORIES REFER TO DRAWINGS FOR PARTITION TYPES, DETAILS AND
BLOCKING REQUIREMENTS.
3. ALL GRAB BARS SHALL COMPLY WITH ANSI A117.1 REINFORCING CONCEALED IN WALL TO RESIST AN APPLIED FORCE OF 250 LB-FT IN ANY DIRECTION. GRAB BARS SHALL NOT ROTATE WITHIN THEIR
FITTINGS.
T-SHAPED TURNING SPACE TURNING RADIUS
5' - 0"
5' - 0"
5'
1'
3'
1'
2' - 0" 3' - 0"
CHANGES IN LEVEL
1/ 4"
M A
X
OUTLETS AT
MILLWORK
4'
CL
PHONE HACK, ELECTRICAL
OUTLET, SWITCH AND
PULL BOX
WINDOW TREATMENT/
PROJECT SCREEN SWITCH
ELECTRIC
OUTLET
PHONE
JACK
1'
CL
CL
MPS
MS
4'
OUTLETS AT
MILLWORK
2'
CL
OUTLETS AT
COUNTERS
OUTLETS AT
COUNTERS W/
BACKSPLASH
2'
" 3'
CL
3'
3'
CL
4" 3'
NOTE:
1. 60" DIAMETER SPACE
MIN.
5' - 0"
M
IN
5'
NOTE:
1. T-SHAPED SPACE FOR 180
DEGREE TURNS
M
IN
3'
"M
IN
5'
MIN.
1' - 0"
MIN.
3' - 0"
MIN.
1' - 0"
NOTE:
1. DIMENSIONS SHOWN APPLY WHEN
'X' IS LESS THAN 48"
2. TURNS AROUND AN OBSTRUCTION
M
IN
4'
MIN.
3' - 6" 1' - 0"
MIN.
3' - 6"
NOTE:
1. 90 DEGREE TURN
M
IN
3'
MIN.
3' - 0" 1' - 0"
MIN.
3' - 0"
NOTE:
1. TWO HINGED DOORS IN SERIES
2' - 6"
4'
NOTE:
1. TWO HINGED DOORS IN SERIES
M
IN
4'
NOTE:
1. TWO HINGED DOORS IN SERIES
M
IN
4'
NOTE:
1. MANEUVERING CLEAR
2. LATCH SIDE APPROACH
MIN.
2' - 0"
PULL SIDE
M
IN
4'
NOTE:
1. MANEUVERING CLEAR
2. FRONT APPROACH
MIN.
1' - 6"
PULL SIDE
M
IN
5'
NOTE:
1. MANEUVERING CLEAR
2. HINGE SIDE APPROACH
MIN.
3' - 0"
PULL SIDE
M
IN
4'
NOTE:
1. MANEUVERING CLEAR
2. HINGE SIDE APPROACH
PUSH SIDE
M
IN
4'
NOTE:
1. MANEUVERING CLEAR
2. FRONT APPROACH
PUSH SIDE
M
IN
4'
NOTE:
1. MANEUVERING CLEAR
2. FRONT APPROACH
PULL SIDE
M
IN
4'
MIN.
4' - 6"
MIN.
1' - 0"
MIN.
2' - 0"
PANIC BAR
CL
5" E
Q E
Q
PANIC BAR
PUSH / PULL
CL
3'
5" E
Q
DEAD BOLT
PUSH PLATE
PULL BAR
4'
4'
/2
CL
NOTES:
1. PROVIDE INTERIOR SIGNAGE FOR EVERY DOOR/ROOM
UNLESS NOTED OTHERWISE (REFER TO FINISH DRAWINGS).
2. ALL FINAL ROOM NAMES SHALL BE APPROVED BY
ARCHITECT/OWNER PRIOR TO SIGN FABRICATION.
3. AT LOCATIONS WHERE THERE ISN'T AVAILABLE WALL SPACE
TO INSTALL THE INTERIOR SIGNAGE AS INDICATED, OBTAIN
ARCHITECT'S INSTRUCTION PRIOR TO INSTALLATION.
4. AT LOCATIONS WHERE THERE ISN'T AVAILABLE WALL SPACE,
BUT AVAILABLE WINDOW SPACE, ADHERE INTERIOR SIGNAGE
WITH DOUBLE SIDED TAPE TO PROVIDE A PERMANENT
INSTALLATION. PROVIDE A BLANK PANEL OF THE SAME
COLOR, SIZE, AND MATERIAL FOR THE BACK SIDE OF THE
SIGN TO BE INSTALLED ON THE GLASS.
T O
P O
F S
IG
N
5'
DOOR FRAME
LATCH SIDE OF
DOOR PANEL
INTERIOR SIGNAGE
TO TOP OF SIGN
3'
M A
X
2'
0"
M A
X
2'
M
IN
TOE CLEARANCE
6" MAX.
DEPTH
17" MIN.
8" MIN. KNEE CLEARANCE
B O
T T
O M
O F
R E
F
LE
C T
IV
E
S U
R F
A C
E
M
IN
3' - 0" ø
'-0
1' - 6"1' - 3"
4"
5' - 9"
1' - 6" 3' - 6"
6"
3' - 10"
M
IN
60" X 56" MIN. CLR.
FLOOR SPACE
(WALL MTD.)
60" X 59" MIN. CLR.
FLOOR SPACE
(FLR. MTD)
30" X 48" MIN. CLR.
FLOOR SPACE AT
LAVATORY
60" X 50" MIN. CLR.
FLOOR SPACE AT
STALL DOOR
STALL DOOR SHALL BE
4" MAX. FROM THE
CORNER OF THE STALL
3' - 0" MIN.
1' - 6"
M
IN
5' - 0" MIN.
4" MAX.
2' - 8" MIN.
M
IN
M
IN
W A
L L M
T D
M
IN
F
L R
M
T D
42" MIN LATCH APPROACH
OTHER APPROACHES 48"
MIN.
5' - 0" MIN.
CLEAR FLOOR
SPACE
MIN.
1' - 6"
M
IN
W
A L
L M
T D
M
IN
F
L R
M
T D
M
IN
MIRROR SOAP DISPENSER PAPER
TOWEL
DISPENSER
TOILET PAPER
DISPENSER
TOILET
PAPER
HOLDER
SANITARY
NAPKIN
DISPOSAL
LAVATORY
INSULATE EXPOSED
PIPING WITH WHITE
PLASTIC PRE-FITTED
INSULATION
MEASURE
TO BOTTOM
OF REFLECTIVE
SURFACE
FIRE
EXTINGUISHERS
AND CABINETS
7-PEG
COAT RACK
2' - 0"
MIN
8"
MIN
11"
KNEE AND TOE
CLEARANCES
E
E
SEALANT
PROVIDE ADA
COMPLIANT FAUCET
WITH WRIST BLADE
CONTROLS
5" MAX
ACCESS HGT. D.F.
SPOUT LOCATION
SPOUT
HEIGHT
STANDING AND
ACCESSIBLE DRINKING
FOUNTAINS
FRONT SIDE
PLAN
ALUM. SEMI-RECESSED CAB.
W/ FULL CLEAR ACRYLIC DOOR
10 LBS
ABC TYPE
BABY CHANGING
TABLE
ROBE
HOOK
"FIRE EXTINGUISHER" IN
RED LETTERS
G
F
F
(ALT)H
J
C
N O O
P
P
MIN
11"
8"
30x48
CLEAR
SPACE
U
TOILET
SEAT COVER
DISPENSER
SIGNAGE
(12" BELOW CEILING)
2"
HANDRAIL
PER NFPA 10
PTD (OF/OI)
PUBLIC TLTS
ONLY
SEMI-
RECESSED
WASTE RECP.
S T
A N
D
IN
G H
E
IG
H T
D .F
A C
C E
S S
H
E
IG
H T
D .F
NOTE: PROVIDE CANE
DETECTABLE APRON AT
THE STANDING HEIGHT
UNIT
MIN
3' - 6"
WATER CLOSET
SIDE WALL
1 1/4" MIN., 2" MAX DIA.
GRAB BAR WITH 1 1/2"
GAP FROM WALL
WATER CLOSET
BACK WALL
TP DISPENSER
MOUNTING AREA
MIN
1' - 0"
MIN
2' - 0"
FLUSH CONTROLS
ON OPEN SIDE
GB42
GB36
A
A
/2
U
CENTER ON
GRAB BAR END
NOTE: GRAB BARS
SHALL BE 33" - 36" TO
TOP OF BAR
MEASURE
TO BOTTOM
OF REFLECTIVE
SURFACE
3' - 0"
MAX
1' - 0"
T .O
B
A R
M
IN
NURSE CALL
& PULL CORD
NURSE CALL
& PULL CORD
NOTES:
1. OBJECTS WITH LEADING EDGES MORE THAN 27
INCHES AND NOT MORE THAN 80 INCHES ABOVE
THE FINISH FLOOR OR GROUND SHALL
PROTRUDE 4 INCHES MAXIMUM HORIZONTALLY
INTO THE CIRCULATION PATH. EXCEPTION:
HANDRAILS SHALL BE PERMITTED TO
PROTRUDE 4 1/2 INCHES MAXIMUM.
2. PROTRUDING OBJECTS SHALL NOT REDUCE THE
CLEAR WIDTH REQUIRED FOR ACCESSIBLE
ROUTES. ABA 307 PRTRUDING OBJECTS.
NOTES:
1. VERTICAL CLEARANCE SHALL BE 80 INCHES
HIGH MINIMUM. GUARDRAILS OR OTHER
BARRIERS SHALL BE PROVIDED WHERE THE
VERTICAL CLEARNACE IS LESS THAN 80 INCHES
HIGH. THE LEADING EDGE OF SUCH GUARDRAIL
OR BARRIER SHALL BE LOCATED 27 INCHES
MAXIMUM ABOVE THE FINISH FLOOR OR
GROUND. EXCEPTION: DOOR CLOSERS AND
DOOR STOPS SHALL BE PERMITTED TO BE 78
INCHES ABOVE THE FINISH FLOOR OR GROUND.
2. PROTRUDING OBJECTS SHALL NOT REDUCE THE
CLEAR WIDTH REQUIRED FOR ACCESSIBLE
ROUTES. ABA 307.4 VERTICAL CLEARANCE
(LIMITS OF PROTRUDING OBJECTS)
4" MAX.
M
IN
M
IN
M
A X
M
IN
(VERTICAL CLEARANCE)
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/3 2"
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/2
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
0"
Romanyk Consulting Focusing on what matters
VA FORM 08 - 6231
F
U.S. Department of Veterans Affairs
E
D
C
B
A
910 7 6 5 4 3 2 1
8910 7 6 5 4 3 2 1
NOT FOR
PERMITTING OR
CONSTRUCTION
E
D
C
B
A
F
Sprinklered
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
Romanyk Consulting Corp. www.romanykconsulting.com 3308 Preston Road, Suite 350-164, Plano, Texas 75093
Consultant:
Sprinklered
A/E
A ut od es k D oc s:
//V
IS
N
T am pa A
E
.5 T
M R
I I C
C /V
A J am es
A H al ey
.5
T M
R I_
A _R
-A
R C
H N
E W
.r vt
9/ 5/
:1
2:
A M
ACCESSIBILITY DETAILS
AW/GF/LN SE
90% PROGRESS SET 673-CSI-132
1.5T MRI ICC
James A. Haley VA Medical Center, Tampa, Florida
9/05/2025
James A. Haley VA
Medical Center, Tampa, Florida
VA: _______
01-GI103
SCALE: N.T.S.1
TURNING SPACE REQUIREMENTS
SCALE: 6" = 1'-0"
ACCESSIBLE ROUTE
SCALE: 3/8" = 1'-0"
TYPICAL MOUNTING HEIGHTS - ELECTRICAL
SCALE: 1/4" = 1'-0"
WHEEL CHAIR TURNING CLEARANCES
SCALE: N.T.S.4
WHEEL CHAIR ACCESSIBLE ROUTE
SCALE: 3/8" = 1'-0"
TYPICAL MOUNTING HEIGHTS - EGRESS DOOR HARDWARE
SCALE: N.T.S.6
SIGNAGE
Revisions: Rev: Date:
SCALE: N.T.S.8
LAVATORY CLEARANCE PLAN AND ELEVATION
SCALE: 1/4" = 1'-0"
ACCESSIBLE TOILETS, BATHS & SHOWERS
SCALE: 1/4" = 1'-0"
MOUNTING HEIGHTS
SCALE: 1/4" = 1'-0"
VERTICAL & PROTRUDING OBJECT CLEARANCES
A/C
A/C
M O T O R
GRILL
FRYER
OVEN
TOUNION
KETTLES
CONVECTION
OVEN
CONVECTION
CONVECTION
OVEN
CONVECTION
OVEN
PASS-THRU
D O
W N
UP
DOWN
DOWN
TO PIPE
BASEMENT
DOWN
DOWN UP
DOWN
UP
U P
U P
WHEEL CHAIR RAMP
WHEEL CHAIR RAMP
U P
D N
UP
DOWN
D N
UP
DN
DN
STAIRS
D O
W N
U P
D N
ROLL-UP DOOR
ROLL-UP DOOR
8" CONC. BLK.
8" CONC. BLK.
TO
CLG
CLOSED
OFF
CLOSED
OFF
DN
DN
R
S
T
17 18 19 20
U
Q
P
N.8
16.2161514.914131210987.1765.854.94.143.232.421
N
M
M.1
L
K
J
H
G
F
E
D
C.2
C
B
A
COMPUTER ROOM
GB-026
OFFICE IMS
GB-022
SYSTEMS
MANAGER
GB-025a
ASST.
SYSTEMS
MANAGER
GB-025
CORRIDOR
C0-03-1
OFFICE IMS
GB-024
OFFICE IMS
GB-023
STAIR #5
S0-05-1
OFFICE IMS
GB-024b
SIGNAL
GB-024c
POWER
GB-024d
STAIR #4
S0-04-1 OFFICE EMS
GB-034
OFFICE
STAFF
GB-030
OFFICE STAFF EMS
GB-030a
IMS
GB-029
CONFERENCE ROOM
GB-035 N&FS
GB-033
N&FS
GB-031
LINEN ROOM
GB-036
CORRIDOR
C0-01-1
C O
R R
ID
O
R
C 0-
-1
IMS
GB-027f
IMS
GB-027
UNIFORM EXCHANGE
GB-039
STO.
GB-038
OFFICE EMS
GB-039a
TELE
PHONE
GB-017
ELECTRICAL
GB-015
MECHANICAL
BB-001b
MECHANICAL
BB-001
TEMPORARY STO.
AB-6d
MECHANICAL
BB-001a
SERVICE ROOM
BA-023b
ELECTRICAL
ATS ROOM
AB-6b
ELECTRICAL
GA-023c
ELECTRICAL
GA-023d
RELEASE OF INFORMATION
GA-024
DOCTOR'S
WORKROOM
GA-027s
RR
GA-025
DOCTOR'S
WORKROOM
GA-027r
CORRIDOR
C0-05a-1
WAITING
GA-027a
PATIENT
RECORD
FILE ROOM
GA-027
WOMEN'S
RR
GA-027h
MEN'S
RR
GA-027h
PHYSICAL
THERAPY
TREATMENT
GA-013
MANUAL ARTS
THERAPY
GA-015
ELEC.
GE-002
MECH.
GE-001
EMERGENCY
ELEC.
GE-003
TELECOMMUNICATIONS
GE-004
SIGNAL
GE-005
STAIR #9
S0-09-1
LOBBY
GA-027t
STO.
GA-027w
O.T. ADMIN
GA-013a
O.T. ADMIN
GA-012a
O.T.
ADMIN
GA-014
OCUPATIONAL
THERAPY
GA-013a
OCCUPATIONAL
THERAPY
GA-012
POOL SERVICE ROOM
GA-011a
THERAPEUTIC
POOL
GA-011
EMPLOYEE
GYM
GA-004
M.A.T.
ADMIN.
GA-004a
STAFF
PHYSICIAN
GA-007
MEN'S RR
SHOWERS
AND
LOCKERS
GA-009
WOMEN'S
RR
SHOWERS
AND
LOCKERS
GA-011b
CARDIAC
REHABILITATION
GA-04b
C O
R R
ID
O
R
C 0-b-
CORRIDOR
C0-05c-1
ELEC.
GA-016
EDUCATIONAL
THERAPY
ADMIN.
GA-010
ADL CLINIC
GA-008
STAIR #2
S0-02-1
SECRETARY AND
WAITING PM&RS
GA-002
RESIDENT
PM&RS
GA-003
OFFICE
PM&RS
GA-005
OFFICE
PM&RS
GA-005a
EMG
GA-006a
OFFICE CHIEF
PM&RS
GA-006
OFFICE
PM&RS
GA-018
OFFICE
PM&RS
GD-040
CORRIDOR
C0-05-1
C O
R R
ID
O
R
C 0-d-
MANUAL
ARTS
OFFICE
CLERKS
GA-004
C O
R R
ID
O
R C
0-
-1
PROSTHETICS
STORAGE
GD-010
TELEPHONE
GD-010c
CORRIDOR
C0-09-1
CORRIDOR
C0-09a-1
CORRIDOR
C0-14-1
M E
C H
G B
-0 e
M E
C H
G B
-0 a
OFFICE IMS
GB-023
OFFICE IMS
GB-023b
MS CHIEF OFFICE
GB-027b
IMS
GB-027a
OFFICE IMS
GB-021a
PC REPAIR
GB-021
MECH
GB-021e
IMS
GB-020c
UNION OFFICE
GB-020UNION
OFFICE
GB-020a
C O
R R
ID
O
R
C 0-
-1
C O
R R
ID
O
R
C 0-b-
STO.
GB-020b
WOMEN'S
RR
GB-014 ELECTRICAL
GB-013
CORRIDOR
C0-01c-1
MECH.
GB-011
GB-010
SPD AMMS
GC-003
GC-003
G C
-0 03 C
O R
R
ID
O R
C 0-
-1
AB-6c
A/C &
REFRIGERATION/SHEET
METAL SHOP
BA-023a
CORRIDOR
C0-05-1
OLD GRAPHIC
CONTROL
GA-023
GA-019
ELECTRICAL
GA-021
MANUAL
ARTS
THERAPY
PM&RS
GA-004c
STORAGE
GA-004d
POLICE
GD-010a
PROSTHETICS
ASSISTANT
CHIEF
GD-0121
WOMEN'S RR
GD-009
MEN'S RR
GD-011
PROSTHETICS
GD-012a
PROSTHETICS
GD-012b
PROSTHETICS
GD-012c
PROSTHETICS
GD-012d
PROSTHETICS
GD-012
WOMEN'S
LOUNGE
GD-0123
WOMEN'S
LOCKERS
GD-013a
WOMEN'S RR
AND SHOWERS
GD-013c
GD-014 GD-014
MEN'S RR AND
SHOWERS
GD-015b
MEN'S
LOUNGE
GD-015
SAFETY
GD-017e
SAFETY
GD-017a
MEN'S
LOCKERS
GD-015a ELECTRONICS SHOP
GD-023e
WOMEN'S
LOCKERS
GD-013b
SAFETY
GD-017c
ELECTRONICS SHOP
GD-023d
ELECTRONICS
SHOP
GD-023c
ELECTRONIC
S SHOP
GD-023b
ELECTRONICS
SHOP
GD-023a
STAIR #8
S0-08-1
SAFETY
GD-017f SAFETY
GD-017
SAFETY
GD-017a
C O
R R
ID
O
R
C 0-
-1
SAFETY
GD-017b
BIOMED SHOP
GD-024
BIOMED SHOP
GD-022
BIOMED SHOP
GD-022a
C O
R R
ID
O
R
C 0-
-1
H.A.C.
GD-018
LAB
SPECTOMETER
GD-020
LAB
SPECTOMETER
GD-020a
CORRIDOR
C0-16-1
UNASSIGNED
GD-040
WOMEN'S
RR
GD-030
MEN'S
RR
GD-029
MORGUE
GD-026
ELECTRICAL
MORGUE
GD-026a
MORGUE
GD-031a MORGUE
GD-031 H
.A
.C
G D
-0
CREDIT
UNION
GD-032CREDIT
UNION
GD-033b
MORGUE
GD-027
MECHANICAL
GD-036
CREDIT
UNION
GD-033b
C O
R R
ID
O
R
C 0-
-1
BARBER SHOP
GD-036a
C O
R R
ID
O
R
C 0-
-1
ELECTRICAL
MEZZANINE
GD-036bC O
R R
ID
O
R
C 0-
-1
MEN'S RR
GD-034
C O
R R
ID
O
R
C 0-
-1
PROSTHETICS
GD-038d
PROSTHETICS
GD-038g
STAIR #1
S0-01-1
OFFICE N&FS
GD-037
FOOD
PRODUCTION
OFFICE
GD-007j
ELECTRICAL
GD-039
GD-035
PROSTHETICS
EXAM
GD-038c
PROSTHETICS
GD-038e
PROSTHETICS
WAITING
GD-038
PROSTHETICS
GD-038f
ELECTRICAL
OFFICE N&FS
GD-037c
OFFICE N&FS
GD-037a
DIETETIC
CLASSROOM
GD-037b
CANTEEN
VENDING
GD-008
PROSTHETICS
BRACE SHOP
GD-038b
N&FS OFFICE
GD-007t
N&FS OFFICE
GD-007u
MAIN KITCHEN
GD-007
ELEVATOR LOBBY
GD-001
ELEVATOR LOBBY
GD-002
C O
R R
ID
O
R
C 0-a-
GA-028
GD-007o
DISHWASHER
GD-007m
CART WASH
GA-019
H.A.C.
GA-020
RECEIVING &
DECONTAMINATION
GA-029
ELEVATOR
LOBBY
GD-030
ELECTRICAL
GD-003e
TRAY
CONVEYOR
GD-003d C O
R R
ID
O
R
C 0-a-
CART WASH
GD-007a
ASSEMBLY WORK
ROOM &
STERILATION
GD-003b
SPD AMMS
GC-003
SPD
GD-003a
H.A.C.
GC-006
FREEZER
GC-007w
FROZEN FOOD
HOLDING
GD-007e
DIETETICS
OFFICE
GC-001c
DIETETICS
OFFICE
GC-001b
C O
R R
ID
O
R
C 0-a-
REFRIGERATOR
GC-007v
MEAT
REFRIGERATOR
GD-007d
VEGETABLE
REFRIGERATOR
GD-007c
COOKS
REFRIGERATOR
GD-007b
DIETETICS
OFFICE
GC-001a ELECTRICAL
GC-005
FREEZER
GD-0017a
ELECTRICAL
GC-007a
KITCHEN
STORAGE
GC-007
INGREDIENT
CONTROL
GD-007f
GENERAL
STORAGE
GD-007p
DAIRY & EGG
REFRIGERATOR
GD-007g
PATIENT
LAUNDRY
GD-007
STAIR #3
S0-03-1
C O
R R
ID
O
R
C 0-
-1
CORRIDOR
C0-07a-1
CORRIDOR
C0-07b-1
OFFICE
PHARMACY
GC-008a
OFFICE
PHARMACY
GC-008b
OFFICE
PHARMACY
GC-008c
PHARMACY
OUT PATIENT
GC-008
ELECTRICAL
GC-008d
OFFICE
PHARMACY
GC-008f
MAIL ROOM
GC-008h
CHIEF SPD
GC-008i
MEDICAL
GASES
GC-009
MEDICAL
GASES
GD-010
OFFICE
WAREHOUSE
GC-004c
SILVER
RECOVERY
GC-004d
GC-011
REFRIGERATION
EQUIPMENT
GC-004b
OFFICES
WAREHOUSE
GC-004a
STAIR
S0-XX-1
LOADING
DOCK
TRASH COLLECTION
GC-012
GC-012a
BREAK AREA
GC-004
WAREHOUSE
GC-004
STAIR #7
S0-07-1
STAIR #12
S0-12-1
PROCESS
STORES
GC-004
WAREHOUSE
ADDITION
GC-004f
WAREHOUSE
STORAGE
GC-004
STAIR #6
S0-06-1
WAREHOUSE
STORAGE
GC-004e
REPRODUCTION
GC-008g
STAFF PHYSICIAN
GC-046
NON-PROF. NON-
PHYS.
GC-047
STAIR #20
S0-20-1
LINENS
GC-048
MECHANICAL
GC-050
EXAM
GC-023
S T
A
IR
S 0-
-1
MAGNETIC
TAPE
GC-049
LOBBY
GC-020
RECEPTION
GC-020 DRESS
GC-022A
DRESS
GC-022B
R T
U C
O R
R
ID
O R
CORRIDOR
C0-18-1
RESTROOM
GC-025
SCREENING
GC-024
ELEVATOR
#18
GURNEY
STAGE
GC-032 PREP
HOLD
GC-033
MACHINE
ROOM
GC-036
3T MRI
GC-027
OPEN MRI
GC-034
CONTROL
GC-035 CONTROL ROOM
GC-028
EQUIPMENT
ROOM
GC-028a
MECHANICAL
GC-028b
PLANTER
GI107
SIM.
GI107
GROUND FLOOR PLAN KEYNOTES
SITE ACCESS FOR CONTRACTOR PERSONNEL AND MATERIAL DELIVERY.1
CONTRACTOR BUILDING ACCESS.
CONTRACTOR ELEVATOR ACCESS.
CONTRACTOR TOILET - PROVIDE TEMPORARY SIGNAGE.
OVERALL PLAN LEGEND
SCOPE OF WORK AREA
NO SCOPE OF WORK AREA
TEMPORARILY REMOVE RAILING FOR MRI DELIVERY; REINSTALL TO MATCH EXISTING
CONDITIONS.
CONTRACTOR EQUIPMENT REPLACEMENT ACCESS PATH
NEW NON-RATED PARTITION
EXISTING PARTITION
EXISTING 2 HR FIRE PARTITION
EXISTING 1 HR FIRE PARTITION
NEW SMOKE PARTITION
EXISTING SMOKE PARTITION
VERTICAL CIRCULATION/ ELEVATOR
PLAN N
TRUE N
KEY PLAN
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/3 2"
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/2
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
0"
Romanyk Consulting Focusing on what matters
VA FORM 08 - 6231
F
U.S. Department of Veterans Affairs
E
D
C
B
A
910 7 6 5 4 3 2 1
8910 7 6 5 4 3 2 1
NOT FOR
PERMITTING OR
CONSTRUCTION
E
D
C
B
A
F
Sprinklered
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
Romanyk Consulting Corp. www.romanykconsulting.com 3308 Preston Road, Suite 350-164, Plano, Texas 75093
Consultant:
Sprinklered
A/E
A ut od es k D oc s:
//V
IS
N
T am pa A
E
.5 T
M R
I I C
C /V
A J am es
A H al ey
.5
T M
R I_
A _R
-A
R C
H N
E W
.r vt
9/ 5/
:1
2:
A M
GROUND FLOOR OVERALL PLAN
AW/GF/LN SE
90% PROGRESS SET 673-CSI-132
1.5T MRI ICC
James A. Haley VA Medical Center, Tampa, Florida
9/05/2025
James A. Haley VA
Medical Center, Tampa, Florida
VA: ________
01-GI105
SCALE: 1" = 20'-0"
GROUND FLOOR OVERALL PLAN
T
T
TT
T
T
T
UP
UP
UP
UP
UP
U P
DN
UP
UP
UP
UP
UP
U P
UP
UP
UP
UP
UP
T T
T
U P
A C
ID
T
A N
K
AC-17
E-12
R
S
T
17 18 19 20
U
Q
P
N.8
16.2161514.914131210987.1765.854.94.143.232.421
N
M
M.1
L
K
J
H
G
F
E
D
C.2
C
B
A
GI107
VCS STORAGE
CB-6F
VCS
STORAGE
CB-6G
VCS STORAGE
CB-6F
SIGN SHOP
CB-6H
ELEVATOR
#18
CB-6D
CB-6C
TOILET
CB-6B
CB-6A STAIR #20
SB-20-1
PAINT
STORAGE
AND MIX
CB-1
PLUMBING
STORAGE
CB-1C
ELECTRICAL
CB-1H
STORAGE
CB-1B
MECH AREA
CB-2
STAIR #6
SB-06-1
A/C
REFRIGERANT
STORAGE
CB-1A
ELECTRONIC
STORAGE
CB-1E
ELECTRONIC
STORAGE
CB-1E
BIOMED
CB-1G
BULK
MOTOR
STORAGE
CB-1P
BIOMED
STORAGE
PROJECT
WORK ROOM
CB-4B
MECHANICAL
CB-4
STAIR #7
SB-07-1
STAIR #12
SB-12-1
CARPENTRY
SHOP
STORAGE
CB-3D
BULK
MOTOR
STORAGE
CB-1P
CARPENTRY
SHOP STORAGE
CB-3C
STORAGE
CB-3A
MISC
ELECTRICAL
STORAGE
CB-3B
STAIR #3
SB-03-1
STAIR #3
SB-03-1
BOILER ROOM
BIOMED
STORAGE
THERAPEUTIC
POOL ABOVE
POOL SERVICE ROOM
STAIR #8
SB-08-1
S T
A
IR
S B
-0 9-
STAIR #2
SB-02-1
PARTS BINS & WORK TABLES
S T
A
IR
S B
-0 5-
STAIR #4
SB-04-1
WORK BENCHES
BASEMENT FLOOR PLAN KEYNOTES
CONTRACTOR BUILDING ACCESS.
CONTRACTOR BUILDING ACCESS TO ELEVATOR.
CONTRACTOR TOILET - PROVIDE TEMPORARY SIGNAGE.
OVERALL PLAN LEGEND
SCOPE OF WORK AREA
NO SCOPE OF WORK AREA
CONTRACTOR EQUIPMENT REPLACEMENT ACCESS PATH
NEW NON-RATED PARTITION
EXISTING PARTITION
EXISTING 2 HR FIRE PARTITION
EXISTING 1 HR FIRE PARTITION
NEW SMOKE PARTITION
EXISTING SMOKE PARTITION
VERTICAL CIRCULATION/ ELEVATOR
PLAN N
TRUE N
KEY PLAN
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/1 6"
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/3 2"
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
/8
0"
G ra p h ic S ca le
/2
0"
G ra p h ic S ca le
/4
0"
G ra p h ic S ca le
0"
Romanyk Consulting Focusing on what matters
VA FORM 08 - 6231
F
U.S. Department of Veterans Affairs
E
D
C
B
A
910 7 6 5 4 3 2 1
8910 7 6 5 4 3 2 1
NOT FOR
PERMITTING OR
CONSTRUCTION
E
D
C
B
A
F
Sprinklered
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
Romanyk Consulting Corp. www.romanykconsulting.com 3308 Preston Road, Suite 350-164, Plano, Texas 75093
Consultant:
Sprinklered
A/E
A ut od es k D oc s:
//V
IS
N
T am pa A
E
.5 T
M R
I I C
C /V
A J am es
A H al ey
.5
T M
R I_
A _R
-A
R C
H N
E W
.r vt
9/ 5/
:1
2:
A M
BASEMENT FLOOR OVERALL PLAN
AW/GF/LN SE
90% PROGRESS SET 673-CSI-132
1.5T MRI ICC
James A. Haley VA Medical Center, Tampa, Florida
9/05/2025
James A. Haley VA
Medical Center, Tampa, Florida
VA: _______
01-GI106
SCALE: 1" = 20'-0"
BASEMENT FLOOR OVERALL PLAN
D N
UP
DN
DN
DN
DN
R
S
T
U
Q
P
N.8
14131211
DRESSING
MRI SCANNER
EQUIPMENT ROOM
CONTROL ROOM
MRI COIL
STORAGE
CABINET
GB-010 OFFICE
PHARMACY
GC-008a
OFFICE
PHARMACY
GC-008b
ELECTRICAL
GC-008d
REPRODUCTION
GC-008g
STAFF PHYSICIAN
GC-046
NON-PROF. NON-
PHYS.
GC-047
STAIR #20
S0-20-1
LINENS
GC-048
MECHANICAL
GC-050
EXAM
GC-023
S T
A
IR
S 0-
-1
MAGNETIC
TAPE
GC-049
LOBBY
GC-020
RECEPTION
GC-020
DRESS
GC-022A
DRESS
GC-022B
R T
U C
O R
R
ID
O R
CORRIDOR
C0-18-1
RESTROOM
GC-025
SCREENING
GC-024ELEVATOR
#18
GURNEY
STAGE
GC-032
PREP
HOLD
GC-033
MACHINE
ROOM
GC-036
3T MRI
GC-027
OPEN MRI
GC-034
CONTROL
GC-035
CONTROL ROOM
GC-028
EQUIPMENT
ROOM
GC-028a
MECHANICAL
GC-028b
E T
D : 1
7" E
T D
: 1
5"
PLANTER
CPT: 97' - 10"
CPT: 99' - 6"
42"
M R
I S
A F
E
32"
C O
R R
ID
O
R L
E N
G T
H
6'-0" CLR MIN
C
LR
6'
ICRA PHASING / PROJECT MILESTONES
PHASE 1
1. MRI VENDOR SHOP DRAWINGS AND SHIELDING REPORT REVIEW AND COORDINATION.
2. GC SCHEDULE, SITE ACCESS (CONTRACTOR STAGING AREA, TOILET, ETC.) VERIFIED WITH COR.
3. ICRA PERMIT ISSUED.
PHASE 2 (GROUND FLOOR NEW MRI SCOPE AND DOOR / CORRIDOR RENOVATION FOR EXISTING MRI EQUIPMENT
REMOVAL / TRANSPORT)
PHASE 2.A (GROUND FLOOR NEW MRI SCOPE) CONTROL ROOM, SCAN ROOM, EQUIPMENT ROOM AND DRESSING
1. REMOVAL OF EXISTING VA PERSONNEL, COMPUTERS AND SMALL MEDICAL EQUIPMENT.
2. INSTALLATION OF TEMPORARY WALL AND CEILING ICRA BARRIERS PER PROJECT SCOPE. INCLUDING LIFE
SAFETY SIGNAGE, EGRESS AND PROTECTION OF EXISTING BUILDING AND FINISHES NOT IN SCOPE OF WORK.
REST OF THE FACILITY TO REMAIN FUNCTIONAL FOR PATIENTS, STAFF AND VISITORS. ALARM SYSTEMS, MECHANICAL, ELECTRICAL AND LIFE SAFETY FOR FACILITY TO REMAIN OPERATIONAL.
3. TEMPORARILY RELOCATE CONTROL ROOM AND DOOR TO ACCOMMODATE BARRIER FOR NEW CONTROL
ROOM WORK SCOPE.
PHASE 2.B (GROUND FLOOR EQUIPMENT TRANSPORTATION) CORRIDOR/DOOR ICRA BARRIERS AND OR HEPACART
FOR EQUIPMENT TRANSPORT
1. ICRA BARRIER(S) CEILING AND WALL AND OR HEPACART FOR DOOR ENLARGEMENT, RENOVATION. WORK TO BE DONE AT NIGHT OR WEEKENDS AND PHASED FOR THIS SCOPE. EGRESS TO REMAIN OPERATIONAL DURING
PATIENT, STAFF AND VISITOR HOSPITAL HOURS OF OPERATION.
PHASE 2.C BASEMENT (STRUCTURE AND MEP)
1. INSTALLATION OF TEMPORARY WALL AND CEILING ICRA BARRIERS PER PROJECT SCOPE. INCLUDING LIFE SAFETY SIGNAGE , EGRESS AND PROTECTION OF EXISTING BUILDING UTILITIES AND FINISHES NOT IN SCOPE OF WORK. REST OF THE FACILITLY TO REMAIN FUNTIONAL FOR PATIENTS, STAFF AND VISITORS. ALARM SYSTEMS, MECHANICAL, ELECTRICAL AND LIFE SAFETY FOR FACILITY TO REMAIN OPERATIONAL.
PHASE 3 (EXISTING MRI EQUIPMENT REMOVAL)
1. PHASE 2.B COMPLETED.
2. EXISTING MRI REMOVAL AT NIGHT OR WEEKEND, COORDINATE WITH COR.
PHASE 4 (DEMOLITION GROUND FLOOR AND BASEMENT)
1. DEMOLITION OF EXISTING GROUND FLOOR AREA IN SCOPE (PHASE 2A INCLUDING FINISHES, UTILITIES, ETC.)
TO PREPARE SPACE FOR NEW WORK SCOPE.
2. DEMOLITION OF EXISTING BASEMENT UTILITY SCOPE (PHASE 2C).
3. DEBRIS TO BE REMOVED AT NIGHT IN COVERED CONTAINERS, COORDINATE WITH COR.
PHASE 5 (GROUND FLOOR AND BASEMENT WORK SCOPE)
PHASE 5.A (GROUND FLOOR)
1. COORDINATION WITH NEW MEDICAL EQUIPMENT AND RF SHIELDING.
2. STUD FRAMING, NEW AND EXISTING UTILITIES, SPRINKLRS, ETC. ROUGHED-IN.
3. ABOVE CEILING DUCTS, CABLE TRAYS, EXHAUST TO THE OUTSIDE, ETC. COMPLETED AND TESTED.
4. GYPSUM BOARD WALLS COMPLETED AND SLAB PREPARED FOR NEW RF SHIELDING.
5. RF SHIELDING CONSTRUCTION AT WALLS, CONCEALED ABOVE CEILING, SLAB, MRI ANCHORAGE , EQUIPMENT
CEILING SUPPORT, QUENCHING AND VENTING, WINDOWS AND DOOR WITH INSPECTIONS DURING
CONSTRUCTION AND TESTING.
PHASE 5.B (BASEMENT)
1. STRUCTURE AND UTILITY WORK COMPLETED MEETING ALL FIRE RATED SLAB AND OR WALL
PENETRATIONS.
PHASE 5.C (UTILITIES GROUND FLOOR AND BASEMENT)
1. USE HEPACART TO TAKE ALL UTILITIES IN NEW AREA WORK SCOPE TO MECHANICAL, ELECTRICAL AND IT
ROOMS.
2. TESTING.
PHASE 6 (GROUND FLOOR MRI 1.5 AREA)
1. PROTECT INSTALLED RF SHIELDING.
2. INSTALLATION OF FINISHES, LIGHTS, LUMINOUS CEIING, DIFFUSERS, MILLWORK, ETC. INCLUDING TEMPORARY
EXPANSION OF BARRIERS AT NIGHT FOR WALL PAINTING IN COORIDORS AND INSTALLATION OF WALL GUARDS
AND CRASH BUMPERS.
3. PREPARE, CLEAN AND PROTECT SPACE FOR VA AND VENDOR MRI/EQUIPMENT.
4. REMOVE ICRA BARRIERS.
PHASE 7 (GROUND FLOOR EQUIPMENT INSTALLATION)
1. DELIVERY AND INSTALLATION OF VA VENDOR EQUIPMENT.
PHASE 8 (GROUND FLOOR EQUIPMENT TESTING)
1. COMPLETE COMMISSIONING AND TESTING OF ALL EQUIPMENT AND UTILITES.
PHASE 9
1. TRAINING, WARRANTIES AND RECORD DOCUMENTS TURNED OVER TO THE VA.
PHASE 10
1. TURN OVER SPACE TO THE FACILITY.
1. ISOLATE EXISTING HVAC SYSTEM IN AREAS WHERE WORK IS TO BE PERFORMED. ALL AIR VENTS MUST BE SEALED OFF AND UNDER NEGATIVE PRESSURE NEAR THE CONSTRUCTION AREA AS REQUIRED AFTER COORDINATION WITH COR TO ENSURE NON-INTERFERENCE WITH HVAC AND NEGATIVE PRESSURE SYSTEMS. DUST
TO BE CONTROLLED WITHIN THE WORK SITE FROM FLOOR TO DECK.
2. TRAFFIC CONTROL: DESIGNATED ENTRY AND EXIT PROCEDURES WILL BE DEFINED AND CLEARLY ARTICULATED WITH CONSTRUCTION SIGNAGE TO BE PROVIDED BY THE CONTRACTOR. ALL EGRESS WAYS MUST BE MAINTAINED FREE OF DEBRIS AT ALL TIMES. THEY MUST BE UTILIZED AT SCHEDULED TIMES ONLY AS COORDINATED WITH COR. DUST MATS MUST BE PLACED AT ENTRANCES/EXITS OF WORK AREA AND REPLACED DAILY OR MORE FREQUENTLY IF NECESSARY. DEBRIS WHEN TRANSPORTED THROUGH HOSPITAL AREAS MUST BE COMPLETELY TIGHTLY COVERED TO CONTAIN DUST DURING TRANSPORT. DEBRIS SHALL BE REMOVED IN EVENINGS OR NON-DUTY TIMES IF POSSIBLE. ALL CART WHEELS MUST BE CLEANED BEFORE LEAVING THE
CONSTRUCTION AREA.
3. CLEANING: THE CONSTRUCTION ZONE AND ADJACENT ENTRY AREA SHALL BE MAINTAINED IN A CLEAN AND SANITARY MANNER BY THE CONTRACTOR AND WILL BE HIGH EFFICIENCY PARTICULATE AIR (HEPA) VACUUMED AND WET MOPPED WITH DISINFECTANT DAILY OR MORE FREQUENTLY AS NEEDED TO MINIMIZE DUST GENERATION. CLOTHING SHALL BE FREE OF LOOSE SOIL AND DEBRIS UPON EXITING THE CONSTRUCTION ZONE.
4. CONTRACTOR TO OBTAIN INFECTION CONTROL PERMIT BEFORE CONSTRUCTION BEGINS.
5. STAGING AREAS WILL BE DESIGNATED BY THE COR. CONTRACTOR TO COORDINATE WITH THE COR PRIOR TO
CONSTRUCTION.
6. CONTRACTOR TO PROVIDE PROTECTION ABOVE CEILING WITHIN THE CONTAINMENT AREA, IF EXISTING WALLS
AND/OR PARTITIONS DO NOT EXTEND TO THE STRUCTURE ABOVE.
7. COORDINATE WITH OTHER ENGINEERING DISCIPLINES.
8. ICRA PLANS DENOTE TOTAL DEFINED AREAS OF WORK ON ALL AFFECTED LEVELS. THE VA MAY, BASED ON
DYNAMIC UNFORESEEN VARIABLES (PATIENT CENSUS, OTHER PROJECTS, ETC.), REQUIRE THE GENERAL CONTRACTOR TO MODIFY EXTENTS AND AREA SIZES OF ICRA BARRIERS. ANY SUCH MODIFICATION WILL REQUIRE THE SAME REQUISITE PROVISIONS REQUIRING CONTAINMENT AIR- PRESSURIZATION CRITERIA, AND
IDENTIFICATION AS NOTED ON INFECTION CONTROL RISK ASSESSMENT.
9. ANY EXCESSIVE NOISE PERCEIVED OUTSIDE THE CONSTRUCTION CONTAINMENT BARRIER ABOVE 85 DECIBELS
SHALL BE COORDINATED WITH COR.
10. ANYTHING THE COR HAS DEEMED EXCESSIVE OR DISRUPTIVE TO PATIENT CARE PROCEDURES. A PLAN OF ACTION WILL BE IMMEDIATELY PUT IN PLACE TO AVOID DISRUPTIONS TO THE CONSTRUCTION SCHEDULE.
ICRA KEYNOTES
TEMPORARY DUST CONTROL BARRIERS FOR DEMOLITION AND NEW CONSTRUCTION.
GC TO COORD. SCHEDULE AND HOURS OF DEMOLITION REMOVAL. REFER TO BARRIER SYSTEM DETAILS
ON SHEET 01-GI110.
ANTE ROOM. 2
USE HEPACART FOR DOOR AND UTILITY CONNECTIONS OUTSIDE OR BARRIER WORK SCOPE.3
ISOLATE HVAC SYSTEM, MAINTAIN NEGATIVE PRESSURE. 4
PROVIDE PROTECTION ABOVE CEILINGS IN CONTAINMENT AREA IF EXISTING WALLS AND PARTITIONS DO
NOT EXTEND TO THE STRUCTURE ABOVE CEILING. 5
MAINTAIN ACCESS TO ALL EXISTING BUILDINGS, UTILITIES AND FACILITIES WITHIN THE CONSTRUCTION
LIMITS SERVING THE MEDICAL CENTER. 6
TEMPORARILIY RELOCATE DOOR FOR NEW WORK SCOPE. 7
INFECTION CONTROL NOTES
1. THE LIFE SAFETY PLANS ARE "DIAGRAMMATIC ONLY" THEIR PURPOSE IS SOLELY TO REPRESENT THE LIFE SAFETY COMPONENTS FOR THE PROJECT. THE GENERAL CONTRACTOR SHALL USE THE CONSTRUCTION DOCUMENTS (NOT THE LIFESAFETY PLANS) FOR THE IMPLEMENTATION OF THE REQUIRED LIFE SAFETY
COMPONENTS INTO THE PROJECT.
LIFE SAFETY NOTES
NO SCOPE OF WORK AREA
LIFE SAFETY LEGEND
EXISTING 2 HR FIRE PARTITION
EXISTING 1 HR FIRE PARTITION
NEW SMOKE PARTITION
ICRA VESTIBULE WITH DUST COLLECTING
MATS
TEMPORARY DUST-PROOF BARRIER. INSTALL
MAGNETIC ACCESS DUST-PROOF DOOR
WHERE REQUIRED (USE ACCESS ZIPPER
DOOR WHERE REQUIRED BY I.C.R.A.)
EXISTING EXIT LIGHT
NEW NON-RATED PARTITION
EXISTING PARTITION
EGRESS WIDTH
FEC (FIRE EXTINGUISHER CABINET)
xx"
PROPOSED MRI TRAVEL & DELIVERY PATH
FEC
EXIT TRAVEL DISTANCE & COMMON
PATH OF TRAVEL
EXISTING SMOKE PARTITION
OCCUPANCY
MACHINE ROOM 235 SF / 300/PERSONS = 1 OCCUPANT
OPEN MRI ROOM 530 SF / 300/PERSONS = 2 OCCUPANTS
3T MRI ROOM 463 SF / 300/PERSONS = 2 OCCUPANTS
CONTROL ROOM 137 SF / 100/PERSONS = 3 OCCUPANTS
SCREENING ROOM 178 SF / 100/PERSONS = 2 OCCUPANTS
GURNEY ROOM 126 SF / 100/PERSONS = 2 OCCUPANTS
PREP HOLD 128 SF / 100/PERSONS = 2 OCCUPANTS
TOTAL (EXIST. FLOOR AREA) 14 OCCUPANTS
EQUIPMENT ROOM 124 SF / 300/PERSONS = 1 OCCUPANT
CONTROL ROOM 126 SF / 100/PERSONS = 3 OCCUPANTS PROVIDED
MRI SCANNER ROOM 618 SF / 300/PERSONS = 3 OCCUPANTS
DRESSING ROOM 67 SF / 300/PERSONS = 1 OCCUPANT
TOTAL (NEW FLOOR AREA) 8 OCCUPANTS
TOTAL EXIT OCCUPANT LOAD 22 OCCUPANTS
EXIT WIDTH PROVIDED 32 INCHES
EXIT CAPACITY UNIT ALLOWED 0.2 INCHES/OCCUPANT
TOTAL EXIT OCCUPANT SIZE PROVIDED 160 OCCUPANTS
EXISTING FLOOR AREA
NEW FLOOR AREA
SCOPE OF WORK AREA EXIT STAIRWELL/PASSAGEWAY
R
S
T
U
Q
P
N.8
1514.9141312
N
VCS STORAGE
CB-6F
VCS
STORAGE
CB-6G
VCS STORAGE
CB-6F
SIGN SHOP
CB-6H
ELEVATOR
#18
CB-6D
CB-6C
TOILET
CB-6B
CB-6A
STAIR #20
SB-20-1
PAINT
STORAGE
AND MIX
CB-1
PLUMBING
STORAGE
CB-1C
ELECTRICAL
CB-1H
STORAGE
CB-1B
A/C
REFRIGERANT
STORAGE
CB-1A
ELECTRONIC
STORAGE
CB-1E
CARPENTRY
SHOP
STORAGE
CB-3D
BULK
MOTOR
STORAGE
CB-1P
STORAGE
CB-3A
ETD: 134' - 0"
SCOPE OF WORK ON
GROUND FLOOR
(ABOVE)
PROJECT PHASING
PRE-CONSTRUCTION 1
1. GC SCHEDULE, SITE ACCESS, CONSTRUCTION FENCING AS REQUIRED (CONTRACTOR STAGING AREA, TOILET, ETC.) VERIFIED WITH COR.
CONSTRUCTION PART 1B
1. CORRIDOR WORK FOR NEW MRI TRANSPORTATION AT CMU WALLS FOR PERMANENT DOOR FRAME OPENING CHANGES. LIMITED HOURS AND
TEMPORARY ACCESS TO ADJACENT AREAS REQUIRED TO BE MAINTAINED.
PRE-CONSTRUCTION 2
1. REMOVAL OF EXISTING VA PERSONNEL, COMPUTER AND SMALL MEDICAL EQUIPMENT.
2. INSTALLATION OF TEMPORARY WALL AND CEILING ICRA BARRIERS PER PROJECT SCOPE. INCLUDING LIFE SAFETY SIGNAGE, EGRESS AND PROTECTION OF EXISTING
BUILDING AND FINISHES NOT IN SCOPE OF WORK. REST OF THE FACILITY TO REMAIN FUNCTIONAL FOR PATIENTS, STAFF AND VISITORS.