This document is a Testing Laboratory Services specification (Section 01 45 29) for the AE Site Prep for ED CT Replacement project at Bay Pines VAMC. The specification outlines comprehensive testing and inspection requirements for earthwork, concrete, reinforcement, and structural steel during construction. Key services include performing field density tests, concrete sampling and testing (including cylinder compression tests, slump tests, and air content tests), inspecting reinforcing steel placement, and conducting detailed structural steel weld and bolt inspections according to specific ASTM and AWS standards. The testing laboratory must be accredited by a laboratory accreditation authority and will be responsible for submitting detailed test reports to the Contracting Officer's Representative (COR), with special requirements for reporting any test failures or irregularities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24826Q0004 0005.pdf | ||
| WD-FL20260222 01-02-26.pdf | ||
| Guldmann_GH3_BayPines_VA_Submission_Package.pdf | ||
| 36C24826Q0004 0004.pdf | ||
| Base Offer Price Breakdown - 1 page.xlsx | XLSX spreadsheet | |
| 36C24826Q0004 0003.docx | DOCX document | |
| 516-CSI-142 - Bay Pines ED CT_ADD 1.pdf | ||
| 03 30 00-CAST-IN-PLACE CONCRETE.pdf | ||
| 36C24826Q0004 0002.docx | DOCX document | |
| RFI_516-CSI-142 Pre-Bid.docx | DOCX document | |
| PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| ED CT scanner site walk sign-in sheet 10-07-25.pdf | ||
| 36C24826Q0004 0001.docx | DOCX document | |
| 516-CSI-142_Bay Pines_ED CT_ Specs.pdf | ||
| VHA Infection Control Risk Assessment.pdf | ||
| 36C24826Q0004_1.docx | DOCX document | |
| EMR 1 page.pdf | ||
| WD-FL20250222 05-23-2025.pdf | ||
| 516-CSI-142_Bay Pines_ED CT_ Drawings.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
516-CSI-142
AE Site Prep for ED CT Replacement
Bay Pines VAMC
TESTING LABORATORY
SERVICES
01 45 29 - 1
SECTION 01 45 29
TESTING LABORATORY SERVICES
PART 1 - GENERAL
1.1 DESCRIPTION:
A. This section specifies materials testing activities and inspection services required during project construction to be provided by a Testing Laboratory retained by the General Contractor.
1.2 APPLICABLE PUBLICATIONS:
A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
B. American Society for Testing and Materials (ASTM):
A370-12 Standard Test Methods and Definitions for
Mechanical Testing of Steel Products
C31/C31M-10 Standard Practice for Making and Curing
Concrete Test Specimens in the Field
C33/C33M-11a Standard Specification for Concrete
Aggregates
C39/C39M-12 Standard Test Method for Compressive
Strength of Cylindrical Concrete Specimens
C109/C109M-11b Standard Test Method for Compressive
Strength of Hydraulic Cement Mortars
C136-06 Standard Test Method for Sieve Analysis of
Fine and Coarse Aggregates
C138/C138M-10b
Standard Test Method for Density (Unit
Weight), Yield, and Air Content (Gravimetric) of Concrete
C143/C143M-10a Standard Test Method for Slump of
Hydraulic Cement Concrete
C172/C172M-10 Standard Practice for Sampling Freshly
Mixed Concrete
C173/C173M-10b
Standard Test Method for Air Content of freshly Mixed Concrete by the Volumetric
Method
C1064/C1064M-11 Standard Test Method for Temperature of
Freshly Mixed Portland Cement Concrete
C1077-11c
Standard Practice for Agencies Testing
Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing
Agency Evaluation
01 45 29 - 2
D422-63(2007) Standard Test Method for Particle-Size
Analysis of Soils
D698-07e1
Standard Test Methods for Laboratory
Compaction Characteristics of Soil Using
Standard Effort
D1140-00(2006) Standard Test Methods for Amount of
Material in Soils Finer than No. 200 Sieve
D1188-07e1
Standard Test Method for Bulk Specific
Gravity and Density of Compacted
Bituminous Mixtures Using Coated Samples
D1556-07
Standard Test Method for Density and Unit
Weight of Soil in Place by the Sand-Cone
Method
D1557-09
Standard Test Methods for Laboratory
Compaction Characteristics of Soil Using
Modified Effort (56,000ft lbf/ft3 (2,700
KNm/m3))
D2166-06 Standard Test Method for Unconfined
Compressive Strength of Cohesive Soil
D2167-08
Standard Test Method for Density and Unit
Weight of Soil in Place by the Rubber
Balloon Method
D2216-10
Standard Test Methods for Laboratory
Determination of Water (Moisture) Content of Soil and Rock by Mass
D2974-07a
Standard Test Methods for Moisture, Ash, and Organic Matter of Peat and Other
Organic Soils
D3740-11
Standard Practice for Minimum
Requirements for Agencies Engaged in
Testing and/or Inspection of Soil and Rock as used in Engineering Design and
Construction
D6938-10
Standard Test Method for In-Place Density and Water Content of Soil and Soil-
Aggregate by Nuclear Methods (Shallow
Depth)
E94-04(2010) Standard Guide for Radiographic
Examination
E164-08 Standard Practice for Contact Ultrasonic
Testing of Weldments
E329-11c
Standard Specification for Agencies
Engaged in Construction Inspection, Testing, or Special Inspection
01 45 29 - 3
E543-09 Standard Specification for Agencies
Performing Non-Destructive Testing
E709-08 Standard Guide for Magnetic Particle
Examination
E1155-96(R2008) Determining FF Floor Flatness and FL Floor
Levelness Numbers
F3125/F3125M-15
Standard Specification for High Strength
Structural Bolts, Steel and Alloy Steel, Heat
Treated, 120 ksi (830 MPa) and 150 ksi
(1040 MPa) Minimum Tensile Strength, Inch and Metric Dimensions
C. American Welding Society (AWS):
D1.D1.1M-10 Structural Welding Code-Steel
1.3 REQUIREMENTS:
A. Accreditation Requirements: Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory’s scope of accreditation must include the appropriate ASTM standards (i.e.; E329, C1077, D3666, D3740, A880, E543) listed in the technical sections of the specifications. Laboratories engaged in Hazardous Materials Testing shall meet the requirements of OSHA and EPA. The policy applies to the specific laboratory performing the actual testing, not just the “Corporate Office.”
B. Inspection and Testing: Testing laboratory shall inspect materials and workmanship and perform tests described herein and additional tests requested by COR. When it appears materials furnished, or work performed by Contractor fail to meet construction contract requirements, Testing Laboratory shall direct attention of COR to such failure.
C. Written Reports: Testing laboratory shall submit test reports to COR, Contractor, unless other arrangements are agreed to in writing by the COR. Submit reports of tests that fail to meet construction contract requirements on colored paper.
D. Verbal Reports: Give verbal notification to COR immediately of any irregularity.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 EARTHWORK:
A. General: The Testing Laboratory shall provide qualified personnel, materials, equipment, and transportation as required to perform the services identified/required herein, within the agreed to schedule and/or time frame. The work to be performed shall be as identified herein and shall include but not be limited to the following:
1. Observe fill and subgrades during proof-rolling to evaluate suitability of surface material to receive fill or base course. Provide recommendations to the COR regarding suitability or unsuitability of areas where proof-rolling was observed. Where unsuitable results are observed, witness excavation of unsuitable material and recommend to COR extent of removal and replacement of unsuitable materials and observe proof-rolling of replaced areas until satisfactory results are obtained.
2. Provide part time observation of fill placement and compaction and field density testing in building areas and provide part time observation of fill placement and compaction and field density testing in pavement areas to verify that earthwork compaction obtained is in accordance with contract documents.
3. Provide supervised geotechnical technician to inspect excavation, subsurface preparation, and backfill for structural fill.
01 45 29 - 4
B. Testing Compaction:
1. Determine maximum density and optimum moisture content for each type of fill, backfill and subgrade material used, in compliance with ASTM D1557.
2. Make field density tests in accordance with the primary testing method following ASTM D6938 wherever possible. Field density tests utilizing ASTM D1556 or ASTM D2167 shall be utilized on a case by case basis only if there are problems with the validity of the results from the primary method due to specific site field conditions. Should the testing laboratory propose these alternative methods, they should provide satisfactory explanation to the COR before the tests are conducted.
a. Building Slab Subgrade: At least one test of subgrade for every 185 m2 (2000 square feet) of building slab, but in no case fewer than three tests. In each compacted fill layer, perform one test for every 185 m2 (2000 square feet) of overlaying building slab, but in no case fewer than three tests.
C. Fill and Backfill Material Gradation: One test per 500 cubicyards stockpiled or in-place source material. Gradation of fill and backfill material shall be determined in accordance with ASTM C136.
D. Testing Materials: Test suitability of on-site and off-site borrow as directed by COR.
3.2 CONCRETE:
A. Batch Plant Inspection and Materials Testing:
1. Perform continuous batch plant inspection until concrete quality is established to satisfaction of COR with concurrence of Contracting Officer and perform periodic inspections thereafter as determined by COR.
2. Periodically inspect and test batch proportioning equipment for accuracy and report deficiencies to COR.
3. Sample and test mix ingredients as necessary to insure compliance with specifications.
4. Sample and test aggregates daily and as necessary for moisture content. Test the dry rodded weight of the coarse aggregate whenever a sieve analysis is made, and when it appears there has been a change in the aggregate.
5. Certify, in duplicate, ingredients and proportions and amounts of ingredients in concrete conform to approved trial mixes. When concrete is batched or mixed off immediate building site, certify (by signing, initialing or stamping thereon) on delivery slips (duplicate) that ingredients in truck-load mixes conform to proportions of aggregate weight, cement factor, and water-cement ratio of approved trial mixes.
B. Field Inspection and Materials Testing:
1. Provide a technician at site of placement at all times to perform concrete sampling and testing.
2. Review the delivery tickets of the ready-mix concrete trucks arriving on-site. Notify the Contractor if the concrete cannot be placed within the specified time limits or if the type of concrete delivered is incorrect. Reject any loads that do not comply with the Specification requirements. Rejected loads are to be removed from the site at the Contractor’s expense.
Any rejected concrete that is placed will be subject to removal.
3. Take concrete samples at point of placement in accordance with ASTM C172. Mold and cure compression test cylinders in accordance with ASTM C31. Make at least five cylinders for each 40 m3 (50 cubic yards) or less of each concrete type, and at least three cylinders for any one day's pour for each concrete type. After good concrete quality control has been established and maintained as determined by COR make five cylinders for each 80 m3 (100 cubic yards) or less of each concrete type, and at least five cylinders from any one day's pour for each concrete type. Label each cylinder with an identification number. COR may require additional cylinders to be molded and cured under job conditions.
4. Perform slump tests in accordance with ASTM C143. Test the first truck each day, and every time test cylinders are made. Test pumped concrete at the hopper and at the
01 45 29 - 5 discharge end of the hose at the beginning of each day’s pumping operations to determine change in slump.
5. Determine the air content of concrete per ASTM C173. For concrete required to be air-entrained, test the first truck and every 20 m3 (25 cubic yards) thereafter each day. For concrete not required to be air-entrained, test every 80 m3 (100 cubic yards) at random.
For pumped concrete, initially test concrete at both the hopper and the discharge end of the hose to determine change in air content.
6. If slump or air content fall outside specified limits, make another test immediately from another portion of same batch.
7. Perform unit weight tests in compliance with ASTM C138 for normal weight concrete. Test the first truck and each time cylinders are made.
8. Notify laboratory technician at batch plant of mix irregularities and request materials and proportioning check.
9. Verify that specified mixing has been accomplished.
10. Environmental Conditions: Determine the temperature per ASTM C1064 for each truckload of concrete during hot weather and cold weather concreting operations:
a. When ambient air temperature falls below 4.4 degrees C (40 degrees F), record maximum and minimum air temperatures in each 24 hour period; record air temperature inside protective enclosure; record minimum temperature of surface of hardened concrete.
b. When ambient air temperature rises above 29.4 degrees C (85 degrees F), record maximum and minimum air temperature in each 24 hour period; record minimum relative humidity; record maximum wind velocity; record maximum temperature of surface of hardened concrete.
11. Inspect the reinforcing steel placement, including bar size, bar spacing, top and bottom concrete cover, proper tie into the chairs, and grade of steel prior to concrete placement.
Submit detailed report of observations.
12. Observe conveying, placement, and consolidation of concrete for conformance to specifications.
13. Observe condition of formed surfaces upon removal of formwork prior to repair of surface defects and observe repair of surface defects.
14. Observe curing procedures for conformance with specifications, record dates of concrete placement, start of preliminary curing, start of final curing, end of curing period.
15. Observe preparations for placement of concrete:
a. Inspect handling, conveying, and placing equipment, inspect vibrating and compaction equipment.
b. Inspect preparation of construction, expansion, and isolation joints.
16. Observe preparations for protection from hot weather, cold weather, sun, and rain, and preparations for curing.
17. Observe concrete mixing:
a. Monitor and record amount of water added at project site.
b. Observe minimum and maximum mixing times.
18. Measure concrete flatwork for levelness and flatness as follows:
a. Perform Floor Tolerance Measurements FF and FL in accordance with ASTM E1155.
Calculate the actual overall F- numbers using the inferior/superior area method.
b. Perform all floor tolerance measurements within 48 hours after slab installation and prior to removal of shoring and formwork.
c. Provide the Contractor and the COR with the results of all profile tests, including a running tabulation of the overall FF and FL values for all slabs installed to date, within 72 hours after each slab installation.
19. Other inspections:
a. Grouting under base plates.
b. Grouting anchor bolts and reinforcing steel in hardened concrete.
C. Laboratory Tests of Field Samples:
01 45 29 - 6
1. Test compression test cylinders for strength in accordance with ASTM C39. For each test series, test one cylinder at 7 days and three cylinder at 28 days. Use remaining cylinder as a spare tested as directed by COR. Compile laboratory test reports as follows:
Compressive strength test shall be result of three cylinder, except when one cylinder shows evidence of improper sampling, molding or testing, in which case it shall be discarded and strength of spare cylinder shall be used.
2. Furnish certified compression test reports (duplicate) to COR. In test report, indicate the following information:
a. Cylinder identification number and date cast.
b. Specific location at which test samples were taken.
c. Type of concrete, slump, and percent air.
d. Compressive strength of concrete in MPa (psi).
e. Weather conditions during placing.
f. Temperature of concrete in each test cylinder when test cylinder was molded.
g. Maximum and minimum ambient temperature during placing.
h. Ambient temperature when concrete sample in test cylinder was taken.
i. Date delivered to laboratory and date tested.
3.3 REINFORCEMENT:
A. Review mill test reports furnished by Contractor.
B. Written report shall include, in addition to test results, heat number, manufacturer, type and grade of steel, and bar size.
3.4 STRUCTURAL STEEL:
A. General: Provide shop and field inspection and testing services to certify structural steel work is done in accordance with contract documents. Welding shall conform to AWS D1.1 Structural Welding Code.
B. Prefabrication Inspection:
1. Review design and shop detail drawings for size, length, type and location of all welds to be made.
2. Approve welding procedure qualifications either by pre-qualification or by witnessing qualifications tests.
3. Approve welder qualifications by certification or retesting.
4. Approve procedure for control of distortion and shrinkage stresses.
5. Approve procedures for welding in accordance with applicable sections of AWS D1.1.
C. Fabrication and Erection:
1. Weld Inspection:
a. Inspect welding equipment for capacity, maintenance and working condition.
b. Verify specified electrodes and handling and storage of electrodes in accordance with
AWS D1.1.
c. Inspect preparation and assembly of materials to be welded for conformance with
AWS D1.1.
d. Inspect preheating and interpass temperatures for conformance with AWS D1.1.
e. Measure 25 percent of fillet welds.
f. Welding Magnetic Particle Testing: Test in accordance with ASTM E709 for a minimum of:
1) 20 percent of all shear plate fillet welds at random, final pass only.
2) 20 percent of all continuity plate and bracing gusset plate fillet welds, at random, final pass only.
3) 100 percent of tension member fillet welds (i.e., hanger connection plates and other similar connections) for root and final passes.
4) 20 percent of length of built-up column member partial penetration and fillet welds at random for root and final passes.
01 45 29 - 7
5) 100 percent of length of built-up girder member partial penetration and fillet welds for root and final passes.
g. Welding Ultrasonic Testing: Test in accordance with ASTM E164 and AWS D1.1 for 100 percent of all full penetration welds, braced and moment frame column splices, and a minimum of 20 percent of all other partial penetration column splices, at random.
h. Welding Radiographic Testing: Test in accordance with ASTM E94, and AWS D1.1 for 5 percent of all full penetration welds at random.
i. Verify that correction of rejected welds are made in accordance with AWS D1.1.
j. Testing and inspection do not relieve the Contractor of the responsibility for providing materials and fabrication procedures in compliance with the specified requirements.
2. Bolt Inspection:
a. Inspect high-strength bolted connections in accordance AISC Specifications for Structural Joints Using ASTM F3125 Bolts.
b. Slip-Critical Connections: Inspect 10 percent of bolts, but not less than 2 bolts, selected at random in each connection in accordance with AISC Specifications for Structural Joints Using ASTM F3125 Bolts. Inspect all bolts in connection when one or more are rejected.
c. Fully Pre-tensioned Connections: Inspect 10 percent of bolts, but not less than 2 bolts, selected at random in 25 percent of connections in accordance with AISC Specification for Structural Joints Using ASTM F3125 Bolts. Inspect all bolts in connection when one or more are rejected.
d. Bolts installed by turn-of-nut tightening may be inspected with calibrated wrench when visual inspection was not performed during tightening.
e. Snug Tight Connections: Inspect 10 percent of connections verifying that plies of connected elements have been brought into snug contact.
f. Inspect field erected assemblies; verify locations of structural steel for plumbness, level, and alignment.
D. Submit inspection reports, record of welders and their certification, and identification, and instances of noncompliance to COR.
3.5 TYPE OF TEST:
Approximate Number of Tests Required
A. Earthwork:
Field Density, Soils (ASTM D6398)
B. Concrete:
Making and Curing Concrete Test Cylinders (ASTM C31)
Compressive Strength, Test Cylinders (ASTM C39)
Concrete Slump Test (ASTM C143)
Concrete Air Content Test (ASTM C173)
Aggregate, Normal Weight: Gradation (ASTM C33)
Deleterious Substances (ASTM C33)
Soundness (ASTM C33)
Abrasion (ASTM C33)
Deleterious Substances (ASTM C330)
01 45 29 - 8
Unit Weight (ASTM C330)
Flatness and Levelness Readings (ASTM E1155) (number of days)
END OF SECTION